by ATUL MANOHAR YAMSANWAR · Industrial Area Butibori, Nagpur 441122

What’s in the report? →

Possession date of Britain Empire (MahaRERA P50500020960): 30 December 2022, and it has already passed. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P50500020960. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P50500020960, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (December 2022) has passed.

What do you want to know about Britain Empire?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Britain Empire

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P50500020960
Status
Lapsed (registration period ended)
Builder
ATUL MANOHAR YAMSANWAR
Location
Industrial Area Butibori, Nagpur · 441122
Project type
Plotted
Registered on
27 May 2019
Completion date at registration
December 2022
Latest completion date
December 2022
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Britain Empire: buildings, flats and land, as filed on MahaRERA

  • Land: 25,511 sq m (about 6.3 acres)
  • Land, as filed: 168,169,21
  • Map: Get directions

The builder’s record and reviews

Atul Manoharrao Yamsanwar has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 67 months late); 1 lapsed. 1 complaint on MahaRERA across 1 project.

Read Google reviews of Britain Empire →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Britain Empire: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Britain Empire

What is the possession date of Britain Empire?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Britain Empire in Industrial Area Butibori, Nagpur is 30 December 2022. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Britain Empire?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Britain Empire's builder has filed on MahaRERA, the official one, is 30 December 2022, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Britain Empire?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Britain Empire in Industrial Area Butibori, Nagpur is P50500020960.

Is Britain Empire registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Britain Empire is registered as P50500020960 and its status is "Lapsed (registration period ended)".

What is the current construction status of Britain Empire? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Britain Empire's status on MahaRERA is "Lapsed (registration period ended)". GharKundli's full report compares construction progress with the deadline.

Does Britain Empire have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Britain Empire safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Britain Empire is registered on MahaRERA as P50500020960, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Britain Empire?

Britain Empire isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Britain Empire?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Britain Empire: gharkundli.com/tools/property-cost-calculator

Has Britain Empire received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Britain Empire isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 December 2022 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Britain Empire?

According to GharKundli's check of MahaRERA records (updated November 2026), Britain Empire's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 December 2022) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Britain Empire uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Britain Empire was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

Does Britain Empire have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: BRITAIN EMPIRE II (PP1190002500491, possession 12 Sep 2030). Check that your agreement names the registration of your own wing.

How can I get updates if Britain Empire's possession date changes?

The latest dates are on Britain Empire's MahaRERA page (P50500020960). GharKundli's Kundli Watch sends a free WhatsApp update on Britain Empire every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How big is the land of Britain Empire?

According to GharKundli's check of MahaRERA records (updated November 2026), Britain Empire stands on 25,511 sq m of land (about 6.3 acres).

What is the track record of Britain Empire's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Atul Manoharrao Yamsanwar has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 67 months late); 1 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

What are the reviews of Britain Empire?

Google Maps has reviews of Britain Empire written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Britain Empire?

Britain Empire by ATUL MANOHAR YAMSANWAR is in Industrial Area Butibori, Nagpur, pincode 441122, Maharashtra, and is registered on MahaRERA as P50500020960, per GharKundli's check of MahaRERA records. Its land is filed as 168,169,21. GharKundli lists all 94 MahaRERA projects in Industrial Area Butibori (441122).

When was Britain Empire registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Britain Empire was registered on MahaRERA on 27 May 2019. GharKundli did not find a title report on the land on file there.

Does Britain Empire have any legal issues or court cases?

No court cases are listed for Britain Empire on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Britain Empire?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is ATUL MANOHAR YAMSANWAR.

Other projects in Industrial Area Butibori (441122)

All 94 projects in Industrial Area Butibori (441122) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.