by NAYAK BROTHERS · Umred Project, Nagpur

Possession date of NEELKANTH NAGAR: 31 December 2027, moved from 30 December 2025 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P50500032913, and currently active. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about NEELKANTH NAGAR?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of NEELKANTH NAGAR has moved

  1. 30 December 2025

    Completion date given when the project was registered

  2. 31 December 2027

    Extended at the builder's request (MahaRERA application EA21022619939)

    Reason the builder gave MahaRERA: “WE ARE FACING CHALLANGE OF CUSTOMER BOOKING SO WE ARE UNABLE TO COMPLETE THE PROJECT FOR DUE PERIOD I.E 30/12/2025. WE HAVE COMMENCEMENT OF 02/02/2022. WE REQUEST YOU TO KINDLY GIVE US THE EXTENSION U/S 7(3) FOR FURTHER DATE I.E 31/12/2027”

Source: NEELKANTH NAGAR’s extension records on MahaRERA (P50500032913), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on NEELKANTH NAGAR

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the December 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P50500032913
Status
Registered and active
Builder
NAYAK BROTHERS
Location
Umred Project, Nagpur · 441204
Project type
Plotted
Registered on
2 Feb 2022
Completion date at registration
December 2025
Latest completion date
December 2027
Delay so far
24 months
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found

NEELKANTH NAGAR: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of NEELKANTH NAGAR →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

NEELKANTH NAGAR: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about NEELKANTH NAGAR

What is the possession date of NEELKANTH NAGAR?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for NEELKANTH NAGAR in Umred Project, Nagpur is 31 December 2027 — 24 months later than 30 December 2025, the date given at registration.

Is the builder's possession date different from the MahaRERA date for NEELKANTH NAGAR?

Builders and listing sites often quote an earlier "target" date for handover. The completion date NEELKANTH NAGAR's builder has filed on MahaRERA, the official one, is 31 December 2027, already 24 months later than the 30 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of NEELKANTH NAGAR extended?

According to GharKundli's check of MahaRERA records (updated October 2026), NEELKANTH NAGAR's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "WE ARE FACING CHALLANGE OF CUSTOMER BOOKING SO WE ARE UNABLE TO COMPLETE THE PROJECT FOR DUE PERIOD I.E 30/12/2025. WE HAVE COMMENCEMENT OF 02/02/2022. WE REQUEST YOU TO KINDLY GIVE US THE EXTENSION U/S 7(3) FOR FURTHER DATE I.E 31/12/2027".

What is the RERA number of NEELKANTH NAGAR?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of NEELKANTH NAGAR in Umred Project, Nagpur is P50500032913.

Is NEELKANTH NAGAR registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), NEELKANTH NAGAR is registered as P50500032913 and its status is "Registered and active".

What is the construction status of NEELKANTH NAGAR?

According to GharKundli's check of MahaRERA records (updated October 2026), NEELKANTH NAGAR's status on MahaRERA is "Registered and active". GharKundli's full report compares construction progress with the deadline.

Does NEELKANTH NAGAR have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is NEELKANTH NAGAR safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), NEELKANTH NAGAR is registered on MahaRERA as P50500032913, its completion date has moved 24 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if NEELKANTH NAGAR's possession date changes?

The latest dates are on NEELKANTH NAGAR's MahaRERA page (P50500032913). GharKundli's Kundli Watch sends a free WhatsApp update on NEELKANTH NAGAR every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How big is the land of NEELKANTH NAGAR?

According to GharKundli's check of MahaRERA records (updated October 2026), NEELKANTH NAGAR stands on 18,399 sq m of land (about 4.5 acres) and 1,024 sq m of recreational open space.

Where can I read reviews of NEELKANTH NAGAR?

Google Maps has reviews of NEELKANTH NAGAR written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is NEELKANTH NAGAR?

NEELKANTH NAGAR by NAYAK BROTHERS is in Umred Project, Nagpur (pincode 441204), Maharashtra, and is registered on MahaRERA as P50500032913, per GharKundli's check of MahaRERA records.

When was NEELKANTH NAGAR registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), NEELKANTH NAGAR was registered on MahaRERA on 2 February 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on NEELKANTH NAGAR?

No court cases are listed for NEELKANTH NAGAR on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of NEELKANTH NAGAR?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is NAYAK BROTHERS.

All projects with possession due in 2027 in Nagpur →

Other projects in pincode 441204

All 47 projects in Umred Project (441204) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.