Transcon Fortune 500 Tower 1
by Samta Builders Pvt. Ltd. · Mulund West, MumbaiAlso near Wagle I.E
Possession date of Transcon Fortune 500 Tower 1: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800012431, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 9 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Transcon Fortune 500 Tower 1?
How the possession date of Transcon Fortune 500 Tower 1 has moved
30 December 2026
Completion date given when the project was registered
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Transcon Fortune 500 Tower 1’s extension records on MahaRERA (P51800012431), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Transcon Fortune 500 Tower 1
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 9 complaints and 12 court cases, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800012431
- Status
- Registered and active
- Builder
- Samta Builders Pvt. Ltd.
- Location
- Mulund West, Mumbai · 400080
- Project type
- Residential / Group Housing
- Registered on
- 1 Sep 2017
- Completion date at registration
- December 2026
- Latest completion date
- April 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 265
- Sold or booked
- 24%
- Towers
- 1
- Complaints on MahaRERA
- 9
- Court cases listed
- 12
- Appeals at the tribunal
- 2
- Title report on file
- Not found
Construction progress of Transcon Fortune 500 Tower 1, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Transcon Fortune 500 Tower 1 | 100% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Transcon Fortune 500 Tower 1: covers PLINTH LEVEL
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Transcon Fortune 500 Tower 1 every month.
Transcon Fortune 500 Tower 1: buildings, flats and land, as filed on MahaRERA
- Buildings: Transcon Fortune 500 Tower 1 (69 floors, 265 units)
- Car parking: 399 covered
- Land: 690 sq m (about 0.2 acres)
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Transcon Fortune 500 Tower 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Transcon Fortune 500 Tower 1: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Transcon Fortune 500 Tower 1
What is the possession date of Transcon Fortune 500 Tower 1?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Transcon Fortune 500 Tower 1 in Mulund West, Mumbai is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Transcon Fortune 500 Tower 1?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Transcon Fortune 500 Tower 1's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Transcon Fortune 500 Tower 1?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Transcon Fortune 500 Tower 1 in Mulund West, Mumbai is P51800012431.
Is Transcon Fortune 500 Tower 1 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Transcon Fortune 500 Tower 1 is registered as P51800012431 and its status is "Registered and active".
What is the construction status of Transcon Fortune 500 Tower 1?
According to GharKundli's check of MahaRERA records (updated November 2026), Transcon Fortune 500 Tower 1's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Transcon Fortune 500 Tower 1 is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Transcon Fortune 500 Tower 1 have complaints on MahaRERA?
9 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Transcon Fortune 500 Tower 1 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Transcon Fortune 500 Tower 1 is registered on MahaRERA as P51800012431, its completion date has not been moved by the builder and 9 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Transcon Fortune 500 Tower 1's possession date changes?
The latest dates are on Transcon Fortune 500 Tower 1's MahaRERA page (P51800012431). GharKundli's Kundli Watch sends a free WhatsApp update on Transcon Fortune 500 Tower 1 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Transcon Fortune 500 Tower 1 have?
According to GharKundli's check of MahaRERA records (updated November 2026), Transcon Fortune 500 Tower 1 has one building filed: Transcon Fortune 500 Tower 1 with 69 floors and 265 units.
How much parking does Transcon Fortune 500 Tower 1 have?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 399 covered car parking spaces for Transcon Fortune 500 Tower 1.
How big is the land of Transcon Fortune 500 Tower 1?
According to GharKundli's check of MahaRERA records (updated November 2026), Transcon Fortune 500 Tower 1 stands on 690 sq m of land (about 0.2 acres).
Where can I read reviews of Transcon Fortune 500 Tower 1?
Google Maps has reviews of Transcon Fortune 500 Tower 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 9 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Transcon Fortune 500 Tower 1?
Transcon Fortune 500 Tower 1 by Samta Builders Pvt. Ltd. is in Mulund West, Mumbai (pincode 400080), near Wagle I.E, Maharashtra, and is registered on MahaRERA as P51800012431, per GharKundli's check of MahaRERA records.
How many homes are in Transcon Fortune 500 Tower 1?
According to GharKundli's check of MahaRERA records (updated November 2026), Transcon Fortune 500 Tower 1 has 265 homes in 1 tower registered on MahaRERA, and 24% of them are sold or booked.
When was Transcon Fortune 500 Tower 1 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Transcon Fortune 500 Tower 1 was registered on MahaRERA on 1 September 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Transcon Fortune 500 Tower 1?
12 court cases are listed for Transcon Fortune 500 Tower 1 on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Transcon Fortune 500 Tower 1?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Samta Builders Pvt. Ltd..
Check it yourself on MahaRERA
- How to check the possession date of Transcon Fortune 500 Tower 1
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in pincode 400080
- MULUND MAHAVIRDHAM CO. OP. HOUSING SOC. LTD.
- Keshavpada
- ARIHANT ROYALE
- THE SANCTUARY - TOWER 5
- Dhanraj Tower
- Madhuvan Nivanta
- Shraddha Paradise Enclave
- Malhar Guide
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.