by Anand Ravindra Palandurkar & Amol Ravindra Palandurkar · Tirupati Cooperative Housing Society, Nagpur

Possession date of POORVA HEIGHTS: 30 March 2027, moved from 31 December 2019 (83 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P50500017222, and currently active. Its completion date has moved from December 2019 to March 2027: 83 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about POORVA HEIGHTS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of POORVA HEIGHTS has moved

  1. 31 December 2019

    Completion date given when the project was registered

  2. 30 November 2020

    Extended at the builder's request (MahaRERA application EXT50500005629)

    Reason the builder gave MahaRERA: “Work is not completed”
  3. 30 November 2022

    Extended at the builder's request (MahaRERA application EXT50500009779)

    Reason the builder gave MahaRERA: “Work Pending”
  4. 30 November 2026

    Extended at the builder's request (MahaRERA application EXT50500015054)

    Reason the builder gave MahaRERA: “Work Pending 10 %”
  5. 30 March 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: POORVA HEIGHTS’s extension records on MahaRERA (P50500017222), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on POORVA HEIGHTS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P50500017222
Status
Registered and active
Builder
Anand Ravindra Palandurkar & Amol Ravindra Palandurkar
Location
Tirupati Cooperative Housing Society, Nagpur · 440023
Project type
Residential / Group Housing
Registered on
23 Jul 2018
Completion date at registration
December 2019
Latest completion date
March 2027
Delay so far
83 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
8
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of POORVA HEIGHTS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
POORVA HEIGHTS100%90%90%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on POORVA HEIGHTS every month.

POORVA HEIGHTS: buildings, flats and land, as filed on MahaRERA

  • Buildings: POORVA HEIGHTS (32 floors)
  • Land: 472 sq m (about 0.1 acres) · sanctioned built-up 634 sq m
  • Boundaries filed include: KHADGAON ROAD

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of POORVA HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

POORVA HEIGHTS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about POORVA HEIGHTS

What is the possession date of POORVA HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for POORVA HEIGHTS in Tirupati Cooperative Housing Society, Nagpur is 30 March 2027 — 83 months later than 31 December 2019, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for POORVA HEIGHTS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date POORVA HEIGHTS's builder has filed on MahaRERA, the official one, is 30 March 2027, already 83 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of POORVA HEIGHTS extended?

According to GharKundli's check of MahaRERA records (updated November 2026), POORVA HEIGHTS's builder applied to MahaRERA to extend the completion date 3 times: to 30 November 2020, giving the reason "Work is not completed"; to 30 November 2022, giving the reason "Work Pending"; to 30 November 2026, giving the reason "Work Pending 10 %". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of POORVA HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of POORVA HEIGHTS in Tirupati Cooperative Housing Society, Nagpur is P50500017222.

Is POORVA HEIGHTS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), POORVA HEIGHTS is registered as P50500017222 and its status is "Registered and active".

What is the construction status of POORVA HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), POORVA HEIGHTS's status on MahaRERA is "Registered and active". As filed by the builder, slab work on POORVA HEIGHTS is 90% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.

Does POORVA HEIGHTS have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is POORVA HEIGHTS safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), POORVA HEIGHTS is registered on MahaRERA as P50500017222, its completion date has moved 83 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if POORVA HEIGHTS's possession date changes?

The latest dates are on POORVA HEIGHTS's MahaRERA page (P50500017222). GharKundli's Kundli Watch sends a free WhatsApp update on POORVA HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does POORVA HEIGHTS have?

According to GharKundli's check of MahaRERA records (updated November 2026), POORVA HEIGHTS has one building filed: POORVA HEIGHTS with 32 floors.

How big is the land of POORVA HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), POORVA HEIGHTS stands on 472 sq m of land (about 0.1 acres), with 634 sq m of sanctioned built-up area.

Where can I read reviews of POORVA HEIGHTS?

Google Maps has reviews of POORVA HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is POORVA HEIGHTS?

POORVA HEIGHTS by Anand Ravindra Palandurkar & Amol Ravindra Palandurkar is in Tirupati Cooperative Housing Society, Nagpur (pincode 440023), Maharashtra, and is registered on MahaRERA as P50500017222, per GharKundli's check of MahaRERA records. Its boundaries filed there include KHADGAON ROAD.

How many homes are in POORVA HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), POORVA HEIGHTS has 8 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was POORVA HEIGHTS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), POORVA HEIGHTS was registered on MahaRERA on 23 July 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on POORVA HEIGHTS?

No court cases are listed for POORVA HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of POORVA HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Anand Ravindra Palandurkar & Amol Ravindra Palandurkar.

All projects with possession due in 2027 in Nagpur →

Other projects in Nagpur (Rural)

All 66 projects in Wadi (440023) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.