Lotus Link Square
by Lotus Grih Nirman Private Limited · Andheri, MumbaiAlso near Ambivali West, D. N. Nagar, Vile Parle East
Possession date of Lotus Link Square: 31 December 2024, moved from 31 December 2019 (60 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51800005163. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (December 2024) has passed.
What do you want to know about Lotus Link Square?
How the possession date of Lotus Link Square has moved
31 December 2019
Completion date given when the project was registered
30 December 2020
Extended at the builder's request (MahaRERA application EXT51800001536)
Reason the builder gave MahaRERA:
“At the time of registering the said Project, we had furnished certain details regarding the Floor Space Index (“FSI”) available in respect of the said Project. In our application, we had mentioned the details pertaining to FSI in the follow…” Read the full reason
“At the time of registering the said Project, we had furnished certain details regarding the Floor Space Index (“FSI”) available in respect of the said Project. In our application, we had mentioned the details pertaining to FSI in the following manner: Approved FSI as per sanctioned plan – 8455.42 sq. mtrs. Proposed FSI – 9515 sq. mtrs. which comprised of FSI of 3659 sq. mtrs. for which costs had been paid and for which the plans were under approval (“FSI under approval”) and FSI of 5856 sq. mtrs. which we intended to procure. Total FSI i.e. Approved FSI plus Proposed FSI was 17970 sq. mtrs.…”31 March 2023
Extended at the builder's request (MahaRERA application EXT51800009648)
Reason the builder gave MahaRERA:
“Dear sir We have completed work and received OC on 30/12/2021 for entire part which is sold till date. As on date, the construction work in the said Project has been completed for 1 (one) basement + ground floor + 16 (sixteen) upper floors…” Read the full reason
“Dear sir We have completed work and received OC on 30/12/2021 for entire part which is sold till date. As on date, the construction work in the said Project has been completed for 1 (one) basement + ground floor + 16 (sixteen) upper floors + part 17th (seventeenth) and part 18th (eighteenth) floor including 100% of staircases, lifts and lobby / passage common areas (including 4 (four) levels of car parking) in accordance with the proposed date of completion mentioned on the MahaRERA website. We have also received the part occupancy certificate for 1 (one) basement + ground floor + 16 (Sixte…”31 December 2024
Extended at the builder's request (MahaRERA application EXT51800017513)
Reason the builder gave MahaRERA:
“WE HAD OBTAINED PART OC AND HAD GIVEN POSSESSION TO ALL UNIT BUYERS TO WHOM UNITS WERE SOLD TO DATE. SO, TILL DATE ALL SOLD UNITS HAVE RECEIVED THEIR POSSESSION. FOR THE BALANCE CONSTRUCTION OF 2 FLOORS, WE HAVE NOT BEEN OFFERING ANY UNITS…” Read the full reason
“WE HAD OBTAINED PART OC AND HAD GIVEN POSSESSION TO ALL UNIT BUYERS TO WHOM UNITS WERE SOLD TO DATE. SO, TILL DATE ALL SOLD UNITS HAVE RECEIVED THEIR POSSESSION. FOR THE BALANCE CONSTRUCTION OF 2 FLOORS, WE HAVE NOT BEEN OFFERING ANY UNITS FOR SALE SINCE WE HAD UNSOLD OC UNITS TO BE SOLD FIRST. REASON FOR SEEKING EXTENSION: SINCE NOW MAXIMUM OC READY UNITS ARE SOLD, WE SEEK EXTENSION TO CONSTRUCT THE REMAINING PART OF BUILDING AND COMPLETE FULL OC AND HANDOVER. IN BETWEEN DUE TO THE REDUCED DEMAND OF COMMERCIAL OFFICE SPACES POST-LOCKDOWN, THE INVENTORY MOVEMENT WAS VERY SLOW. BECAUSE OF TH…”
Source: Lotus Link Square’s extension records on MahaRERA (P51800005163), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Lotus Link Square
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 3 court cases, and how it ended
- Construction pace against the December 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800005163
- Status
- Lapsed (registration period ended)
- Builder
- Lotus Grih Nirman Private Limited
- Location
- Andheri, Mumbai · 400053
- Project type
- Commercial
- Registered on
- 10 Aug 2017
- Completion date at registration
- December 2019
- Latest completion date
- December 2024
- Delay so far
- 60 months
- Homes
- 122
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 3
- Title report on file
- Not found
Construction progress of Lotus Link Square, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| COMMERCIAL WING | 100% | 85% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Lotus Link Square every month.
