BKC 28
by Vakratunda Buildcon Private Limited · Khernagar, Bandra East, MumbaiAlso near Bandra West, Khar Delivery, Sion
Possession date of BKC 28: 30 March 2027, moved from 30 June 2025 (17 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800028474, and currently active. Its completion date has moved from June 2025 to March 2027: 17 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 4 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about BKC 28?
How the possession date of BKC 28 has moved
30 June 2025
Completion date given when the project was registered
30 November 2026
Extended at the builder's request (MahaRERA application EA12082622110)
Reason the builder gave MahaRERA:
“There was a delay of approximately four months beyond the project's scheduled completion date under RERA in completing the final stage of construction activities and obtaining the Occupation Certificate from the concerned authority. The del…” Read the full reason
“There was a delay of approximately four months beyond the project's scheduled completion date under RERA in completing the final stage of construction activities and obtaining the Occupation Certificate from the concerned authority. The delay was primarily attributable to certain unforeseen challenges faced by the Promoter. Notwithstanding the same, the Promoter made all possible efforts to ensure completion of the project and facilitate the handover of apartments to the allottees. We understand that, in order to complete the project closure process on the new MahaRERA web portal, the proje…”30 March 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: BKC 28’s extension records on MahaRERA (P51800028474), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on BKC 28
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 4 complaints, and how it ended
- Construction pace against the March 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800028474
- Status
- Registered and active
- Builder
- Vakratunda Buildcon Private Limited
- Location
- Khernagar, Bandra East, Mumbai · 400051
- Project type
- Residential / Group Housing
- Registered on
- 3 Mar 2021
- Completion date at registration
- June 2025
- Latest completion date
- March 2027
- Delay so far
- 17 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 98
- Sold or booked
- 98%
- Towers
- 1
- Complaints on MahaRERA
- 4
- Court cases listed
- 0
- Appeals at the tribunal
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of BKC 28, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BKC 28 | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- BKC 28: covers 22 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on BKC 28 every month.
BKC 28: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 639 – 712 | 98 |
- Buildings: BKC 28 (25 floors, 98 units)
- Car parking: 98 covered
- Land: 1,690 sq m (about 0.4 acres) · sanctioned built-up 9,603 sq m
- Boundaries filed include: Railway Plot Boundary
The builder’s record and reviews
Vakratunda Buildcon (a group of 10 linked companies) has 51 projects on MahaRERA since 2017, this one included. Of the 50 GharKundli has checked: 7 finished, 6 within the promised date and 1 needed more time (typically 16 months); 38 still being built, 15 past the promised date (typically 6 months late); 5 lapsed. 454 complaints on MahaRERA across 32 projects.
Read Google reviews of BKC 28 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
BKC 28: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about BKC 28
What is the possession date of BKC 28?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for BKC 28 in Khernagar, Bandra East, Mumbai is 30 March 2027 — 17 months later than 30 June 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for BKC 28?
Builders and listing sites often quote an earlier "target" date for handover. The completion date BKC 28's builder has filed on MahaRERA, the official one, is 30 March 2027, already 17 months later than the 30 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of BKC 28 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), BKC 28's builder applied to MahaRERA to extend the completion date once: to 30 November 2026, giving the reason "There was a delay of approximately four months beyond the project's scheduled completion date under RERA in completing the final stage of construction activities and obtaining the Occupation Certificate from the concerned authority. The delay was primarily attributable to certain unforeseen challenges faced by the Promoter. Notwithstanding the same, the Promoter made all possible efforts to ensure completion of the project and facilitate the handover of apartments to the allottees. We understand that, in order to complete the project closure process on the new MahaRERA web portal, the proje…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of BKC 28?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of BKC 28 in Khernagar, Bandra East, Mumbai is P51800028474.
Is BKC 28 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), BKC 28 is registered as P51800028474 and its status is "Registered and active".
What is the construction status of BKC 28?
According to GharKundli's check of MahaRERA records (updated October 2026), BKC 28's status on MahaRERA is "Registered and active". As filed by the builder, slab work on BKC 28 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does BKC 28 have complaints on MahaRERA?
4 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is BKC 28 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), BKC 28 is registered on MahaRERA as P51800028474, its completion date has moved 17 months since registration and 4 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if BKC 28's possession date changes?
The latest dates are on BKC 28's MahaRERA page (P51800028474). GharKundli's Kundli Watch sends a free WhatsApp update on BKC 28 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does BKC 28 have?
According to GharKundli's check of MahaRERA records (updated October 2026), BKC 28 has one building filed: BKC 28 with 25 floors and 98 units.
What are the flat sizes (carpet area) in BKC 28?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for BKC 28: 2 BHK: 639 to 712 sq ft carpet (98 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does BKC 28 have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 98 covered car parking spaces for BKC 28.
How big is the land of BKC 28?
According to GharKundli's check of MahaRERA records (updated October 2026), BKC 28 stands on 1,690 sq m of land (about 0.4 acres), with 9,603 sq m of sanctioned built-up area.
What is the track record of BKC 28's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Vakratunda Buildcon (a group of 10 linked companies) has 51 projects on MahaRERA since 2017, this one included. Of the 50 GharKundli has checked: 7 finished, 6 within the promised date and 1 needed more time (typically 16 months); 38 still being built, 15 past the promised date (typically 6 months late); 5 lapsed. 454 complaints on MahaRERA across 32 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of BKC 28?
Google Maps has reviews of BKC 28 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 4 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is BKC 28?
BKC 28 by Vakratunda Buildcon Private Limited is in Khernagar, Bandra East, Mumbai (pincode 400051), near Bandra West, Khar Delivery, Sion, Maharashtra, and is registered on MahaRERA as P51800028474, per GharKundli's check of MahaRERA records. Its boundaries filed there include Railway Plot Boundary.
How many homes are in BKC 28?
According to GharKundli's check of MahaRERA records (updated October 2026), BKC 28 has 98 homes in 1 tower registered on MahaRERA, and 98% of them are sold or booked.
When was BKC 28 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), BKC 28 was registered on MahaRERA on 3 March 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on BKC 28?
No court cases are listed for BKC 28 on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of BKC 28?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Vakratunda Buildcon Private Limited, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of BKC 28
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in pincode 400051
- Nero
- Mayur Tower
- K.K.GARMENT HUB
- KHERNAGAR SHRIRAM
- LEO EMINENCE
- Rustomjee Prive
- Vaibhavlaxmi Rhythm 51
- VAKRATUNDA ENTERPRISES
Other projects by Vakratunda Buildcon Private Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.