Skip to content
GharKundli

SHYAMSUNDARRESIDENCY 8

by SHYAMSUNDAR REALTY · Omkar Ngr, NagpurAlso near Pipla, Waranga, Dombivali

Possession date of SHYAMSUNDARRESIDENCY 8: 31 July 2023, moved from 30 January 2023 (6 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P50500033453. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (July 2023) has passed.

What do you want to know about SHYAMSUNDARRESIDENCY 8?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SHYAMSUNDARRESIDENCY 8 has moved

  1. 30 January 2023

    Completion date given when the project was registered

  2. 31 July 2023

    Extended at the builder's request (MahaRERA application EXT50500015449)

    Reason the builder gave MahaRERA: “PROJECT WORKALMOST COMPLETED, APPLIED FOR OCCUPENCY CERTIFICATE TO OUR SANCTIONING AUTHORITY NAGPUR IMPROVEMENT TRUST. OCCUPENCY CERTIFICATE IS UNDE PROCESS WHICH WE WILL RECEIVE WITHIN 15 DAYS.”

Source: SHYAMSUNDARRESIDENCY 8’s extension records on MahaRERA (P50500033453), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SHYAMSUNDARRESIDENCY 8

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P50500033453
Status
Lapsed (registration period ended)
Builder
SHYAMSUNDAR REALTY
Location
Omkar Ngr, Nagpur · 440027
Project type
Residential / Group Housing
Registered on
22 Feb 2022
Completion date at registration
January 2023
Latest completion date
July 2023
Delay so far
6 months
Homes
10
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of SHYAMSUNDARRESIDENCY 8, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SHYAMSUNDAR RESIDENCY 8100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHYAMSUNDARRESIDENCY 8 every month.

SHYAMSUNDARRESIDENCY 8: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SHYAMSUNDARRESIDENCY 8 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SHYAMSUNDARRESIDENCY 8: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SHYAMSUNDARRESIDENCY 8

What is the possession date of SHYAMSUNDARRESIDENCY 8?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SHYAMSUNDARRESIDENCY 8 in Omkar Ngr, Nagpur is 31 July 2023 — 6 months later than 30 January 2023, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for SHYAMSUNDARRESIDENCY 8?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SHYAMSUNDARRESIDENCY 8's builder has filed on MahaRERA, the official one, is 31 July 2023, already 6 months later than the 30 January 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SHYAMSUNDARRESIDENCY 8 extended?

According to GharKundli's check of MahaRERA records (updated November 2026), SHYAMSUNDARRESIDENCY 8's builder applied to MahaRERA to extend the completion date once: to 31 July 2023, giving the reason "PROJECT WORKALMOST COMPLETED, APPLIED FOR OCCUPENCY CERTIFICATE TO OUR SANCTIONING AUTHORITY NAGPUR IMPROVEMENT TRUST. OCCUPENCY CERTIFICATE IS UNDE PROCESS WHICH WE WILL RECEIVE WITHIN 15 DAYS.".

What is the RERA number of SHYAMSUNDARRESIDENCY 8?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SHYAMSUNDARRESIDENCY 8 in Omkar Ngr, Nagpur is P50500033453.

Is SHYAMSUNDARRESIDENCY 8 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SHYAMSUNDARRESIDENCY 8 is registered as P50500033453 and its status is "Lapsed (registration period ended)".

What is the construction status of SHYAMSUNDARRESIDENCY 8?

According to GharKundli's check of MahaRERA records (updated November 2026), SHYAMSUNDARRESIDENCY 8's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SHYAMSUNDAR RESIDENCY 8 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does SHYAMSUNDARRESIDENCY 8 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is SHYAMSUNDARRESIDENCY 8 safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SHYAMSUNDARRESIDENCY 8 is registered on MahaRERA as P50500033453, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 6 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SHYAMSUNDARRESIDENCY 8's possession date changes?

The latest dates are on SHYAMSUNDARRESIDENCY 8's MahaRERA page (P50500033453). GharKundli's Kundli Watch sends a free WhatsApp update on SHYAMSUNDARRESIDENCY 8 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SHYAMSUNDARRESIDENCY 8 have?

According to GharKundli's check of MahaRERA records (updated November 2026), SHYAMSUNDARRESIDENCY 8 has one building filed: SHYAMSUNDAR RESIDENCY 8 with 12 floors.

How big is the land of SHYAMSUNDARRESIDENCY 8?

According to GharKundli's check of MahaRERA records (updated November 2026), SHYAMSUNDARRESIDENCY 8 stands on 367 sq m of land (about 0.1 acres), with 1,055 sq m of sanctioned built-up area.

Where can I read reviews of SHYAMSUNDARRESIDENCY 8?

Google Maps has reviews of SHYAMSUNDARRESIDENCY 8 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SHYAMSUNDARRESIDENCY 8?

SHYAMSUNDARRESIDENCY 8 by SHYAMSUNDAR REALTY is in Omkar Ngr, Nagpur (pincode 440027), near Pipla, Waranga, Dombivali, Maharashtra, and is registered on MahaRERA as P50500033453, per GharKundli's check of MahaRERA records.

How many homes are in SHYAMSUNDARRESIDENCY 8?

According to GharKundli's check of MahaRERA records (updated November 2026), SHYAMSUNDARRESIDENCY 8 has 10 homes in 1 tower registered on MahaRERA.

When was SHYAMSUNDARRESIDENCY 8 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SHYAMSUNDARRESIDENCY 8 was registered on MahaRERA on 22 February 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on SHYAMSUNDARRESIDENCY 8?

No court cases are listed for SHYAMSUNDARRESIDENCY 8 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SHYAMSUNDARRESIDENCY 8?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHYAMSUNDAR REALTY, which has 2 other projects registered on MahaRERA.

Other projects in Nagpur (Urban)

All 16 projects in Parvati Nagar (440027) →

Other projects by SHYAMSUNDAR REALTY

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.