Oak Serenade
by OAK BUILDTECH INDIA LLP · Kadbi Chowk, Nagpur 440004Also near Jaripatka, Dr.Ambedkar Marg
What’s in the report? →Possession date of Oak Serenade (MahaRERA P50500009275): 31 December 2019, moved from 31 December 2018 (12 months later), and it has already passed. It has 18 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P50500009275. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P50500009275, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (December 2019) has passed.
What do you want to know about Oak Serenade?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Oak Serenade has moved
31 December 2018
Completion date given when the project was registered
31 December 2019
Extended at the builder's request (MahaRERA application EXT50500000986)
Reason the builder gave MahaRERA:
“We have proposed to construct two additional floors in the project and request has been made to the Town Planning Department (NMC), Nagpur, to grant time for submission of revised building plan for sanction. Copy of the stamped letter submi…” Read the full reason
“We have proposed to construct two additional floors in the project and request has been made to the Town Planning Department (NMC), Nagpur, to grant time for submission of revised building plan for sanction. Copy of the stamped letter submitted to Town Planning Department (NMC), Nagpur, is attached herewith.”
Source: Oak Serenade’s extension records on MahaRERA (P50500009275), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Oak Serenade
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2019 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P50500009275
- Status
- Lapsed (registration period ended)
- Builder
- OAK BUILDTECH INDIA LLP
- Location
- Kadbi Chowk, Nagpur · 440004
- Project type
- Residential / Group Housing
- Registered on
- 22 Aug 2017
- Completion date at registration
- December 2018
- Latest completion date
- December 2019
- Delay so far
- 12 months
- Homes
- 18
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Oak Serenade, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| OAK SERENADE | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Oak Serenade every 1–2 months.
Oak Serenade: buildings, flats and land, as filed on MahaRERA
- Buildings: OAK SERENADE (8 floors)
- Land: 1,078 sq m (about 0.3 acres) · sanctioned built-up 1,137 sq m
- Land, as filed: PLOT NO 21 CITY SUREVEY NO 68/1 HOUSE NO 892/A
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Oak Serenade →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Oak Serenade: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Oak Serenade
What is the possession date of Oak Serenade?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Oak Serenade in Kadbi Chowk, Nagpur is 31 December 2019 — 12 months later than 31 December 2018, the date given at registration. That date has already passed.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Oak Serenade?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Oak Serenade's builder has filed on MahaRERA, the official one, is 31 December 2019, already 12 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Oak Serenade extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Oak Serenade's builder applied to MahaRERA to extend the completion date once: to 31 December 2019, giving the reason "We have proposed to construct two additional floors in the project and request has been made to the Town Planning Department (NMC), Nagpur, to grant time for submission of revised building plan for sanction. Copy of the stamped letter submitted to Town Planning Department (NMC), Nagpur, is attached herewith.".
What is the RERA number of Oak Serenade?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Oak Serenade in Kadbi Chowk, Nagpur is P50500009275.
Is Oak Serenade registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Oak Serenade is registered as P50500009275 and its status is "Lapsed (registration period ended)".
What is the current construction status of Oak Serenade? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Oak Serenade's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on OAK SERENADE is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Oak Serenade have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Oak Serenade safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Oak Serenade is registered on MahaRERA as P50500009275, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Oak Serenade?
Oak Serenade isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Oak Serenade?
For a flat in Oak Serenade (Nagpur), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Transport Surcharge + 1% LBT. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Oak Serenade received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Oak Serenade isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 December 2019 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Oak Serenade?
According to GharKundli's check of MahaRERA records (updated November 2026), Oak Serenade's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 December 2019) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Oak Serenade uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Oak Serenade was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Oak Serenade's possession date changes?
The latest dates are on Oak Serenade's MahaRERA page (P50500009275). GharKundli's Kundli Watch sends a free WhatsApp update on Oak Serenade every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Oak Serenade have?
According to GharKundli's check of MahaRERA records (updated November 2026), Oak Serenade has one building filed: OAK SERENADE with 8 floors.
How big is the land of Oak Serenade?
According to GharKundli's check of MahaRERA records (updated November 2026), Oak Serenade stands on 1,078 sq m of land (about 0.3 acres), with 1,137 sq m of sanctioned built-up area.
What are the reviews of Oak Serenade?
Google Maps has reviews of Oak Serenade written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Oak Serenade?
Oak Serenade by OAK BUILDTECH INDIA LLP is in Kadbi Chowk, Nagpur, pincode 440004 (near Jaripatka, Dr.Ambedkar Marg), Maharashtra, and is registered on MahaRERA as P50500009275, per GharKundli's check of MahaRERA records. Its land is filed as PLOT NO 21 CITY SUREVEY NO 68/1 HOUSE NO 892/A.
How many flats are in Oak Serenade?
According to GharKundli's check of MahaRERA records (updated November 2026), Oak Serenade has 18 homes in 2 towers registered on MahaRERA.
When was Oak Serenade registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Oak Serenade was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.
Does Oak Serenade have any legal issues or court cases?
No court cases are listed for Oak Serenade on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Oak Serenade?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is OAK BUILDTECH INDIA LLP.
Check it yourself on MahaRERA
- How to check the possession date of Oak Serenade
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Nagpur (Urban)
All Nagpur projects with no pincode on MahaRERA →
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.