Rustomjee Prive
by Keysky Realtors Private Limited · Bandra East, MumbaiAlso near BKC, Bandra Kurla Complex, Nirmal Nagar
Possession date of Rustomjee Prive: 30 March 2030. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800079537, and currently active. Its completion date is now March 2030, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Rustomjee Prive?
How the possession date of Rustomjee Prive has moved
30 November 2029
Completion date given when the project was registered
30 March 2030
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Rustomjee Prive’s extension records on MahaRERA (P51800079537), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Rustomjee Prive
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the March 2030 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800079537
- Status
- Registered and active
- Builder
- Keysky Realtors Private Limited
- Location
- Bandra East, Mumbai · 400051
- Project type
- Residential / Group Housing
- Registered on
- 10 Mar 2025
- Completion date at registration
- November 2029
- Latest completion date
- March 2030
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 82
- Sold or booked
- 64%
- Towers
- 3
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Rustomjee Prive, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Wing A | 0% | 0% | 0% | 0% |
| Wing B | 0% | 0% | 0% | 0% |
| Wing C | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Wing A: covers 27 floors
- Wing B: covers 26 floors
- Wing C: covers 26 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Rustomjee Prive every month.
Rustomjee Prive: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 3 BHK | 649 – 1,213 | 69 |
| 2 BHK | 725 – 795 | 11 |
| 1 BHK | 471 – 649 | 2 |
- Buildings: Wing A (27 floors, 30 units) · Wing B (26 floors, 30 units) · Wing C (26 floors, 22 units)
- Car parking: 152 covered
- Land: 1,872 sq m (about 0.5 acres) · sanctioned built-up 9,529 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Keyblue Realtors (a group of 2 linked companies) has 8 projects on MahaRERA since 2023, this one included. Of the 8 GharKundli has checked: 8 still being built, none past the promised date yet. 1 complaint on MahaRERA across 1 project.
Read Google reviews of Rustomjee Prive →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Rustomjee Prive: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Rustomjee Prive
What is the possession date of Rustomjee Prive?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Rustomjee Prive in Bandra East, Mumbai is 30 March 2030, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Rustomjee Prive?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Rustomjee Prive's builder has filed on MahaRERA, the official one, is 30 March 2030, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Rustomjee Prive?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Rustomjee Prive in Bandra East, Mumbai is P51800079537.
Is Rustomjee Prive registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Rustomjee Prive is registered as P51800079537 and its status is "Registered and active".
What is the construction status of Rustomjee Prive?
According to GharKundli's check of MahaRERA records (updated October 2026), Rustomjee Prive's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does Rustomjee Prive have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Rustomjee Prive safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Rustomjee Prive is registered on MahaRERA as P51800079537, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Rustomjee Prive's possession date changes?
The latest dates are on Rustomjee Prive's MahaRERA page (P51800079537). GharKundli's Kundli Watch sends a free WhatsApp update on Rustomjee Prive every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Rustomjee Prive have?
According to GharKundli's check of MahaRERA records (updated October 2026), Rustomjee Prive has 3 buildings filed: Wing A with 27 floors and 30 units; Wing B with 26 floors and 30 units; Wing C with 26 floors and 22 units.
What are the flat sizes (carpet area) in Rustomjee Prive?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Rustomjee Prive: 3 BHK: 649 to 1213 sq ft carpet (69 homes); 2 BHK: 725 to 795 sq ft carpet (11 homes); 1 BHK: 471 to 649 sq ft carpet (2 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Rustomjee Prive have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 152 covered car parking spaces for Rustomjee Prive.
How big is the land of Rustomjee Prive?
According to GharKundli's check of MahaRERA records (updated October 2026), Rustomjee Prive stands on 1,872 sq m of land (about 0.5 acres), with 9,529 sq m of sanctioned built-up area.
What is the track record of Rustomjee Prive's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Keyblue Realtors (a group of 2 linked companies) has 8 projects on MahaRERA since 2023, this one included. Of the 8 GharKundli has checked: 8 still being built, none past the promised date yet. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Rustomjee Prive?
Google Maps has reviews of Rustomjee Prive written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Rustomjee Prive?
Rustomjee Prive by Keysky Realtors Private Limited is in Bandra East, Mumbai (pincode 400051), near BKC, Bandra Kurla Complex, Nirmal Nagar, Maharashtra, and is registered on MahaRERA as P51800079537, per GharKundli's check of MahaRERA records.
How many homes are in Rustomjee Prive?
According to GharKundli's check of MahaRERA records (updated October 2026), Rustomjee Prive has 82 homes in 3 towers registered on MahaRERA, and 64% of them are sold or booked.
When was Rustomjee Prive registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Rustomjee Prive was registered on MahaRERA on 10 March 2025. GharKundli did not find a title report on the land on file there.
Are there court cases on Rustomjee Prive?
No court cases are listed for Rustomjee Prive on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Rustomjee Prive?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Keysky Realtors Private Limited.
Check it yourself on MahaRERA
- How to check the possession date of Rustomjee Prive
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2030 in Mumbai Suburban →
Other projects in pincode 400051
- Kalpataru Magnus
- Nero
- Mayur Tower
- BKC 28
- K.K.GARMENT HUB
- KHERNAGAR SHRIRAM
- LEO EMINENCE
- Vaibhavlaxmi Rhythm 51
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.