by JARRY INFRACON · Mauja-Bhokara, NagpurAlso near Godhani

Possession date of SILVER VALLEY: 31 December 2028, moved from 31 December 2025 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P50500031811, and currently active.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SILVER VALLEY?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SILVER VALLEY has moved

  1. 31 December 2025

    Completion date given when the project was registered

  2. 31 December 2028

    Extended at the builder's request (MahaRERA application EA30122519139)

    Reason the builder gave MahaRERA:
    “Sir/Madam, We, JARRY INFRACON, Promoter of the real estate project “SILVER VALLEY”, bearing MahaRERA Registration No. P50500031811, respectfully submit this application seeking extension of project registration validity for a further period…” Read the full reason“Sir/Madam, We, JARRY INFRACON, Promoter of the real estate project “SILVER VALLEY”, bearing MahaRERA Registration No. P50500031811, respectfully submit this application seeking extension of project registration validity for a further period of three (3) years. The present validity of the project is up to 31st December 2025. The project could not be completed within the stipulated timeline due to unavoidable and genuine reasons beyond the control of the Promoter, including delay in statutory approvals, dependence on external infrastructure works by local authorities, shortage of skilled manp…”

Source: SILVER VALLEY’s extension records on MahaRERA (P50500031811), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SILVER VALLEY

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P50500031811
Status
Registered and active
Builder
JARRY INFRACON
Location
Mauja-Bhokara, Nagpur · 441111
Project type
Residential / Group Housing
Registered on
12 Nov 2021
Completion date at registration
December 2025
Latest completion date
December 2028
Delay so far
36 months
Homes
120
Sold or booked
54%
Towers
22
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of SILVER VALLEY, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SILVER VALLEY PLOT NO 22100%100%100%0%
SILVER VALLEY PLOT NO 4100%100%100%0%
SILVER VALLEY PLOT NO 5100%100%100%0%
SILVER VALLEY PLOT NO 6100%100%100%0%
SILVER VALLEY PLOT NO 7100%100%100%0%
SILVER VALLEY PLOT NO 8100%100%100%0%
SILVER VALLEY PLOT NO 9100%100%100%0%
SILVER VALLEY PLOT NO 10100%100%100%0%
SILVER VALLEY PLOT NO 120%0%0%0%
SILVER VALLEY PLOT NO 19100%100%100%0%
SILVER VALLEY PLOT NO 20100%100%100%0%
SILVER VALLEY PLOT NO 21100%100%100%0%
SILVER VALLEY PLOT NO 1100%100%92%62%
SILVER VALLEY PLOT NO 2100%100%100%0%
SILVER VALLEY PLOT NO 3100%100%100%0%
SILVER VALLEY PLOT NO 11100%100%100%0%
SILVER VALLEY PLOT NO 13100%100%100%0%
SILVER VALLEY PLOT NO 14100%100%100%0%
SILVER VALLEY PLOT NO 15100%100%100%0%
SILVER VALLEY PLOT NO 16100%100%100%0%
SILVER VALLEY PLOT NO 17100%100%100%0%
SILVER VALLEY PLOT NO 18100%100%100%0%

Commencement certificate (CC), as filed on MahaRERA

  • SILVER VALLEY PLOT NO 22: covers 2 floors
  • SILVER VALLEY PLOT NO 4: covers 2 floors
  • SILVER VALLEY PLOT NO 5: covers 2 floors
  • SILVER VALLEY PLOT NO 6: covers 2 floors
  • SILVER VALLEY PLOT NO 7: covers 2 floors
  • SILVER VALLEY PLOT NO 8: covers 2 floors
  • SILVER VALLEY PLOT NO 9: covers 2 floors
  • SILVER VALLEY PLOT NO 10: covers 2 floors
  • SILVER VALLEY PLOT NO 12: covers 2 floors
  • SILVER VALLEY PLOT NO 19: covers 2 floors
  • SILVER VALLEY PLOT NO 20: covers 2 floors
  • SILVER VALLEY PLOT NO 21: covers 2 floors
  • SILVER VALLEY PLOT NO 1: covers 11 floors
  • SILVER VALLEY PLOT NO 2: covers 2 floors
  • SILVER VALLEY PLOT NO 3: covers 2 floors
  • SILVER VALLEY PLOT NO 11: covers 2 floors
  • SILVER VALLEY PLOT NO 13: covers 2 floors
  • SILVER VALLEY PLOT NO 14: covers 2 floors
  • SILVER VALLEY PLOT NO 15: covers 2 floors
  • SILVER VALLEY PLOT NO 16: covers 2 floors
  • SILVER VALLEY PLOT NO 17: covers 2 floors
  • SILVER VALLEY PLOT NO 18: covers 2 floors

Latest CC order on MahaRERA: dated 28/06/2022.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SILVER VALLEY every month.

