Sadoday Shubham
by Santdas Sadoromal Chawla · Chitnavis Layout Chindwara Road, Nagpur, NagpurAlso near Pipla, Waranga, Dombivali
Possession date of Sadoday Shubham: 30 October 2026, moved from 31 December 2025 (6 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P50500033808, and currently active. Its completion date has moved from December 2025 to October 2026: 6 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (October 2026) has passed.
What do you want to know about Sadoday Shubham?
How the possession date of Sadoday Shubham has moved
31 December 2025
Completion date given when the project was registered
30 June 2026
Extended at the builder's request (MahaRERA application EA30122519152)
Reason the builder gave MahaRERA: “Only 24% work is pending, kindly provide extension form completion of project with occupancy certificate.”
30 October 2026
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Sadoday Shubham’s extension records on MahaRERA (P50500033808), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Sadoday Shubham
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P50500033808
- Status
- Registered and active
- Builder
- Santdas Sadoromal Chawla
- Location
- Chitnavis Layout Chindwara Road, Nagpur, Nagpur · 440013
- Project type
- Residential / Group Housing
- Registered on
- 8 Mar 2022
- Completion date at registration
- December 2025
- Latest completion date
- October 2026
- Delay so far
- 6 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 15
- Sold or booked
- 47%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Sadoday Shubham, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Sadoday Shubham | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- Sadoday Shubham: covers 6 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sadoday Shubham every month.
Sadoday Shubham: buildings, flats and land, as filed on MahaRERA
- Buildings: Sadoday Shubham (7 floors, 15 units)
- Land: 713 sq m (about 0.2 acres) · sanctioned built-up 2,280 sq m
- Boundaries filed include: NMC Ground
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Sadoday Shubham →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Sadoday Shubham: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Sadoday Shubham
What is the possession date of Sadoday Shubham?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sadoday Shubham in Chitnavis Layout Chindwara Road, Nagpur, Nagpur is 30 October 2026 — 6 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Sadoday Shubham?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Sadoday Shubham's builder has filed on MahaRERA, the official one, is 30 October 2026, already 6 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Sadoday Shubham extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Sadoday Shubham's builder applied to MahaRERA to extend the completion date once: to 30 June 2026, giving the reason "Only 24% work is pending, kindly provide extension form completion of project with occupancy certificate.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Sadoday Shubham?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sadoday Shubham in Chitnavis Layout Chindwara Road, Nagpur, Nagpur is P50500033808.
Is Sadoday Shubham registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sadoday Shubham is registered as P50500033808 and its status is "Registered and active".
What is the construction status of Sadoday Shubham?
According to GharKundli's check of MahaRERA records (updated October 2026), Sadoday Shubham's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Sadoday Shubham is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Sadoday Shubham have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Sadoday Shubham safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Sadoday Shubham is registered on MahaRERA as P50500033808, its completion date has moved 6 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Sadoday Shubham's possession date changes?
The latest dates are on Sadoday Shubham's MahaRERA page (P50500033808). GharKundli's Kundli Watch sends a free WhatsApp update on Sadoday Shubham every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Sadoday Shubham have?
According to GharKundli's check of MahaRERA records (updated October 2026), Sadoday Shubham has one building filed: Sadoday Shubham with 7 floors and 15 units.
How big is the land of Sadoday Shubham?
According to GharKundli's check of MahaRERA records (updated October 2026), Sadoday Shubham stands on 713 sq m of land (about 0.2 acres), with 2,280 sq m of sanctioned built-up area.
Where can I read reviews of Sadoday Shubham?
Google Maps has reviews of Sadoday Shubham written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Sadoday Shubham?
Sadoday Shubham by Santdas Sadoromal Chawla is in Chitnavis Layout Chindwara Road, Nagpur, Nagpur (pincode 440013), near Pipla, Waranga, Dombivali, Maharashtra, and is registered on MahaRERA as P50500033808, per GharKundli's check of MahaRERA records. Its boundaries filed there include NMC Ground.
How many homes are in Sadoday Shubham?
According to GharKundli's check of MahaRERA records (updated October 2026), Sadoday Shubham has 15 homes in 1 tower registered on MahaRERA, and 47% of them are sold or booked.
When was Sadoday Shubham registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sadoday Shubham was registered on MahaRERA on 8 March 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on Sadoday Shubham?
No court cases are listed for Sadoday Shubham on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Sadoday Shubham?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Santdas Sadoromal Chawla.
Check it yourself on MahaRERA
- How to check the possession date of Sadoday Shubham
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Nagpur →
Other projects in Nagpur (Urban)
- ROYAL PARK
- GLOCAL SQUARE 3 RD FLOOR
- SHREE APARTMENTS
- Mithila Apartment
- EMPRESS ROYAL EFGH
- ROYAL PRIDE
- Devotie
- Swapnapurtee - A Project by NMC
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.