Sai Siddhi Residency
by DEVENDRA DAMODAR PATIL · Dombivali, Thane 421204Also near Borivali West, Bhiwandi
What’s in the report? →Possession date of Sai Siddhi Residency (MahaRERA P51700046244): 30 January 2027, moved from 31 December 2024 (21 months later). It has 30 homes, 57% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700046244, and currently active. Its completion date has moved from December 2024 to January 2027: 21 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700046244, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Sai Siddhi Residency?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Sai Siddhi Residency has moved
31 December 2024
Completion date given when the project was registered
31 December 2025
Extended at the builder's request (MahaRERA application EXT51700025926)
Reason the builder gave MahaRERA:
“Shortage of Funds due to low demand The real estate project, situated in a remote area, has faced significant challenges due to limited customer bookings, resulting in a lower-than-anticipated response from prospective buyers. This lack of…” Read the full reason
“Shortage of Funds due to low demand The real estate project, situated in a remote area, has faced significant challenges due to limited customer bookings, resulting in a lower-than-anticipated response from prospective buyers. This lack of adequate buyer interest adversely impacted the financial inflow required for the timely completion of the project, as the anticipated funding from customer bookings could not be realized. Despite these challenges, the promoters have demonstrated unwavering commitment to the project's completion by arranging the necessary funds through the liquidation of p…”30 September 2026
Extended at the builder's request (MahaRERA application EA17022619877)
Reason the builder gave MahaRERA:
“Shortage of Funds due to low demand: The real estate project, situated in a remote area, has faced significant challenges due to limited customer bookings, resulting in a lower-than-anticipated response from prospective buyers. This lack of…” Read the full reason
“Shortage of Funds due to low demand: The real estate project, situated in a remote area, has faced significant challenges due to limited customer bookings, resulting in a lower-than-anticipated response from prospective buyers. This lack of adequate buyer interest adversely impacted the financial inflow required for the timely completion of the project, as the anticipated funding from customer bookings could not be realized. Despite these challenges, the promoters have demonstrated unwavering commitment to the project's completion by arranging the necessary funds through the liquidation of…”30 January 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Sai Siddhi Residency’s extension records on MahaRERA (P51700046244), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Sai Siddhi Residency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the January 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- SAI SIDDHI RESIDENCYP51700018663 · possession 30 Mar 2023
- MahaRERA registration
- P51700046244
- Status
- Registered and active
- Builder
- DEVENDRA DAMODAR PATIL
- Location
- Dombivali, Thane · 421204
- Project type
- Residential / Group Housing
- Registered on
- 20 Jun 2022
- Completion date at registration
- December 2024
- Latest completion date
- January 2027
- Delay so far
- 21 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 30
- Sold or booked
- 57%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Sai Siddhi Residency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Sai Siddhi Residency B Wing | 100% | 100% | 70% | 30% |
Commencement certificate (CC), as filed on MahaRERA
- Sai Siddhi Residency B Wing: covers 8 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sai Siddhi Residency every 1–2 months.
Sai Siddhi Residency: buildings, flats and land, as filed on MahaRERA
- Buildings: Sai Siddhi Residency B Wing (8 floors, 30 units)
- Car parking: 9 covered
- Land: 850 sq m (about 0.2 acres) · sanctioned built-up 2,329 sq m
- Land, as filed: SURVEY NO 11, HISSA NO 2/1, 3/2/1,
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Devendra Damodar Patil (a group of 2 linked companies) has 2 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 18 months late). No complaints on MahaRERA.
