Skip to content
GharKundli

Sunrise Orlem 2B Phase 3

by Dhaval Housing AOP · Santacruz West, MumbaiAlso near malad east, Kurar Village, Dindoshi

Possession: Sunrise Orlem 2B Phase 3 is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800006843. Status: Completed. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Sunrise Orlem 2B Phase 3?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Sunrise Orlem 2B Phase 3 has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 30 June 2022

    Extended at the builder's request (MahaRERA application EXT51800009530)

    Reason the builder gave MahaRERA:
    “Our project timelines have severely been affected due to the global pandemic, resulting in a delayed approval process by the department. Our final approval for the tower has been received, which has been attached. We would want you to also…” Read the full reason“Our project timelines have severely been affected due to the global pandemic, resulting in a delayed approval process by the department. Our final approval for the tower has been received, which has been attached. We would want you to also acknowledge the sluggish real estate market due to which the approvals had been delayed, followed by the global pandemic, overall leading to a delay for which would like to seek extension.”
  3. 31 December 2023

    Extended at the builder's request (MahaRERA application EXT51800012861)

    Reason the builder gave MahaRERA: “The delay is on account of hardships due to covid situation and site condition.”

Source: Sunrise Orlem 2B Phase 3’s extension records on MahaRERA (P51800006843), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Sunrise Orlem 2B Phase 3

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint and 1 court case, and how it ended
  • Construction pace against the December 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51800006843
Status
Completed
Builder
Dhaval Housing AOP
Location
Santacruz West, Mumbai · 400097
Project type
Residential / Group Housing
Registered on
16 Aug 2017
Completion date at registration
June 2021
Latest completion date
December 2023
Delay so far
30 months
Homes
42
Towers
1
Complaints on MahaRERA
1
Court cases listed
1
Title report on file
Not found
Builder's other MahaRERA projects
4

Construction progress of Sunrise Orlem 2B Phase 3, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Sunrise Orlem 2B100%100%60%95%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sunrise Orlem 2B Phase 3 every month.

Sunrise Orlem 2B Phase 3: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Dhaval Housing AOP has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 5 finished, 2 within the promised date and 3 needed more time (typically 18 months). 1 complaint on MahaRERA across 1 project.

Read Google reviews of Sunrise Orlem 2B Phase 3 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Sunrise Orlem 2B Phase 3: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Sunrise Orlem 2B Phase 3

What is the possession date of Sunrise Orlem 2B Phase 3?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Sunrise Orlem 2B Phase 3 in Santacruz West, Mumbai is 31 December 2023 — 30 months later than 30 June 2021, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Sunrise Orlem 2B Phase 3?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Sunrise Orlem 2B Phase 3's builder has filed on MahaRERA, the official one, is 31 December 2023, already 30 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Sunrise Orlem 2B Phase 3 extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Sunrise Orlem 2B Phase 3's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2022, giving the reason "Our project timelines have severely been affected due to the global pandemic, resulting in a delayed approval process by the department. Our final approval for the tower has been received, which has been attached. We would want you to also acknowledge the sluggish real estate market due to which the approvals had been delayed, followed by the global pandemic, overall leading to a delay for which would like to seek extension."; to 31 December 2023, giving the reason "The delay is on account of hardships due to covid situation and site condition.".

What is the RERA number of Sunrise Orlem 2B Phase 3?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Sunrise Orlem 2B Phase 3 in Santacruz West, Mumbai is P51800006843.

Is Sunrise Orlem 2B Phase 3 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Sunrise Orlem 2B Phase 3 is registered as P51800006843 and its status is "Completed".

What is the construction status of Sunrise Orlem 2B Phase 3?

According to GharKundli's check of MahaRERA records (updated November 2026), Sunrise Orlem 2B Phase 3's status on MahaRERA is "Completed". As filed by the builder, slab work on Sunrise Orlem 2B is 100% done and internal work 60%. GharKundli's full report compares construction progress with the deadline.

Does Sunrise Orlem 2B Phase 3 have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Sunrise Orlem 2B Phase 3 safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Sunrise Orlem 2B Phase 3 is registered on MahaRERA as P51800006843, its MahaRERA status is "Completed", its completion date has moved 30 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Sunrise Orlem 2B Phase 3 have other wings or phases?

Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: Sunrise Orlem 2A Phase 1 (P51800007706, possession 31 Jan 2023); Sunrise Orlem Building 4 (P51800007714, possession 31 Dec 2019). Check that your agreement names the registration of your own wing.

How can I get updates if Sunrise Orlem 2B Phase 3's possession date changes?

The latest dates are on Sunrise Orlem 2B Phase 3's MahaRERA page (P51800006843). GharKundli's Kundli Watch sends a free WhatsApp update on Sunrise Orlem 2B Phase 3 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Sunrise Orlem 2B Phase 3 have?

According to GharKundli's check of MahaRERA records (updated November 2026), Sunrise Orlem 2B Phase 3 has one building filed: Sunrise Orlem 2B with 24 floors.

How big is the land of Sunrise Orlem 2B Phase 3?

According to GharKundli's check of MahaRERA records (updated November 2026), Sunrise Orlem 2B Phase 3 stands on 225 sq m of land (about 0.1 acres), with 1,469 sq m of sanctioned built-up area and 735 sq m of recreational open space.

What is the track record of Sunrise Orlem 2B Phase 3's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Dhaval Housing AOP has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 5 finished, 2 within the promised date and 3 needed more time (typically 18 months). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Sunrise Orlem 2B Phase 3?

Google Maps has reviews of Sunrise Orlem 2B Phase 3 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Sunrise Orlem 2B Phase 3?

Sunrise Orlem 2B Phase 3 by Dhaval Housing AOP is in Santacruz West, Mumbai (pincode 400097), near malad east, Kurar Village, Dindoshi, Maharashtra, and is registered on MahaRERA as P51800006843, per GharKundli's check of MahaRERA records.

How many homes are in Sunrise Orlem 2B Phase 3?

According to GharKundli's check of MahaRERA records (updated November 2026), Sunrise Orlem 2B Phase 3 has 42 homes in 1 tower registered on MahaRERA.

When was Sunrise Orlem 2B Phase 3 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Sunrise Orlem 2B Phase 3 was registered on MahaRERA on 16 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Sunrise Orlem 2B Phase 3?

1 court case is listed for Sunrise Orlem 2B Phase 3 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Sunrise Orlem 2B Phase 3?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Dhaval Housing AOP, which has 4 other projects registered on MahaRERA.

Other projects in Santacruz West

All 195 projects in Malad East (400097) →

Other projects by Dhaval Housing AOP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.