S V Enclave
by Concept Realtors · Lashribagh, Nagpur
Possession date of S V Enclave: 30 July 2026, moved from 30 June 2018 (93 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P50500012528. Status: Lapsed (registration period ended). Its completion date has moved from June 2018 to July 2026: 93 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (July 2026) has passed.
What do you want to know about S V Enclave?
How the possession date of S V Enclave has moved
30 June 2018
Completion date given when the project was registered
30 June 2020
Extended at the builder's request (MahaRERA application EXT50500002219)
Reason the builder gave MahaRERA:
“The Promoters have submitted Revised Building Plan for sanction to the Town Planner, Town Planning Department, Nagpur Municipal Corporation, Nagpur on 18-04-2019 which was rejected owing to reason that the Project land is falling within the…” Read the full reason
“The Promoters have submitted Revised Building Plan for sanction to the Town Planner, Town Planning Department, Nagpur Municipal Corporation, Nagpur on 18-04-2019 which was rejected owing to reason that the Project land is falling within the limits of Nagpur Metro Rail Corridor and the Revised Plan should be submitted as per Government Resolution No. TPS-2414/477/Pra.Kra.248/2014/Navi-9 dated 09-06-2017. The Promoters have now prepared the revised Building Plan as per the Government Notification and sanctioning is in process, due to above circumstances the Promoters have failed to compete th…”30 September 2023
Extended at the builder's request (MahaRERA application EXT50500011282)
Reason the builder gave MahaRERA:
“The Promoters have submitted Revised Building Plan for sanction to the Town Planner, Town Planning Department, Nagpur Municipal Corporation, Nagpur on 08/09/2021 The project land is falling within the limits of Nagpur Metro Rail Corridor an…” Read the full reason
“The Promoters have submitted Revised Building Plan for sanction to the Town Planner, Town Planning Department, Nagpur Municipal Corporation, Nagpur on 08/09/2021 The project land is falling within the limits of Nagpur Metro Rail Corridor and the Revised Plan is been submitted. The Promoters have now prepared the revised Building Plan as per the Government Notification and sanctioning is is been sanctioned, due to above circumstances the Promoters have decided to extend the project for additional 2 floor been sanctioned”30 March 2026
Extended at the builder's request (MahaRERA application EA03072501944)
Reason the builder gave MahaRERA: “Due to technical glitches on MahaCriti, a new site launched by MahaRERA and labour shortage in areas, we were unable to complete the project in extended time”
30 July 2026
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: S V Enclave’s extension records on MahaRERA (P50500012528), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on S V Enclave
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P50500012528
- Status
- Lapsed (registration period ended)
- Builder
- Concept Realtors
- Location
- Lashribagh, Nagpur · 440017
- Project type
- Others
- Registered on
- 1 Sep 2017
- Completion date at registration
- June 2018
- Latest completion date
- July 2026
- Delay so far
- 93 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 17
- Sold or booked
- 42%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of S V Enclave, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| S V Enclave | 100% | 100% | 100% | 80% |
Commencement certificate (CC), as filed on MahaRERA
- S V Enclave: covers 6 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on S V Enclave every month.
S V Enclave: buildings, flats and land, as filed on MahaRERA
- Buildings: S V Enclave (6 floors, 27 units)
- Land: 680 sq m (about 0.2 acres) · sanctioned built-up 680 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of S V Enclave →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
S V Enclave: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about S V Enclave
What is the possession date of S V Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for S V Enclave in Lashribagh, Nagpur is 30 July 2026 — 93 months later than 30 June 2018, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.
Is the builder's possession date different from the MahaRERA date for S V Enclave?
Builders and listing sites often quote an earlier "target" date for handover. The completion date S V Enclave's builder has filed on MahaRERA, the official one, is 30 July 2026, already 93 months later than the 30 June 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of S V Enclave extended?
According to GharKundli's check of MahaRERA records (updated October 2026), S V Enclave's builder applied to MahaRERA to extend the completion date 3 times: to 30 June 2020, giving the reason "The Promoters have submitted Revised Building Plan for sanction to the Town Planner, Town Planning Department, Nagpur Municipal Corporation, Nagpur on 18-04-2019 which was rejected owing to reason that the Project land is falling within the limits of Nagpur Metro Rail Corridor and the Revised Plan should be submitted as per Government Resolution No. TPS-2414/477/Pra.Kra.248/2014/Navi-9 dated 09-06-2017. The Promoters have now prepared the revised Building Plan as per the Government Notification and sanctioning is in process, due to above circumstances the Promoters have failed to compete th…"; to 30 September 2023, giving the reason "The Promoters have submitted Revised Building Plan for sanction to the Town Planner, Town Planning Department, Nagpur Municipal Corporation, Nagpur on 08/09/2021 The project land is falling within the limits of Nagpur Metro Rail Corridor and the Revised Plan is been submitted. The Promoters have now prepared the revised Building Plan as per the Government Notification and sanctioning is is been sanctioned, due to above circumstances the Promoters have decided to extend the project for additional 2 floor been sanctioned"; to 30 March 2026, giving the reason "Due to technical glitches on MahaCriti, a new site launched by MahaRERA and labour shortage in areas, we were unable to complete the project in extended time". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of S V Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of S V Enclave in Lashribagh, Nagpur is P50500012528.
Is S V Enclave registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), S V Enclave is registered as P50500012528 and its status is "Lapsed (registration period ended)".
What is the construction status of S V Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), S V Enclave's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on S V Enclave is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does S V Enclave have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is S V Enclave safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), S V Enclave is registered on MahaRERA as P50500012528, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 93 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if S V Enclave's possession date changes?
The latest dates are on S V Enclave's MahaRERA page (P50500012528). GharKundli's Kundli Watch sends a free WhatsApp update on S V Enclave every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does S V Enclave have?
According to GharKundli's check of MahaRERA records (updated October 2026), S V Enclave has one building filed: S V Enclave with 6 floors and 27 units.
How big is the land of S V Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), S V Enclave stands on 680 sq m of land (about 0.2 acres), with 680 sq m of sanctioned built-up area.
Where can I read reviews of S V Enclave?
Google Maps has reviews of S V Enclave written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is S V Enclave?
S V Enclave by Concept Realtors is in Lashribagh, Nagpur (pincode 440017), Maharashtra, and is registered on MahaRERA as P50500012528, per GharKundli's check of MahaRERA records.
How many homes are in S V Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), S V Enclave has 17 homes in 1 tower registered on MahaRERA, and 42% of them are sold or booked.
When was S V Enclave registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), S V Enclave was registered on MahaRERA on 1 September 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on S V Enclave?
No court cases are listed for S V Enclave on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of S V Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Concept Realtors, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of S V Enclave
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Nagpur →
Other projects in Nagpur (Urban)
- ROYAL PARK
- GLOCAL SQUARE 3 RD FLOOR
- SHREE APARTMENTS
- Mithila Apartment
- EMPRESS ROYAL EFGH
- ROYAL PRIDE
- Devotie
- Swapnapurtee - A Project by NMC
Other projects by Concept Realtors
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.