SILVER VALLEY: buildings, flats and land, as filed on MahaRERA

  • Buildings: SILVER VALLEY PLOT NO 22 (2 floors, 1 units) · SILVER VALLEY PLOT NO 4 (2 floors, 1 units) · SILVER VALLEY PLOT NO 5 (2 floors, 1 units) · SILVER VALLEY PLOT NO 6 (2 floors, 1 units) · SILVER VALLEY PLOT NO 7 (2 floors, 1 units) · SILVER VALLEY PLOT NO 8 (2 floors, 1 units) · SILVER VALLEY PLOT NO 9 (2 floors, 1 units) · SILVER VALLEY PLOT NO 10 (2 floors, 1 units) · and 14 more
  • Land: 5,937 sq m (about 1.5 acres) · sanctioned built-up 12,409 sq m · recreational space 809 sq m
  • Boundaries filed include: RAILWAY LINE
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SILVER VALLEY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SILVER VALLEY: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SILVER VALLEY

What is the possession date of SILVER VALLEY?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SILVER VALLEY in Mauja-Bhokara, Nagpur is 31 December 2028 — 36 months later than 31 December 2025, the date given at registration.

Is the builder's possession date different from the MahaRERA date for SILVER VALLEY?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SILVER VALLEY's builder has filed on MahaRERA, the official one, is 31 December 2028, already 36 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SILVER VALLEY extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SILVER VALLEY's builder applied to MahaRERA to extend the completion date once: to 31 December 2028, giving the reason "Sir/Madam, We, JARRY INFRACON, Promoter of the real estate project “SILVER VALLEY”, bearing MahaRERA Registration No. P50500031811, respectfully submit this application seeking extension of project registration validity for a further period of three (3) years. The present validity of the project is up to 31st December 2025. The project could not be completed within the stipulated timeline due to unavoidable and genuine reasons beyond the control of the Promoter, including delay in statutory approvals, dependence on external infrastructure works by local authorities, shortage of skilled manp…".

What is the RERA number of SILVER VALLEY?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SILVER VALLEY in Mauja-Bhokara, Nagpur is P50500031811.

Is SILVER VALLEY registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SILVER VALLEY is registered as P50500031811 and its status is "Registered and active".

What is the construction status of SILVER VALLEY?

According to GharKundli's check of MahaRERA records (updated October 2026), SILVER VALLEY's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 22 towers. GharKundli's full report compares construction progress with the deadline.

Does SILVER VALLEY have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is SILVER VALLEY safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SILVER VALLEY is registered on MahaRERA as P50500031811, its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SILVER VALLEY's possession date changes?

The latest dates are on SILVER VALLEY's MahaRERA page (P50500031811). GharKundli's Kundli Watch sends a free WhatsApp update on SILVER VALLEY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SILVER VALLEY have?

According to GharKundli's check of MahaRERA records (updated October 2026), SILVER VALLEY has 22 buildings filed: SILVER VALLEY PLOT NO 22 with 2 floors and 1 units; SILVER VALLEY PLOT NO 4 with 2 floors and 1 units; SILVER VALLEY PLOT NO 5 with 2 floors and 1 units; SILVER VALLEY PLOT NO 6 with 2 floors and 1 units; SILVER VALLEY PLOT NO 7 with 2 floors and 1 units; SILVER VALLEY PLOT NO 8 with 2 floors and 1 units; and 16 more.

How big is the land of SILVER VALLEY?

According to GharKundli's check of MahaRERA records (updated October 2026), SILVER VALLEY stands on 5,937 sq m of land (about 1.5 acres), with 12,409 sq m of sanctioned built-up area and 809 sq m of recreational open space.

Where can I read reviews of SILVER VALLEY?

Google Maps has reviews of SILVER VALLEY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SILVER VALLEY?

SILVER VALLEY by JARRY INFRACON is in Mauja-Bhokara, Nagpur (pincode 441111), near Godhani, Maharashtra, and is registered on MahaRERA as P50500031811, per GharKundli's check of MahaRERA records. Its boundaries filed there include RAILWAY LINE.

How many homes are in SILVER VALLEY?

According to GharKundli's check of MahaRERA records (updated October 2026), SILVER VALLEY has 120 homes in 22 towers registered on MahaRERA, and 54% of them are sold or booked.

When was SILVER VALLEY registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SILVER VALLEY was registered on MahaRERA on 12 November 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on SILVER VALLEY?

No court cases are listed for SILVER VALLEY on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of SILVER VALLEY?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is JARRY INFRACON.

All projects with possession due in 2028 in Nagpur →

Other projects in Nagpur (Urban)

All 34 projects in Koradi Tps (441111) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.