Redevelopment of Jai Vijay CHSL - Phase I
by KOLTE-PATIL DEVELOPERS LIMITED · Vile-Parle East, MumbaiAlso near Nallasopara West, Andheri East
Possession: Redevelopment of Jai Vijay CHSL - Phase I is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800004446. Status: Completed. 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Redevelopment of Jai Vijay CHSL - Phase I?
How the possession date of Redevelopment of Jai Vijay CHSL - Phase I has moved
30 September 2019
Completion date given when the project was registered
29 September 2020
Extended at the builder's request (MahaRERA application EXT51800002456)
Reason the builder gave MahaRERA: “Pending disputes and differences between Society and Developer which has resulted in delay.”
29 March 2022
Extended at the builder's request (MahaRERA application EXT51800009256)
Reason the builder gave MahaRERA: “reasons attached”
29 September 2022
Revised completion date on MahaRERA
Source: Redevelopment of Jai Vijay CHSL - Phase I’s extension records on MahaRERA (P51800004446), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Redevelopment of Jai Vijay CHSL - Phase I
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints and 1 court case, and how it ended
- Construction pace against the September 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800004446
- Status
- Completed
- Builder
- KOLTE-PATIL DEVELOPERS LIMITED
- Location
- Vile-Parle East, Mumbai · 400099
- Project type
- Residential / Group Housing
- Registered on
- 9 Aug 2017
- Completion date at registration
- September 2019
- Latest completion date
- September 2022
- Delay so far
- 36 months
- Homes
- 260
- Towers
- 12
- Complaints on MahaRERA
- 2
- Court cases listed
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 63
Construction progress of Redevelopment of Jai Vijay CHSL - Phase I, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| WING A FLOOR 1 TO 8 | 100% | 100% | 100% | 100% |
| WING A PROPOSED FLOOR 9 TO 11 | 0% | 100% | 100% | 100% |
| WING B FLOOR 1 TO 8 | 100% | 100% | 100% | 100% |
| WING B PROPOSED FLOOR 9 TO 11 | 0% | 100% | 100% | 100% |
| WING C FLOOR 1 TO 8 | 100% | 100% | 100% | 100% |
| WING C PROPOSED FLOOR 9 TO 11 | 0% | 100% | 100% | 100% |
| WING D FLOOR 1 TO 8 | 100% | 100% | 100% | 100% |
| WING D PROPOSED FLOOR 9 TO 11 | 0% | 100% | 100% | 100% |
| WING E FLOOR 1 TO 9 | 100% | 100% | 100% | 100% |
| WING E PROPOSED FLOOR 10 TO 11 | 0% | 100% | 100% | 100% |
| WING F FLOOR 1 TO 9 | 100% | 100% | 100% | 100% |
| WING F PROPOSED FLOOR 10 TO 11 | 0% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Redevelopment of Jai Vijay CHSL - Phase I every month.
Redevelopment of Jai Vijay CHSL - Phase I: buildings, flats and land, as filed on MahaRERA
- Buildings: WING A FLOOR 1 TO 8 (11 floors) · WING A PROPOSED FLOOR 9 TO 11 (3 floors) · WING B FLOOR 1 TO 8 (11 floors) · WING B PROPOSED FLOOR 9 TO 11 (3 floors) · WING C FLOOR 1 TO 8 (11 floors) · WING C PROPOSED FLOOR 9 TO 11 (3 floors) · WING D FLOOR 1 TO 8 (11 floors) · WING D PROPOSED FLOOR 9 TO 11 (3 floors) · and 4 more
- Land: 8,979 sq m (about 2.2 acres) · sanctioned built-up 22,400 sq m · recreational space 2,245 sq m
- Boundaries filed include: WESTERN EXPRESS HIGHWAY
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Kolte-patil Developers has 64 projects on MahaRERA since 2017, this one included. Of the 55 GharKundli has checked: 11 finished, 6 within the promised date and 5 needed more time (typically 9 months); 40 still being built, 2 past the promised date (typically 8 months late); 4 lapsed. 29 complaints on MahaRERA across 19 projects.
Read Google reviews of Redevelopment of Jai Vijay CHSL - Phase I →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Redevelopment of Jai Vijay CHSL - Phase I: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Redevelopment of Jai Vijay CHSL - Phase I
What is the possession date of Redevelopment of Jai Vijay CHSL - Phase I?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Redevelopment of Jai Vijay CHSL - Phase I in Vile-Parle East, Mumbai is 29 September 2022 — 36 months later than 30 September 2019, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Redevelopment of Jai Vijay CHSL - Phase I?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Redevelopment of Jai Vijay CHSL - Phase I's builder has filed on MahaRERA, the official one, is 29 September 2022, already 36 months later than the 30 September 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Redevelopment of Jai Vijay CHSL - Phase I extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Redevelopment of Jai Vijay CHSL - Phase I's builder applied to MahaRERA to extend the completion date 2 times: to 29 September 2020, giving the reason "Pending disputes and differences between Society and Developer which has resulted in delay."; to 29 March 2022, giving the reason "reasons attached".
