ONE ANUSHKA
by MINAL NARHARI KAWLE · Swawlambi Nagar, Deendayal Nagar, Nagpur
Possession date of ONE ANUSHKA: 14 October 2024, moved from 15 October 2021 (36 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P50500018519. Status: Lapsed (registration period ended).
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (October 2024) has passed.
What do you want to know about ONE ANUSHKA?
How the possession date of ONE ANUSHKA has moved
15 October 2021
Completion date given when the project was registered
14 April 2022
Extended at the builder's request (MahaRERA application EXT50500009468)
Reason the builder gave MahaRERA:
“Respected sir/madam As there was lockdown throughtout our country we were unable to complete our work and as the work started gradually now their is again lockdown in state of maharashtra till 30 th april ,due shortage of manpower and goods…” Read the full reason
“Respected sir/madam As there was lockdown throughtout our country we were unable to complete our work and as the work started gradually now their is again lockdown in state of maharashtra till 30 th april ,due shortage of manpower and goods we were unable to complete our work or project in given time ,we would request you to grant us extension for project completion ,i hope that you take our request under consideration”14 October 2024
Extended at the builder's request (MahaRERA application EXT50500017750)
Reason the builder gave MahaRERA:
“Respected Sir/Madam, Initially, our project was delayed due to lockdown throughout the state. There was substantial shortage of manpower and goods and it took a while to return to normalcy. We had expected to complete the project within ext…” Read the full reason
“Respected Sir/Madam, Initially, our project was delayed due to lockdown throughout the state. There was substantial shortage of manpower and goods and it took a while to return to normalcy. We had expected to complete the project within extended date, however, a small part of it is still remaining. It was further delayed due to personal reasons of the promoters. We are confident of completing the remaining part of the project within the extended date we are applying for. We also want to be through with all our compliances in this respect. We have also attached consent of allottees for that…”
Source: ONE ANUSHKA’s extension records on MahaRERA (P50500018519), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on ONE ANUSHKA
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P50500018519
- Status
- Lapsed (registration period ended)
- Builder
- MINAL NARHARI KAWLE
- Location
- Swawlambi Nagar, Deendayal Nagar, Nagpur · 440022
- Project type
- Residential / Group Housing
- Registered on
- 12 Nov 2018
- Completion date at registration
- October 2021
- Latest completion date
- October 2024
- Delay so far
- 36 months
- Homes
- 41
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of ONE ANUSHKA, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| ONE ANUSHKA | 100% | 100% | 70% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on ONE ANUSHKA every month.
ONE ANUSHKA: buildings, flats and land, as filed on MahaRERA
- Buildings: ONE ANUSHKA (13 floors)
- Land: 1,576 sq m (about 0.4 acres) · sanctioned built-up 5,672 sq m
- Boundaries filed include: SARASWATI SOCIETY
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of ONE ANUSHKA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
ONE ANUSHKA: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about ONE ANUSHKA
What is the possession date of ONE ANUSHKA?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for ONE ANUSHKA in Swawlambi Nagar, Deendayal Nagar, Nagpur is 14 October 2024 — 36 months later than 15 October 2021, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for ONE ANUSHKA?
Builders and listing sites often quote an earlier "target" date for handover. The completion date ONE ANUSHKA's builder has filed on MahaRERA, the official one, is 14 October 2024, already 36 months later than the 15 October 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of ONE ANUSHKA extended?
According to GharKundli's check of MahaRERA records (updated November 2026), ONE ANUSHKA's builder applied to MahaRERA to extend the completion date 2 times: to 14 April 2022, giving the reason "Respected sir/madam As there was lockdown throughtout our country we were unable to complete our work and as the work started gradually now their is again lockdown in state of maharashtra till 30 th april ,due shortage of manpower and goods we were unable to complete our work or project in given time ,we would request you to grant us extension for project completion ,i hope that you take our request under consideration"; to 14 October 2024, giving the reason "Respected Sir/Madam, Initially, our project was delayed due to lockdown throughout the state. There was substantial shortage of manpower and goods and it took a while to return to normalcy. We had expected to complete the project within extended date, however, a small part of it is still remaining. It was further delayed due to personal reasons of the promoters. We are confident of completing the remaining part of the project within the extended date we are applying for. We also want to be through with all our compliances in this respect. We have also attached consent of allottees for that…".
What is the RERA number of ONE ANUSHKA?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of ONE ANUSHKA in Swawlambi Nagar, Deendayal Nagar, Nagpur is P50500018519.
Is ONE ANUSHKA registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), ONE ANUSHKA is registered as P50500018519 and its status is "Lapsed (registration period ended)".
What is the construction status of ONE ANUSHKA?
According to GharKundli's check of MahaRERA records (updated November 2026), ONE ANUSHKA's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on ONE ANUSHKA is 100% done and internal work 70%. GharKundli's full report compares construction progress with the deadline.
Does ONE ANUSHKA have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is ONE ANUSHKA safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), ONE ANUSHKA is registered on MahaRERA as P50500018519, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if ONE ANUSHKA's possession date changes?
The latest dates are on ONE ANUSHKA's MahaRERA page (P50500018519). GharKundli's Kundli Watch sends a free WhatsApp update on ONE ANUSHKA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does ONE ANUSHKA have?
According to GharKundli's check of MahaRERA records (updated November 2026), ONE ANUSHKA has one building filed: ONE ANUSHKA with 13 floors.
How big is the land of ONE ANUSHKA?
According to GharKundli's check of MahaRERA records (updated November 2026), ONE ANUSHKA stands on 1,576 sq m of land (about 0.4 acres), with 5,672 sq m of sanctioned built-up area.
Where can I read reviews of ONE ANUSHKA?
Google Maps has reviews of ONE ANUSHKA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is ONE ANUSHKA?
ONE ANUSHKA by MINAL NARHARI KAWLE is in Swawlambi Nagar, Deendayal Nagar, Nagpur (pincode 440022), Maharashtra, and is registered on MahaRERA as P50500018519, per GharKundli's check of MahaRERA records. Its boundaries filed there include SARASWATI SOCIETY.
How many homes are in ONE ANUSHKA?
According to GharKundli's check of MahaRERA records (updated November 2026), ONE ANUSHKA has 41 homes in 1 tower registered on MahaRERA.
When was ONE ANUSHKA registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), ONE ANUSHKA was registered on MahaRERA on 12 November 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on ONE ANUSHKA?
No court cases are listed for ONE ANUSHKA on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of ONE ANUSHKA?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is MINAL NARHARI KAWLE.
Check it yourself on MahaRERA
- How to check the possession date of ONE ANUSHKA
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Nagpur (Urban)
- ROYAL PARK
- GLOCAL SQUARE 3 RD FLOOR
- SHREE APARTMENTS
- Mithila Apartment
- EMPRESS ROYAL EFGH
- ROYAL PRIDE
- Swapnapurtee - A Project by NMC
- Devotie
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.