Lotus Link Square: buildings, flats and land, as filed on MahaRERA
- Buildings: COMMERCIAL WING (23 floors)
- Land: 2,226 sq m (about 0.6 acres) · sanctioned built-up 14,961 sq m
- Boundaries filed include: K-2 Society
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Lotus Link Square →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Lotus Link Square: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Lotus Link Square
What is the possession date of Lotus Link Square?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Lotus Link Square in Andheri, Mumbai is 31 December 2024 — 60 months later than 31 December 2019, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Lotus Link Square?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Lotus Link Square's builder has filed on MahaRERA, the official one, is 31 December 2024, already 60 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Lotus Link Square extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Lotus Link Square's builder applied to MahaRERA to extend the completion date 3 times: to 30 December 2020, giving the reason "At the time of registering the said Project, we had furnished certain details regarding the Floor Space Index (“FSI”) available in respect of the said Project. In our application, we had mentioned the details pertaining to FSI in the following manner: Approved FSI as per sanctioned plan – 8455.42 sq. mtrs. Proposed FSI – 9515 sq. mtrs. which comprised of FSI of 3659 sq. mtrs. for which costs had been paid and for which the plans were under approval (“FSI under approval”) and FSI of 5856 sq. mtrs. which we intended to procure. Total FSI i.e. Approved FSI plus Proposed FSI was 17970 sq. mtrs.…"; to 31 March 2023, giving the reason "Dear sir We have completed work and received OC on 30/12/2021 for entire part which is sold till date. As on date, the construction work in the said Project has been completed for 1 (one) basement + ground floor + 16 (sixteen) upper floors + part 17th (seventeenth) and part 18th (eighteenth) floor including 100% of staircases, lifts and lobby / passage common areas (including 4 (four) levels of car parking) in accordance with the proposed date of completion mentioned on the MahaRERA website. We have also received the part occupancy certificate for 1 (one) basement + ground floor + 16 (Sixte…"; to 31 December 2024, giving the reason "WE HAD OBTAINED PART OC AND HAD GIVEN POSSESSION TO ALL UNIT BUYERS TO WHOM UNITS WERE SOLD TO DATE. SO, TILL DATE ALL SOLD UNITS HAVE RECEIVED THEIR POSSESSION. FOR THE BALANCE CONSTRUCTION OF 2 FLOORS, WE HAVE NOT BEEN OFFERING ANY UNITS FOR SALE SINCE WE HAD UNSOLD OC UNITS TO BE SOLD FIRST. REASON FOR SEEKING EXTENSION: SINCE NOW MAXIMUM OC READY UNITS ARE SOLD, WE SEEK EXTENSION TO CONSTRUCT THE REMAINING PART OF BUILDING AND COMPLETE FULL OC AND HANDOVER. IN BETWEEN DUE TO THE REDUCED DEMAND OF COMMERCIAL OFFICE SPACES POST-LOCKDOWN, THE INVENTORY MOVEMENT WAS VERY SLOW. BECAUSE OF TH…".
What is the RERA number of Lotus Link Square?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Lotus Link Square in Andheri, Mumbai is P51800005163.
Is Lotus Link Square registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Lotus Link Square is registered as P51800005163 and its status is "Lapsed (registration period ended)".
What is the construction status of Lotus Link Square?
According to GharKundli's check of MahaRERA records (updated November 2026), Lotus Link Square's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on COMMERCIAL WING is 85% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Lotus Link Square have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Lotus Link Square safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Lotus Link Square is registered on MahaRERA as P51800005163, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 60 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Lotus Link Square's possession date changes?
The latest dates are on Lotus Link Square's MahaRERA page (P51800005163). GharKundli's Kundli Watch sends a free WhatsApp update on Lotus Link Square every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Lotus Link Square have?
According to GharKundli's check of MahaRERA records (updated November 2026), Lotus Link Square has one building filed: COMMERCIAL WING with 23 floors.
How big is the land of Lotus Link Square?
According to GharKundli's check of MahaRERA records (updated November 2026), Lotus Link Square stands on 2,226 sq m of land (about 0.6 acres), with 14,961 sq m of sanctioned built-up area.
Where can I read reviews of Lotus Link Square?
Google Maps has reviews of Lotus Link Square written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Lotus Link Square?
Lotus Link Square by Lotus Grih Nirman Private Limited is in Andheri, Mumbai (pincode 400053), near Ambivali West, D. N. Nagar, Vile Parle East, Maharashtra, and is registered on MahaRERA as P51800005163, per GharKundli's check of MahaRERA records. Its boundaries filed there include K-2 Society.
How many homes are in Lotus Link Square?
According to GharKundli's check of MahaRERA records (updated November 2026), Lotus Link Square has 122 homes in 1 tower registered on MahaRERA.
When was Lotus Link Square registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Lotus Link Square was registered on MahaRERA on 10 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Lotus Link Square?
3 court cases are listed for Lotus Link Square on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Lotus Link Square?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Lotus Grih Nirman Private Limited.
Check it yourself on MahaRERA
- How to check the possession date of Lotus Link Square
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400053
- Parinee i
- Sunbeam Heights
- Tru Gardenia
- Gayatri Enclave
- ESTO ARKIS
- Naman Fifty Eight
- AMAHA SUNFLOWER
- FAME GARDEN
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.