What is the RERA number of Redevelopment of Jai Vijay CHSL - Phase I?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Redevelopment of Jai Vijay CHSL - Phase I in Vile-Parle East, Mumbai is P51800004446.
Is Redevelopment of Jai Vijay CHSL - Phase I registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Redevelopment of Jai Vijay CHSL - Phase I is registered as P51800004446 and its status is "Completed".
What is the construction status of Redevelopment of Jai Vijay CHSL - Phase I?
According to GharKundli's check of MahaRERA records (updated November 2026), Redevelopment of Jai Vijay CHSL - Phase I's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 12 towers. GharKundli's full report compares construction progress with the deadline.
Does Redevelopment of Jai Vijay CHSL - Phase I have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Redevelopment of Jai Vijay CHSL - Phase I safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Redevelopment of Jai Vijay CHSL - Phase I is registered on MahaRERA as P51800004446, its MahaRERA status is "Completed", its completion date has moved 36 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Redevelopment of Jai Vijay CHSL - Phase I's possession date changes?
The latest dates are on Redevelopment of Jai Vijay CHSL - Phase I's MahaRERA page (P51800004446). GharKundli's Kundli Watch sends a free WhatsApp update on Redevelopment of Jai Vijay CHSL - Phase I every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Redevelopment of Jai Vijay CHSL - Phase I have?
According to GharKundli's check of MahaRERA records (updated November 2026), Redevelopment of Jai Vijay CHSL - Phase I has 12 buildings filed: WING A FLOOR 1 TO 8 with 11 floors; WING A PROPOSED FLOOR 9 TO 11 with 3 floors; WING B FLOOR 1 TO 8 with 11 floors; WING B PROPOSED FLOOR 9 TO 11 with 3 floors; WING C FLOOR 1 TO 8 with 11 floors; WING C PROPOSED FLOOR 9 TO 11 with 3 floors; and 6 more.
How big is the land of Redevelopment of Jai Vijay CHSL - Phase I?
According to GharKundli's check of MahaRERA records (updated November 2026), Redevelopment of Jai Vijay CHSL - Phase I stands on 8,979 sq m of land (about 2.2 acres), with 22,400 sq m of sanctioned built-up area and 2,245 sq m of recreational open space.
What is the track record of Redevelopment of Jai Vijay CHSL - Phase I's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Kolte-patil Developers has 64 projects on MahaRERA since 2017, this one included. Of the 55 GharKundli has checked: 11 finished, 6 within the promised date and 5 needed more time (typically 9 months); 40 still being built, 2 past the promised date (typically 8 months late); 4 lapsed. 29 complaints on MahaRERA across 19 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Redevelopment of Jai Vijay CHSL - Phase I?
Google Maps has reviews of Redevelopment of Jai Vijay CHSL - Phase I written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Redevelopment of Jai Vijay CHSL - Phase I?
Redevelopment of Jai Vijay CHSL - Phase I by KOLTE-PATIL DEVELOPERS LIMITED is in Vile-Parle East, Mumbai (pincode 400099), near Nallasopara West, Andheri East, Maharashtra, and is registered on MahaRERA as P51800004446, per GharKundli's check of MahaRERA records. Its boundaries filed there include WESTERN EXPRESS HIGHWAY.
How many homes are in Redevelopment of Jai Vijay CHSL - Phase I?
According to GharKundli's check of MahaRERA records (updated November 2026), Redevelopment of Jai Vijay CHSL - Phase I has 260 homes in 12 towers registered on MahaRERA.
When was Redevelopment of Jai Vijay CHSL - Phase I registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Redevelopment of Jai Vijay CHSL - Phase I was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Redevelopment of Jai Vijay CHSL - Phase I?
1 court case is listed for Redevelopment of Jai Vijay CHSL - Phase I on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Redevelopment of Jai Vijay CHSL - Phase I?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is KOLTE-PATIL DEVELOPERS LIMITED, which has 63 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Redevelopment of Jai Vijay CHSL - Phase I
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Mumbai
All 32 projects in Andheri East (400099) →Other projects by KOLTE-PATIL DEVELOPERS LIMITED
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.