Possession date of PUSHKAR SIGNATURE: 31 December 2024, moved from 31 March 2019 (69 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P50500009067. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (December 2024) has passed.

What do you want to know about PUSHKAR SIGNATURE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of PUSHKAR SIGNATURE has moved

  1. 31 March 2019

    Completion date given when the project was registered

  2. 30 April 2020

    Extended at the builder's request (MahaRERA application EXT50500002489)

    Reason the builder gave MahaRERA: “No Specific Reason”
  3. 31 December 2021

    Extended at the builder's request (MahaRERA application EXT50500008712)

    Reason the builder gave MahaRERA: “Due COVID - 19 & Lock down we faced the shortage of labour, hence applied for extension.”
  4. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT50500015076)

    Reason the builder gave MahaRERA: “OC is pending with the Nagpur muncipal corporation for Phase -1. Phase-2 not yet started.”

Source: PUSHKAR SIGNATURE’s extension records on MahaRERA (P50500009067), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on PUSHKAR SIGNATURE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint and 1 court case, and how it ended
  • Construction pace against the December 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P50500009067
Status
Lapsed (registration period ended)
Builder
Pushkar Homes Private Limited
Location
Civil Lines, Nagpur · 440015
Project type
Residential / Group Housing
Registered on
19 Aug 2017
Completion date at registration
March 2019
Latest completion date
December 2024
Delay so far
69 months
Homes
56
Towers
2
Complaints on MahaRERA
1
Court cases listed
1
Title report on file
Not found
Builder's other MahaRERA projects
5

Construction progress of PUSHKAR SIGNATURE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
PUSHKAR SIGNATURE-BLDG 1100%70%0%0%
PUSHKAR SIGNATURE-BLDG 20%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on PUSHKAR SIGNATURE every month.

PUSHKAR SIGNATURE: buildings, flats and land, as filed on MahaRERA

  • Buildings: PUSHKAR SIGNATURE-BLDG 1 (7 floors) · PUSHKAR SIGNATURE-BLDG 2 (3 floors)
  • Land: 1,621 sq m (about 0.4 acres) · sanctioned built-up 2,025 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of PUSHKAR SIGNATURE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

PUSHKAR SIGNATURE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about PUSHKAR SIGNATURE

What is the possession date of PUSHKAR SIGNATURE?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for PUSHKAR SIGNATURE in Civil Lines, Nagpur is 31 December 2024 — 69 months later than 31 March 2019, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for PUSHKAR SIGNATURE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date PUSHKAR SIGNATURE's builder has filed on MahaRERA, the official one, is 31 December 2024, already 69 months later than the 31 March 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of PUSHKAR SIGNATURE extended?

According to GharKundli's check of MahaRERA records (updated November 2026), PUSHKAR SIGNATURE's builder applied to MahaRERA to extend the completion date 3 times: to 30 April 2020, giving the reason "No Specific Reason"; to 31 December 2021, giving the reason "Due COVID - 19 & Lock down we faced the shortage of labour, hence applied for extension."; to 31 December 2024, giving the reason "OC is pending with the Nagpur muncipal corporation for Phase -1. Phase-2 not yet started.".

What is the RERA number of PUSHKAR SIGNATURE?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of PUSHKAR SIGNATURE in Civil Lines, Nagpur is P50500009067.

Is PUSHKAR SIGNATURE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), PUSHKAR SIGNATURE is registered as P50500009067 and its status is "Lapsed (registration period ended)".

What is the construction status of PUSHKAR SIGNATURE?

According to GharKundli's check of MahaRERA records (updated November 2026), PUSHKAR SIGNATURE's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 0% to 70% across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does PUSHKAR SIGNATURE have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is PUSHKAR SIGNATURE safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), PUSHKAR SIGNATURE is registered on MahaRERA as P50500009067, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 69 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if PUSHKAR SIGNATURE's possession date changes?

The latest dates are on PUSHKAR SIGNATURE's MahaRERA page (P50500009067). GharKundli's Kundli Watch sends a free WhatsApp update on PUSHKAR SIGNATURE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does PUSHKAR SIGNATURE have?

According to GharKundli's check of MahaRERA records (updated November 2026), PUSHKAR SIGNATURE has 2 buildings filed: PUSHKAR SIGNATURE-BLDG 1 with 7 floors; PUSHKAR SIGNATURE-BLDG 2 with 3 floors.

How big is the land of PUSHKAR SIGNATURE?

According to GharKundli's check of MahaRERA records (updated November 2026), PUSHKAR SIGNATURE stands on 1,621 sq m of land (about 0.4 acres), with 2,025 sq m of sanctioned built-up area.

Where can I read reviews of PUSHKAR SIGNATURE?

Google Maps has reviews of PUSHKAR SIGNATURE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is PUSHKAR SIGNATURE?

PUSHKAR SIGNATURE by Pushkar Homes Private Limited is in Civil Lines, Nagpur (pincode 440015), Maharashtra, and is registered on MahaRERA as P50500009067, per GharKundli's check of MahaRERA records.

How many homes are in PUSHKAR SIGNATURE?

According to GharKundli's check of MahaRERA records (updated November 2026), PUSHKAR SIGNATURE has 56 homes in 2 towers registered on MahaRERA.

When was PUSHKAR SIGNATURE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), PUSHKAR SIGNATURE was registered on MahaRERA on 19 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on PUSHKAR SIGNATURE?

1 court case is listed for PUSHKAR SIGNATURE on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of PUSHKAR SIGNATURE?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Pushkar Homes Private Limited, which has 5 other projects registered on MahaRERA.

Other projects in Nagpur (Urban)

All 32 projects in Vivekanand Nagar (440015) →

Other projects by Pushkar Homes Private Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.