Possession date of Brij: 30 April 2028, moved from 30 April 2019 (104 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P50500013364, and currently active. Its completion date has moved from April 2019 to April 2028: 104 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Brij?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Brij has moved

  1. 30 April 2019

    Completion date given when the project was registered

  2. 29 April 2020

    Extended at the builder's request (MahaRERA application EXT50500002137)

    Reason the builder gave MahaRERA:
    “RECESSION IN REAL ESTATE & FUNDS PROBLEM:- The company has invested its entire capital and quasi capital alongwith the delayed release of bank project loan.The very bad situation of real estate sector has been the main reason for delay in c…” Read the full reason“RECESSION IN REAL ESTATE & FUNDS PROBLEM:- The company has invested its entire capital and quasi capital alongwith the delayed release of bank project loan.The very bad situation of real estate sector has been the main reason for delay in completion of construction of project as such we pray for extension of time period for completion of construction and thereby giving possession to the esteemed customers for a further period of one year.”
  3. 30 December 2024

    Extended at the builder's request (MahaRERA application EXT50500010927)

    Reason the builder gave MahaRERA: “Due to current ongoing pandemic we could not arrange the requisite”
  4. 31 December 2027

    Extended at the builder's request (MahaRERA application EA24062621495)

    Reason the builder gave MahaRERA:
    “We, M/s. Ved Bhumi Builders and Developers Pvt. Ltd., promoter of the said project, we are writing to formally request an extension for the completion date of our plotted development project located at Plot No. 7, City Survey No. 34, Mouza…” Read the full reason“We, M/s. Ved Bhumi Builders and Developers Pvt. Ltd., promoter of the said project, we are writing to formally request an extension for the completion date of our plotted development project located at Plot No. 7, City Survey No. 34, Mouza – Wathoda, Tah. – Nagpur, District – Nagpur; total admeasuring 834.20 Sq. Mtrs. The current registration for the aforementioned project is valid until 30-06-2025. We are seeking an extension of 1.5 years, proposing a revised completion date of 31-12-2027. - Reasons for Delay Despite our best efforts to adhere to the original timeline, the development of t…”
  5. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Brij’s extension records on MahaRERA (P50500013364), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Brij

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P50500013364
Status
Registered and active
Builder
Vedbhumi Builders & Developers Pvt. Ltd.
Location
Nagur, Nagpur · 440008
Project type
Others
Registered on
26 Sep 2017
Completion date at registration
April 2019
Latest completion date
April 2028
Delay so far
104 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
16
Sold or booked
96%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Brij, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Brij90%90%40%0%

Commencement certificate (CC), as filed on MahaRERA

  • Brij: covers 7 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Brij every month.

Brij: buildings, flats and land, as filed on MahaRERA

  • Buildings: Brij (7 floors, 24 units)
  • Land: 834 sq m (about 0.2 acres) · sanctioned built-up 834 sq m

The builder’s record and reviews

Vedbhumi Builders & Developers (a group of 2 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 113 months); 1 still being built, 1 past the promised date (typically 86 months late). No complaints on MahaRERA.

Read Google reviews of Brij →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Brij: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Brij

What is the possession date of Brij?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Brij in Nagur, Nagpur is 30 April 2028 — 104 months later than 30 April 2019, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Brij?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Brij's builder has filed on MahaRERA, the official one, is 30 April 2028, already 104 months later than the 30 April 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Brij extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Brij's builder applied to MahaRERA to extend the completion date 3 times: to 29 April 2020, giving the reason "RECESSION IN REAL ESTATE & FUNDS PROBLEM:- The company has invested its entire capital and quasi capital alongwith the delayed release of bank project loan.The very bad situation of real estate sector has been the main reason for delay in completion of construction of project as such we pray for extension of time period for completion of construction and thereby giving possession to the esteemed customers for a further period of one year."; to 30 December 2024, giving the reason "Due to current ongoing pandemic we could not arrange the requisite"; to 31 December 2027, giving the reason "We, M/s. Ved Bhumi Builders and Developers Pvt. Ltd., promoter of the said project, we are writing to formally request an extension for the completion date of our plotted development project located at Plot No. 7, City Survey No. 34, Mouza – Wathoda, Tah. – Nagpur, District – Nagpur; total admeasuring 834.20 Sq. Mtrs. The current registration for the aforementioned project is valid until 30-06-2025. We are seeking an extension of 1.5 years, proposing a revised completion date of 31-12-2027. - Reasons for Delay Despite our best efforts to adhere to the original timeline, the development of t…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Brij?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Brij in Nagur, Nagpur is P50500013364.

Is Brij registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Brij is registered as P50500013364 and its status is "Registered and active".

What is the construction status of Brij?

According to GharKundli's check of MahaRERA records (updated October 2026), Brij's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Brij is 90% done and internal work 40%. GharKundli's full report compares construction progress with the deadline.

Does Brij have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Brij safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Brij is registered on MahaRERA as P50500013364, its completion date has moved 104 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Brij's possession date changes?

The latest dates are on Brij's MahaRERA page (P50500013364). GharKundli's Kundli Watch sends a free WhatsApp update on Brij every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Brij have?

According to GharKundli's check of MahaRERA records (updated October 2026), Brij has one building filed: Brij with 7 floors and 24 units.

How big is the land of Brij?

According to GharKundli's check of MahaRERA records (updated October 2026), Brij stands on 834 sq m of land (about 0.2 acres), with 834 sq m of sanctioned built-up area.

What is the track record of Brij's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Vedbhumi Builders & Developers (a group of 2 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 113 months); 1 still being built, 1 past the promised date (typically 86 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Brij?

Google Maps has reviews of Brij written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Brij?

Brij by Vedbhumi Builders & Developers Pvt. Ltd. is in Nagur, Nagpur (pincode 440008), Maharashtra, and is registered on MahaRERA as P50500013364, per GharKundli's check of MahaRERA records.

How many homes are in Brij?

According to GharKundli's check of MahaRERA records (updated October 2026), Brij has 16 homes in 1 tower registered on MahaRERA, and 96% of them are sold or booked.

When was Brij registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Brij was registered on MahaRERA on 26 September 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Brij?

No court cases are listed for Brij on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Brij?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Vedbhumi Builders & Developers Pvt. Ltd., which has 1 other project registered on MahaRERA.

All projects with possession due in 2028 in Nagpur →

Other projects in Nagpur (Urban)

All 30 projects in Bagadganj (440008) →

Other projects by Vedbhumi Builders & Developers Pvt. Ltd.

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.