SANDHYARANG APARTMENTS

by AARYA ASSOCIATES · Deendayal Nagar, Nagpur

Possession: SANDHYARANG APARTMENTS is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P50500033288. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about SANDHYARANG APARTMENTS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SANDHYARANG APARTMENTS has moved

  1. 31 December 2022

    Completion date given when the project was registered

  2. 30 June 2023

    Extended at the builder's request (MahaRERA application EXT50500013633)

    Reason the builder gave MahaRERA: “occupancy certificate yet to come”

Source: SANDHYARANG APARTMENTS’s extension records on MahaRERA (P50500033288), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SANDHYARANG APARTMENTS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P50500033288
Status
Completed
Builder
AARYA ASSOCIATES
Location
Deendayal Nagar, Nagpur · 440022
Project type
Residential / Group Housing
Registered on
15 Feb 2022
Completion date at registration
December 2022
Latest completion date
June 2023
Delay so far
6 months
Homes
10
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of SANDHYARANG APARTMENTS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SANDHYARANG APARTMENTS100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SANDHYARANG APARTMENTS every month.

SANDHYARANG APARTMENTS: buildings, flats and land, as filed on MahaRERA

  • Buildings: SANDHYARANG APARTMENTS (6 floors)
  • Land: 360 sq m (about 0.1 acres) · sanctioned built-up 922 sq m

The builder’s record and reviews

Aarya Associates has 3 projects on MahaRERA since 2022, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 4 months); 2 still being built, 1 past the promised date (typically 22 months late). No complaints on MahaRERA.

Read Google reviews of SANDHYARANG APARTMENTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SANDHYARANG APARTMENTS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SANDHYARANG APARTMENTS

What is the possession date of SANDHYARANG APARTMENTS?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SANDHYARANG APARTMENTS in Deendayal Nagar, Nagpur is 30 June 2023 — 6 months later than 31 December 2022, the date given at registration.

Is the builder's possession date different from the MahaRERA date for SANDHYARANG APARTMENTS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SANDHYARANG APARTMENTS's builder has filed on MahaRERA, the official one, is 30 June 2023, already 6 months later than the 31 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SANDHYARANG APARTMENTS extended?

According to GharKundli's check of MahaRERA records (updated November 2026), SANDHYARANG APARTMENTS's builder applied to MahaRERA to extend the completion date once: to 30 June 2023, giving the reason "occupancy certificate yet to come".

What is the RERA number of SANDHYARANG APARTMENTS?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SANDHYARANG APARTMENTS in Deendayal Nagar, Nagpur is P50500033288.

Is SANDHYARANG APARTMENTS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SANDHYARANG APARTMENTS is registered as P50500033288 and its status is "Completed".

What is the construction status of SANDHYARANG APARTMENTS?

According to GharKundli's check of MahaRERA records (updated November 2026), SANDHYARANG APARTMENTS's status on MahaRERA is "Completed". As filed by the builder, slab work on SANDHYARANG APARTMENTS is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does SANDHYARANG APARTMENTS have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is SANDHYARANG APARTMENTS safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SANDHYARANG APARTMENTS is registered on MahaRERA as P50500033288, its MahaRERA status is "Completed", its completion date has moved 6 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SANDHYARANG APARTMENTS's possession date changes?

The latest dates are on SANDHYARANG APARTMENTS's MahaRERA page (P50500033288). GharKundli's Kundli Watch sends a free WhatsApp update on SANDHYARANG APARTMENTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SANDHYARANG APARTMENTS have?

According to GharKundli's check of MahaRERA records (updated November 2026), SANDHYARANG APARTMENTS has one building filed: SANDHYARANG APARTMENTS with 6 floors.

How big is the land of SANDHYARANG APARTMENTS?

According to GharKundli's check of MahaRERA records (updated November 2026), SANDHYARANG APARTMENTS stands on 360 sq m of land (about 0.1 acres), with 922 sq m of sanctioned built-up area.

What is the track record of SANDHYARANG APARTMENTS's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Aarya Associates has 3 projects on MahaRERA since 2022, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 4 months); 2 still being built, 1 past the promised date (typically 22 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SANDHYARANG APARTMENTS?

Google Maps has reviews of SANDHYARANG APARTMENTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SANDHYARANG APARTMENTS?

SANDHYARANG APARTMENTS by AARYA ASSOCIATES is in Deendayal Nagar, Nagpur (pincode 440022), Maharashtra, and is registered on MahaRERA as P50500033288, per GharKundli's check of MahaRERA records.

How many homes are in SANDHYARANG APARTMENTS?

According to GharKundli's check of MahaRERA records (updated November 2026), SANDHYARANG APARTMENTS has 10 homes in 1 tower registered on MahaRERA.

When was SANDHYARANG APARTMENTS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SANDHYARANG APARTMENTS was registered on MahaRERA on 15 February 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on SANDHYARANG APARTMENTS?

No court cases are listed for SANDHYARANG APARTMENTS on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SANDHYARANG APARTMENTS?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is AARYA ASSOCIATES, which has 2 other projects registered on MahaRERA.

Other projects in Nagpur (Urban)

All 52 projects in Ranapratap Nagar (440022) →

Other projects by AARYA ASSOCIATES

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.