Read Google reviews of Sai Siddhi Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Sai Siddhi Residency: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Sai Siddhi Residency
What is the possession date of Sai Siddhi Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sai Siddhi Residency in Dombivali, Thane is 30 January 2027 — 21 months later than 31 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 21 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Sai Siddhi Residency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Sai Siddhi Residency's builder has filed on MahaRERA, the official one, is 30 January 2027, already 21 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Sai Siddhi Residency extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Siddhi Residency's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2025, giving the reason "Shortage of Funds due to low demand The real estate project, situated in a remote area, has faced significant challenges due to limited customer bookings, resulting in a lower-than-anticipated response from prospective buyers. This lack of adequate buyer interest adversely impacted the financial inflow required for the timely completion of the project, as the anticipated funding from customer bookings could not be realized. Despite these challenges, the promoters have demonstrated unwavering commitment to the project's completion by arranging the necessary funds through the liquidation of p…"; to 30 September 2026, giving the reason "Shortage of Funds due to low demand: The real estate project, situated in a remote area, has faced significant challenges due to limited customer bookings, resulting in a lower-than-anticipated response from prospective buyers. This lack of adequate buyer interest adversely impacted the financial inflow required for the timely completion of the project, as the anticipated funding from customer bookings could not be realized. Despite these challenges, the promoters have demonstrated unwavering commitment to the project's completion by arranging the necessary funds through the liquidation of…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Sai Siddhi Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sai Siddhi Residency in Dombivali, Thane is P51700046244.
Is Sai Siddhi Residency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Siddhi Residency is registered as P51700046244 and its status is "Registered and active".
What is the current construction status of Sai Siddhi Residency? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Siddhi Residency's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Sai Siddhi Residency B Wing is 100% done and internal work 70%. GharKundli's full report compares construction progress with the deadline.
Does Sai Siddhi Residency have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Sai Siddhi Residency safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Siddhi Residency is registered on MahaRERA as P51700046244, its completion date has moved 21 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Sai Siddhi Residency?
Sai Siddhi Residency is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Sai Siddhi Residency?
For a flat in Sai Siddhi Residency (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Sai Siddhi Residency received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Sai Siddhi Residency is still under construction, with 30 January 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Sai Siddhi Residency uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Sai Siddhi Residency was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
Does Sai Siddhi Residency have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: SAI SIDDHI RESIDENCY (P51700018663, possession 30 Mar 2023). Check that your agreement names the registration of your own wing.
How can I get updates if Sai Siddhi Residency's possession date changes?
The latest dates are on Sai Siddhi Residency's MahaRERA page (P51700046244). GharKundli's Kundli Watch sends a free WhatsApp update on Sai Siddhi Residency every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Sai Siddhi Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Siddhi Residency has one building filed: Sai Siddhi Residency B Wing with 8 floors and 30 units.
How much parking does Sai Siddhi Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 9 covered car parking spaces for Sai Siddhi Residency.
How big is the land of Sai Siddhi Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Siddhi Residency stands on 850 sq m of land (about 0.2 acres), with 2,329 sq m of sanctioned built-up area.
What is the track record of Sai Siddhi Residency's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Devendra Damodar Patil (a group of 2 linked companies) has 2 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 18 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Sai Siddhi Residency?
Google Maps has reviews of Sai Siddhi Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Sai Siddhi Residency?
Sai Siddhi Residency by DEVENDRA DAMODAR PATIL is in Dombivali, Thane, pincode 421204 (near Borivali West, Bhiwandi), Maharashtra, and is registered on MahaRERA as P51700046244, per GharKundli's check of MahaRERA records. Its land is filed as SURVEY NO 11, HISSA NO 2/1, 3/2/1,. GharKundli lists all 252 MahaRERA projects in Manpada (421204).
How many flats are in Sai Siddhi Residency, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Siddhi Residency has 30 homes in 1 tower registered on MahaRERA, and 57% of them are sold or booked.
When was Sai Siddhi Residency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Siddhi Residency was registered on MahaRERA on 20 June 2022. GharKundli did not find a title report on the land on file there.
Does Sai Siddhi Residency have any legal issues or court cases?
No court cases are listed for Sai Siddhi Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Sai Siddhi Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is DEVENDRA DAMODAR PATIL, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Sai Siddhi Residency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Manpada (421204)
- Empress Royal Efgh
- Empress Dreams
- Kuber Heights
- Naivedya
- Regency Sapphire
- Samruddhi CHS LTD
- Vinayak Exotica 9
- Dynamic Crest Phase I - Rimo/everest
Other projects by DEVENDRA DAMODAR PATIL
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.