by SHREEJI INFRA GROUP · Dombivali, Thane 421204Also near Kole, Bhiwandi, VidyashramRegistered on MahaRERA as “KUBER HEIGHTS”

What’s in the report? →

Possession date of Shreeji Kuber Heights (MahaRERA P51700047224): 30 April 2027, moved from 31 December 2024 (24 months later). It has 28 homes, 24% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700047224, and currently active. Its completion date has moved from December 2024 to April 2027: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51700047224, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Shreeji Kuber Heights?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Shreeji Kuber Heights has moved

  1. 31 December 2024

    Completion date given when the project was registered

  2. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51700026056)

    Reason the builder gave MahaRERA:
    “• The real estate industry went through multiple challenges over the pandemic years with supply chain disruption, labour crisis, and budget crunch slowing down growth. • We would like to inform you that due to a change in the project plan a…” Read the full reason“• The real estate industry went through multiple challenges over the pandemic years with supply chain disruption, labour crisis, and budget crunch slowing down growth. • We would like to inform you that due to a change in the project plan and an increase in the construction area, it became necessary to obtain approval from the local authorities, which resulted in a considerable time lapse. The revised plan has also necessitated modifications to the construction activities, leading to additional time requirements. Consequently, the delay in obtaining approvals and the subsequent changes in c…”
  3. 31 December 2026

    Extended at the builder's request (MahaRERA application EA27012619585)

    Reason the builder gave MahaRERA:
    “a) During the pandemic years, the industry faced severe supply chain disruptions, labour shortages, liquidity constraints, and slowdown in construction activities, which adversely affected the project timeline. b) Due to a change in the pro…” Read the full reason“a) During the pandemic years, the industry faced severe supply chain disruptions, labour shortages, liquidity constraints, and slowdown in construction activities, which adversely affected the project timeline. b) Due to a change in the project plan and an increase in the construction area, it became necessary to obtain revised approvals from the local authorities. The approval process consumed considerable time, and the revised plan also required modifications in construction methodology, resulting in further delay in execution. c) The project has progressed substantially, with approximate…”
  4. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Shreeji Kuber Heights’s extension records on MahaRERA (P51700047224), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Shreeji Kuber Heights

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700047224
Status
Registered and active
Builder
SHREEJI INFRA GROUP
Location
Dombivali, Thane · 421204
Project type
Residential / Group Housing
Registered on
12 Oct 2022
Completion date at registration
December 2024
Latest completion date
April 2027
Delay so far
24 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
28
Sold or booked
24%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Shreeji Kuber Heights, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Building No 1100%100%100%95%

Commencement certificate (CC), as filed on MahaRERA

  • Building No 1: covers Ground Floor+7 Habitable Floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shreeji Kuber Heights every 1–2 months.

Shreeji Kuber Heights: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Vatsalya Developer (a group of 2 linked companies) has 2 projects on MahaRERA since 2022, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 18 months late). No complaints on MahaRERA.

Read Google reviews of Shreeji Kuber Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Shreeji Kuber Heights: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Shreeji Kuber Heights

What is the possession date of Shreeji Kuber Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shreeji Kuber Heights in Dombivali, Thane is 30 April 2027 — 24 months later than 31 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 24 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Shreeji Kuber Heights?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Shreeji Kuber Heights's builder has filed on MahaRERA, the official one, is 30 April 2027, already 24 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Shreeji Kuber Heights extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji Kuber Heights's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2025, giving the reason "• The real estate industry went through multiple challenges over the pandemic years with supply chain disruption, labour crisis, and budget crunch slowing down growth. • We would like to inform you that due to a change in the project plan and an increase in the construction area, it became necessary to obtain approval from the local authorities, which resulted in a considerable time lapse. The revised plan has also necessitated modifications to the construction activities, leading to additional time requirements. Consequently, the delay in obtaining approvals and the subsequent changes in c…"; to 31 December 2026, giving the reason "a) During the pandemic years, the industry faced severe supply chain disruptions, labour shortages, liquidity constraints, and slowdown in construction activities, which adversely affected the project timeline. b) Due to a change in the project plan and an increase in the construction area, it became necessary to obtain revised approvals from the local authorities. The approval process consumed considerable time, and the revised plan also required modifications in construction methodology, resulting in further delay in execution. c) The project has progressed substantially, with approximate…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Shreeji Kuber Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shreeji Kuber Heights in Dombivali, Thane is P51700047224.

Is Shreeji Kuber Heights registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji Kuber Heights is registered as P51700047224 and its status is "Registered and active".

What is the current construction status of Shreeji Kuber Heights? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji Kuber Heights's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Building No 1 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Shreeji Kuber Heights have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Shreeji Kuber Heights safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji Kuber Heights is registered on MahaRERA as P51700047224, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Shreeji Kuber Heights?

Shreeji Kuber Heights is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Shreeji Kuber Heights?

For a flat in Shreeji Kuber Heights (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Shreeji Kuber Heights received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji Kuber Heights is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Shreeji Kuber Heights a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji Kuber Heights's planning authority on MahaRERA is Mumbai Metropolitan Region Development Authority, not the Slum Rehabilitation Authority, so it isn't an SRA scheme, and no flats are filed as rehab flats for existing occupants.

Has Shreeji Kuber Heights uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Shreeji Kuber Heights was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Shreeji Kuber Heights's possession date changes?

The latest dates are on Shreeji Kuber Heights's MahaRERA page (P51700047224). GharKundli's Kundli Watch sends a free WhatsApp update on Shreeji Kuber Heights every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Shreeji Kuber Heights have?

According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji Kuber Heights has one building filed: Building No 1 with 8 floors and 34 units.

How much parking does Shreeji Kuber Heights have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 14 open car parking spaces for Shreeji Kuber Heights.

How big is the land of Shreeji Kuber Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji Kuber Heights stands on 1,000 sq m of land (about 0.2 acres), with 1,531 sq m of sanctioned built-up area.

What is the track record of Shreeji Kuber Heights's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Vatsalya Developer (a group of 2 linked companies) has 2 projects on MahaRERA since 2022, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 18 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Shreeji Kuber Heights?

Google Maps has reviews of Shreeji Kuber Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Shreeji Kuber Heights?

Shreeji Kuber Heights by SHREEJI INFRA GROUP is in Dombivali, Thane, pincode 421204 (near Kole, Bhiwandi, Vidyashram), Maharashtra, and is registered on MahaRERA as P51700047224, per GharKundli's check of MahaRERA records. Its land is filed as 68/2. GharKundli lists all 252 MahaRERA projects in Manpada (421204).

How many flats are in Shreeji Kuber Heights, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji Kuber Heights has 28 homes in 1 tower registered on MahaRERA, and 24% of them are sold or booked.

When was Shreeji Kuber Heights registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji Kuber Heights was registered on MahaRERA on 12 October 2022. GharKundli did not find a title report on the land on file there.

Does Shreeji Kuber Heights have any legal issues or court cases?

No court cases are listed for Shreeji Kuber Heights on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Shreeji Kuber Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREEJI INFRA GROUP.

All projects with possession due in 2027 in Thane →

Other projects in Manpada (421204)

All 252 projects in Manpada (421204) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.