DIVINE CITY II

by SADESH REALTY BUILDERS LLP · Jamtha, Nagpur

Possession: DIVINE CITY II is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P50500020052. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about DIVINE CITY II?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of DIVINE CITY II has moved

  1. 30 September 2023

    Completion date given when the project was registered

  2. 29 September 2024

    Extended at the builder's request (MahaRERA application EXT50500012627)

    Reason the builder gave MahaRERA: “Natural calamity of "COVID-19" pandemic.”

Source: DIVINE CITY II’s extension records on MahaRERA (P50500020052), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on DIVINE CITY II

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the September 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P50500020052
Status
Completed
Builder
SADESH REALTY BUILDERS LLP
Location
Jamtha, Nagpur · 441122
Project type
Plotted
Registered on
25 Mar 2019
Completion date at registration
September 2023
Latest completion date
September 2024
Delay so far
12 months
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

DIVINE CITY II: buildings, flats and land, as filed on MahaRERA

  • Land: 45,283 sq m (about 11.2 acres) · recreational space 4,529 sq m

The builder’s record and reviews

Sadesh Realty Builders has 3 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 2 finished, all within the promised date. No complaints on MahaRERA.

Read Google reviews of DIVINE CITY II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

DIVINE CITY II: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about DIVINE CITY II

What is the possession date of DIVINE CITY II?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for DIVINE CITY II in Jamtha, Nagpur is 29 September 2024 — 12 months later than 30 September 2023, the date given at registration.

Is the builder's possession date different from the MahaRERA date for DIVINE CITY II?

Builders and listing sites often quote an earlier "target" date for handover. The completion date DIVINE CITY II's builder has filed on MahaRERA, the official one, is 29 September 2024, already 12 months later than the 30 September 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of DIVINE CITY II extended?

According to GharKundli's check of MahaRERA records (updated November 2026), DIVINE CITY II's builder applied to MahaRERA to extend the completion date once: to 29 September 2024, giving the reason "Natural calamity of "COVID-19" pandemic.".

What is the RERA number of DIVINE CITY II?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of DIVINE CITY II in Jamtha, Nagpur is P50500020052.

Is DIVINE CITY II registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), DIVINE CITY II is registered as P50500020052 and its status is "Completed".

What is the construction status of DIVINE CITY II?

According to GharKundli's check of MahaRERA records (updated November 2026), DIVINE CITY II's status on MahaRERA is "Completed". GharKundli's full report compares construction progress with the deadline.

Does DIVINE CITY II have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is DIVINE CITY II safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), DIVINE CITY II is registered on MahaRERA as P50500020052, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does DIVINE CITY II have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: DIVINE CITY (P50500019810, possession 29 Sep 2024). Check that your agreement names the registration of your own wing.

How can I get updates if DIVINE CITY II's possession date changes?

The latest dates are on DIVINE CITY II's MahaRERA page (P50500020052). GharKundli's Kundli Watch sends a free WhatsApp update on DIVINE CITY II every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How big is the land of DIVINE CITY II?

According to GharKundli's check of MahaRERA records (updated November 2026), DIVINE CITY II stands on 45,283 sq m of land (about 11.2 acres) and 4,529 sq m of recreational open space.

What is the track record of DIVINE CITY II's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Sadesh Realty Builders has 3 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 2 finished, all within the promised date. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of DIVINE CITY II?

Google Maps has reviews of DIVINE CITY II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is DIVINE CITY II?

DIVINE CITY II by SADESH REALTY BUILDERS LLP is in Jamtha, Nagpur (pincode 441122), Maharashtra, and is registered on MahaRERA as P50500020052, per GharKundli's check of MahaRERA records.

When was DIVINE CITY II registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), DIVINE CITY II was registered on MahaRERA on 25 March 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on DIVINE CITY II?

No court cases are listed for DIVINE CITY II on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of DIVINE CITY II?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SADESH REALTY BUILDERS LLP, which has 2 other projects registered on MahaRERA.

Other projects in Jamtha

All 64 projects in Industrial Area Butibori (441122) →

Other projects by SADESH REALTY BUILDERS LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.