Possession date of VAKRATUNDA ENTERPRISES: 30 April 2027, moved from 30 July 2025 (17 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000008100, and currently active. Its completion date has moved from July 2025 to April 2027: 17 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about VAKRATUNDA ENTERPRISES?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of VAKRATUNDA ENTERPRISES has moved

  1. 30 July 2025

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EA24062501727)

    Reason the builder gave MahaRERA: “Due to Slow response to Our project area in Boisar we are unable to complete the project on time. we need time till 31/12/2026 to complete the project in all aspect”
  3. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: VAKRATUNDA ENTERPRISES’s extension records on MahaRERA (P99000008100), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on VAKRATUNDA ENTERPRISES

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000008100
Status
Registered and active
Builder
VAKRATUNDA ENTERPRISES LLP
Location
Bandra East, Palghar · 400051
Project type
Others
Registered on
18 Aug 2017
Completion date at registration
July 2025
Latest completion date
April 2027
Delay so far
17 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
80
Sold or booked
17%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of VAKRATUNDA ENTERPRISES, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
VAKRATUNDA ENTERPRISES100%100%100%0%

Commencement certificate (CC), as filed on MahaRERA

  • VAKRATUNDA ENTERPRISES: covers 4 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on VAKRATUNDA ENTERPRISES every month.

VAKRATUNDA ENTERPRISES: buildings, flats and land, as filed on MahaRERA

  • Buildings: VAKRATUNDA ENTERPRISES (4 floors, 115 units)
  • Land: 5,570 sq m (about 1.4 acres) · sanctioned built-up 3,552 sq m · recreational space 2,018 sq m
  • Boundaries filed include: SUSHIL NAGAR, CHILAR BOISAR ROAD

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of VAKRATUNDA ENTERPRISES →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

VAKRATUNDA ENTERPRISES: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about VAKRATUNDA ENTERPRISES

What is the possession date of VAKRATUNDA ENTERPRISES?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for VAKRATUNDA ENTERPRISES in Bandra East, Palghar is 30 April 2027 — 17 months later than 30 July 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for VAKRATUNDA ENTERPRISES?

Builders and listing sites often quote an earlier "target" date for handover. The completion date VAKRATUNDA ENTERPRISES's builder has filed on MahaRERA, the official one, is 30 April 2027, already 17 months later than the 30 July 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of VAKRATUNDA ENTERPRISES extended?

According to GharKundli's check of MahaRERA records (updated October 2026), VAKRATUNDA ENTERPRISES's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "Due to Slow response to Our project area in Boisar we are unable to complete the project on time. we need time till 31/12/2026 to complete the project in all aspect". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of VAKRATUNDA ENTERPRISES?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of VAKRATUNDA ENTERPRISES in Bandra East, Palghar is P99000008100.

Is VAKRATUNDA ENTERPRISES registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), VAKRATUNDA ENTERPRISES is registered as P99000008100 and its status is "Registered and active".

What is the construction status of VAKRATUNDA ENTERPRISES?

According to GharKundli's check of MahaRERA records (updated October 2026), VAKRATUNDA ENTERPRISES's status on MahaRERA is "Registered and active". As filed by the builder, slab work on VAKRATUNDA ENTERPRISES is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does VAKRATUNDA ENTERPRISES have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is VAKRATUNDA ENTERPRISES safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), VAKRATUNDA ENTERPRISES is registered on MahaRERA as P99000008100, its completion date has moved 17 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if VAKRATUNDA ENTERPRISES's possession date changes?

The latest dates are on VAKRATUNDA ENTERPRISES's MahaRERA page (P99000008100). GharKundli's Kundli Watch sends a free WhatsApp update on VAKRATUNDA ENTERPRISES every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does VAKRATUNDA ENTERPRISES have?

According to GharKundli's check of MahaRERA records (updated October 2026), VAKRATUNDA ENTERPRISES has one building filed: VAKRATUNDA ENTERPRISES with 4 floors and 115 units.

How big is the land of VAKRATUNDA ENTERPRISES?

According to GharKundli's check of MahaRERA records (updated October 2026), VAKRATUNDA ENTERPRISES stands on 5,570 sq m of land (about 1.4 acres), with 3,552 sq m of sanctioned built-up area and 2,018 sq m of recreational open space.

Where can I read reviews of VAKRATUNDA ENTERPRISES?

Google Maps has reviews of VAKRATUNDA ENTERPRISES written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is VAKRATUNDA ENTERPRISES?

VAKRATUNDA ENTERPRISES by VAKRATUNDA ENTERPRISES LLP is in Bandra East, Palghar (pincode 400051), near Sion, Bandra West, Khar Delivery, Maharashtra, and is registered on MahaRERA as P99000008100, per GharKundli's check of MahaRERA records. Its boundaries filed there include SUSHIL NAGAR, CHILAR BOISAR ROAD.

How many homes are in VAKRATUNDA ENTERPRISES?

According to GharKundli's check of MahaRERA records (updated October 2026), VAKRATUNDA ENTERPRISES has 80 homes in 1 tower registered on MahaRERA, and 17% of them are sold or booked.

When was VAKRATUNDA ENTERPRISES registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), VAKRATUNDA ENTERPRISES was registered on MahaRERA on 18 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on VAKRATUNDA ENTERPRISES?

No court cases are listed for VAKRATUNDA ENTERPRISES on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of VAKRATUNDA ENTERPRISES?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is VAKRATUNDA ENTERPRISES LLP.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in pincode 400051

All 79 projects in Bandra East (400051) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.