Possession date of UMIYA LEELA APARTMENT: 31 December 2025, moved from 30 September 2024 (15 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P50500027323. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (December 2025) has passed.

What do you want to know about UMIYA LEELA APARTMENT?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of UMIYA LEELA APARTMENT has moved

  1. 30 September 2024

    Completion date given when the project was registered

  2. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT50500024721)

    Reason the builder gave MahaRERA:
    “Due to unforeseen circumstances beyond our control, like few departmental clearances for the execution of the project, administrative procedures, Labour issues like labour shortage and Migration of labour due to govt. policy and festive sea…” Read the full reason“Due to unforeseen circumstances beyond our control, like few departmental clearances for the execution of the project, administrative procedures, Labour issues like labour shortage and Migration of labour due to govt. policy and festive season.”

Source: UMIYA LEELA APARTMENT’s extension records on MahaRERA (P50500027323), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on UMIYA LEELA APARTMENT

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P50500027323
Status
Lapsed (registration period ended)
Builder
ISHWAR DEVELOPERS
Location
Lakadganj, Nagpur · 440008
Project type
Mixed
Registered on
2 Dec 2020
Completion date at registration
September 2024
Latest completion date
December 2025
Delay so far
15 months
Homes
34
Sold or booked
50%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of UMIYA LEELA APARTMENT, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
UMIYA LEELA APARTMENT100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • UMIYA LEELA APARTMENT: covers 11 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on UMIYA LEELA APARTMENT every month.

UMIYA LEELA APARTMENT: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of UMIYA LEELA APARTMENT →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

UMIYA LEELA APARTMENT: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about UMIYA LEELA APARTMENT

What is the possession date of UMIYA LEELA APARTMENT?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for UMIYA LEELA APARTMENT in Lakadganj, Nagpur is 31 December 2025 — 15 months later than 30 September 2024, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for UMIYA LEELA APARTMENT?

Builders and listing sites often quote an earlier "target" date for handover. The completion date UMIYA LEELA APARTMENT's builder has filed on MahaRERA, the official one, is 31 December 2025, already 15 months later than the 30 September 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of UMIYA LEELA APARTMENT extended?

According to GharKundli's check of MahaRERA records (updated October 2026), UMIYA LEELA APARTMENT's builder applied to MahaRERA to extend the completion date once: to 31 December 2025, giving the reason "Due to unforeseen circumstances beyond our control, like few departmental clearances for the execution of the project, administrative procedures, Labour issues like labour shortage and Migration of labour due to govt. policy and festive season.".

What is the RERA number of UMIYA LEELA APARTMENT?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of UMIYA LEELA APARTMENT in Lakadganj, Nagpur is P50500027323.

Is UMIYA LEELA APARTMENT registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), UMIYA LEELA APARTMENT is registered as P50500027323 and its status is "Lapsed (registration period ended)".

What is the construction status of UMIYA LEELA APARTMENT?

According to GharKundli's check of MahaRERA records (updated October 2026), UMIYA LEELA APARTMENT's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on UMIYA LEELA APARTMENT is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does UMIYA LEELA APARTMENT have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is UMIYA LEELA APARTMENT safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), UMIYA LEELA APARTMENT is registered on MahaRERA as P50500027323, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 15 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if UMIYA LEELA APARTMENT's possession date changes?

The latest dates are on UMIYA LEELA APARTMENT's MahaRERA page (P50500027323). GharKundli's Kundli Watch sends a free WhatsApp update on UMIYA LEELA APARTMENT every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does UMIYA LEELA APARTMENT have?

According to GharKundli's check of MahaRERA records (updated October 2026), UMIYA LEELA APARTMENT has one building filed: UMIYA LEELA APARTMENT with 65 floors and 40 units.

How much parking does UMIYA LEELA APARTMENT have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 19 open car parking spaces for UMIYA LEELA APARTMENT.

How big is the land of UMIYA LEELA APARTMENT?

According to GharKundli's check of MahaRERA records (updated October 2026), UMIYA LEELA APARTMENT stands on 1,003 sq m of land (about 0.2 acres), with 3,010 sq m of sanctioned built-up area.

Where can I read reviews of UMIYA LEELA APARTMENT?

Google Maps has reviews of UMIYA LEELA APARTMENT written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is UMIYA LEELA APARTMENT?

UMIYA LEELA APARTMENT by ISHWAR DEVELOPERS is in Lakadganj, Nagpur (pincode 440008), near Nagpur City, Maharashtra, and is registered on MahaRERA as P50500027323, per GharKundli's check of MahaRERA records.

How many homes are in UMIYA LEELA APARTMENT?

According to GharKundli's check of MahaRERA records (updated October 2026), UMIYA LEELA APARTMENT has 34 homes in 1 tower registered on MahaRERA, and 50% of them are sold or booked.

When was UMIYA LEELA APARTMENT registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), UMIYA LEELA APARTMENT was registered on MahaRERA on 2 December 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on UMIYA LEELA APARTMENT?

No court cases are listed for UMIYA LEELA APARTMENT on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of UMIYA LEELA APARTMENT?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ISHWAR DEVELOPERS, which has 3 other projects registered on MahaRERA.

Other projects in Nagpur (Urban)

All 30 projects in Bagadganj (440008) →

Other projects by ISHWAR DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.