Akshay

by Mahendra Purushottam Tank · Chikhali (Deosthan), NagpurAlso near Nagpur City, Dr.Ambedkar Marg

Possession date of Akshay: 31 December 2026, moved from 30 December 2022 (48 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P50500010478, and currently active.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Akshay?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Akshay has moved

  1. 30 December 2022

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EA25052621091)

    Reason the builder gave MahaRERA:
    “Financial hardships due to under valued & low sales than expected. I, the promoter had to liquidate my personal property to ensure completion of the project. Now the project is out of debt & in position of completion hence requesting your g…” Read the full reason“Financial hardships due to under valued & low sales than expected. I, the promoter had to liquidate my personal property to ensure completion of the project. Now the project is out of debt & in position of completion hence requesting your genuine kindness in approving the extension & completion for me to deliver the promised units to the buyers & complete the project appropriately. Have also attached the PERT CPM chart for reference.”

Source: Akshay’s extension records on MahaRERA (P50500010478), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Akshay

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P50500010478
Status
Registered and active
Builder
Mahendra Purushottam Tank
Location
Chikhali (Deosthan), Nagpur · 440002
Project type
Residential / Group Housing
Registered on
31 Aug 2017
Completion date at registration
December 2022
Latest completion date
December 2026
Delay so far
48 months
Homes
89
Sold or booked
53%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Akshay, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Akshay100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • Akshay: covers 6 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Akshay every month.

Akshay: buildings, flats and land, as filed on MahaRERA

  • Buildings: Akshay (8 floors, 89 units)
  • Car parking: 1 covered, 18 open
  • Land: 3,736 sq m (about 0.9 acres) · sanctioned built-up 4,583 sq m · recreational space 2,155 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Akshay →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Akshay: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Akshay

What is the possession date of Akshay?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Akshay in Chikhali (Deosthan), Nagpur is 31 December 2026 — 48 months later than 30 December 2022, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Akshay?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Akshay's builder has filed on MahaRERA, the official one, is 31 December 2026, already 48 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Akshay extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Akshay's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "Financial hardships due to under valued & low sales than expected. I, the promoter had to liquidate my personal property to ensure completion of the project. Now the project is out of debt & in position of completion hence requesting your genuine kindness in approving the extension & completion for me to deliver the promised units to the buyers & complete the project appropriately. Have also attached the PERT CPM chart for reference.".

What is the RERA number of Akshay?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Akshay in Chikhali (Deosthan), Nagpur is P50500010478.

Is Akshay registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Akshay is registered as P50500010478 and its status is "Registered and active".

What is the construction status of Akshay?

According to GharKundli's check of MahaRERA records (updated October 2026), Akshay's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Akshay is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Akshay have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Akshay safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Akshay is registered on MahaRERA as P50500010478, its completion date has moved 48 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Akshay's possession date changes?

The latest dates are on Akshay's MahaRERA page (P50500010478). GharKundli's Kundli Watch sends a free WhatsApp update on Akshay every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Akshay have?

According to GharKundli's check of MahaRERA records (updated October 2026), Akshay has one building filed: Akshay with 8 floors and 89 units.

How much parking does Akshay have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1 covered and 18 open car parking spaces for Akshay.

How big is the land of Akshay?

According to GharKundli's check of MahaRERA records (updated October 2026), Akshay stands on 3,736 sq m of land (about 0.9 acres), with 4,583 sq m of sanctioned built-up area and 2,155 sq m of recreational open space.

Where can I read reviews of Akshay?

Google Maps has reviews of Akshay written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Akshay?

Akshay by Mahendra Purushottam Tank is in Chikhali (Deosthan), Nagpur (pincode 440002), near Nagpur City, Dr.Ambedkar Marg, Maharashtra, and is registered on MahaRERA as P50500010478, per GharKundli's check of MahaRERA records.

How many homes are in Akshay?

According to GharKundli's check of MahaRERA records (updated October 2026), Akshay has 89 homes in 1 tower registered on MahaRERA, and 53% of them are sold or booked.

When was Akshay registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Akshay was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Akshay?

No court cases are listed for Akshay on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Akshay?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Mahendra Purushottam Tank.

All projects with possession due in 2026 in Nagpur →

Other projects in Nagpur (Urban)

All 6 projects in Nagpur City (440002) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.