SWARAJ SAHANIWAS

by KUKADE LAYOUT (LIG)COOPERATIVE HOUSING SOCIETY LTD. · Near ERA international school, Nagpur

Possession: SWARAJ SAHANIWAS is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P50500020570. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about SWARAJ SAHANIWAS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SWARAJ SAHANIWAS has moved

  1. 30 March 2022

    Completion date given when the project was registered

  2. 29 March 2023

    Extended at the builder's request (MahaRERA application EXT50500011878)

    Reason the builder gave MahaRERA: “Due to second wave of pandemic and temporiry lockdown and labour unavaibility further we are unable to complete the project in timeline”
  3. 30 March 2024

    Extended at the builder's request (MahaRERA application EXT50500015199)

    Reason the builder gave MahaRERA: “Due to pandemic project was held up due to unavailability of labour. also contractor has not worked in stipulated time, and made hurdles in progress of project. Now society has taken project in hand started work .”

Source: SWARAJ SAHANIWAS’s extension records on MahaRERA (P50500020570), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SWARAJ SAHANIWAS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P50500020570
Status
Completed
Builder
KUKADE LAYOUT (LIG)COOPERATIVE HOUSING SOCIETY LTD.
Location
Near ERA international school, Nagpur · 441122
Project type
Residential / Group Housing
Registered on
26 Apr 2019
Completion date at registration
March 2022
Latest completion date
March 2024
Delay so far
24 months
Homes
46
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of SWARAJ SAHANIWAS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SAWARAJ SAHANIWAS100%100%100%5%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SWARAJ SAHANIWAS every month.

SWARAJ SAHANIWAS: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SWARAJ SAHANIWAS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SWARAJ SAHANIWAS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SWARAJ SAHANIWAS

What is the possession date of SWARAJ SAHANIWAS?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SWARAJ SAHANIWAS in Near ERA international school, Nagpur is 30 March 2024 — 24 months later than 30 March 2022, the date given at registration.

Is the builder's possession date different from the MahaRERA date for SWARAJ SAHANIWAS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SWARAJ SAHANIWAS's builder has filed on MahaRERA, the official one, is 30 March 2024, already 24 months later than the 30 March 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SWARAJ SAHANIWAS extended?

According to GharKundli's check of MahaRERA records (updated November 2026), SWARAJ SAHANIWAS's builder applied to MahaRERA to extend the completion date 2 times: to 29 March 2023, giving the reason "Due to second wave of pandemic and temporiry lockdown and labour unavaibility further we are unable to complete the project in timeline"; to 30 March 2024, giving the reason "Due to pandemic project was held up due to unavailability of labour. also contractor has not worked in stipulated time, and made hurdles in progress of project. Now society has taken project in hand started work .".

What is the RERA number of SWARAJ SAHANIWAS?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SWARAJ SAHANIWAS in Near ERA international school, Nagpur is P50500020570.

Is SWARAJ SAHANIWAS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SWARAJ SAHANIWAS is registered as P50500020570 and its status is "Completed".

What is the construction status of SWARAJ SAHANIWAS?

According to GharKundli's check of MahaRERA records (updated November 2026), SWARAJ SAHANIWAS's status on MahaRERA is "Completed". As filed by the builder, slab work on SAWARAJ SAHANIWAS is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does SWARAJ SAHANIWAS have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is SWARAJ SAHANIWAS safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SWARAJ SAHANIWAS is registered on MahaRERA as P50500020570, its MahaRERA status is "Completed", its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SWARAJ SAHANIWAS's possession date changes?

The latest dates are on SWARAJ SAHANIWAS's MahaRERA page (P50500020570). GharKundli's Kundli Watch sends a free WhatsApp update on SWARAJ SAHANIWAS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SWARAJ SAHANIWAS have?

According to GharKundli's check of MahaRERA records (updated November 2026), SWARAJ SAHANIWAS has one building filed: SAWARAJ SAHANIWAS with 7 floors.

How big is the land of SWARAJ SAHANIWAS?

According to GharKundli's check of MahaRERA records (updated November 2026), SWARAJ SAHANIWAS stands on 1,200 sq m of land (about 0.3 acres), with 1,800 sq m of sanctioned built-up area.

Where can I read reviews of SWARAJ SAHANIWAS?

Google Maps has reviews of SWARAJ SAHANIWAS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SWARAJ SAHANIWAS?

SWARAJ SAHANIWAS by KUKADE LAYOUT (LIG)COOPERATIVE HOUSING SOCIETY LTD. is in Near ERA international school, Nagpur (pincode 441122), Maharashtra, and is registered on MahaRERA as P50500020570, per GharKundli's check of MahaRERA records.

How many homes are in SWARAJ SAHANIWAS?

According to GharKundli's check of MahaRERA records (updated November 2026), SWARAJ SAHANIWAS has 46 homes in 1 tower registered on MahaRERA.

When was SWARAJ SAHANIWAS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SWARAJ SAHANIWAS was registered on MahaRERA on 26 April 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on SWARAJ SAHANIWAS?

No court cases are listed for SWARAJ SAHANIWAS on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SWARAJ SAHANIWAS?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is KUKADE LAYOUT (LIG)COOPERATIVE HOUSING SOCIETY LTD..