Swapna-Niketan by NMC
by SANDEEP DWELLERS PVT. LTD. · Wanjara, Nagpur
Possession: Swapna-Niketan by NMC is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P50500050570. Status: Completed. 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Swapna-Niketan by NMC?
How the possession date of Swapna-Niketan by NMC has moved
31 March 2025
Completion date given when the project was registered
30 March 2026
Extended at the builder's request (MahaRERA application EXT50500028075)
Reason the builder gave MahaRERA:
“We had been allotted the Work Order by Slum Rehabilitation Authority (Of Nagpur Municipal Corporation), for the Construction Development and Sale of 480 EWS DU’s including the required basic infrastructure of roads, utilities, social amenit…” Read the full reason
“We had been allotted the Work Order by Slum Rehabilitation Authority (Of Nagpur Municipal Corporation), for the Construction Development and Sale of 480 EWS DU’s including the required basic infrastructure of roads, utilities, social amenities etc. under AHP Pradhan Mantri Awas Yojana in Nagpur. The tenure of the work contract was for a period of 24 months. We were able to start work on 6 out of 8 building in the month of April 2023 but works of 2 buildings could not be started before June 2023 due to change in layout of the overall project as per site condition. In spite of this we have be…”
Source: Swapna-Niketan by NMC’s extension records on MahaRERA (P50500050570), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Swapna-Niketan by NMC
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints, and how it ended
- Construction pace against the March 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P50500050570
- Status
- Completed
- Builder
- SANDEEP DWELLERS PVT. LTD.
- Location
- Wanjara, Nagpur · 440026
- Project type
- Residential / Group Housing
- Registered on
- 21 Apr 2023
- Completion date at registration
- March 2025
- Latest completion date
- March 2026
- Delay so far
- 12 months
- Homes
- 480
- Towers
- 8
- Complaints on MahaRERA
- 2
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 26
Construction progress of Swapna-Niketan by NMC, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A1 | 100% | 100% | 100% | 100% |
| A2 | 100% | 100% | 100% | 85% |
| A3 | 100% | 100% | 93% | 50% |
| A4 | 100% | 100% | 100% | 100% |
| A5 | 100% | 100% | 100% | 50% |
| A6 | 100% | 100% | 93% | 50% |
| A7 | 100% | 100% | 100% | 75% |
| A8 | 100% | 100% | 100% | 50% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Swapna-Niketan by NMC every month.
Swapna-Niketan by NMC: buildings, flats and land, as filed on MahaRERA
- Buildings: A1 (8 floors) · A2 (8 floors) · A3 (8 floors) · A4 (8 floors) · A5 (8 floors) · A6 (8 floors) · A7 (8 floors) · A8 (8 floors)
- Land: 12,913 sq m (about 3.2 acres) · sanctioned built-up 19,085 sq m · recreational space 2,025 sq m
- Boundaries filed include: Kamptee Road and Basti
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Sandeep Dwellers has 27 projects on MahaRERA since 2018, this one included. Of the 14 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 2 months); 12 still being built, 1 past the promised date (typically 18 months late). 6 complaints on MahaRERA across 4 projects.
Read Google reviews of Swapna-Niketan by NMC →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Swapna-Niketan by NMC: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Swapna-Niketan by NMC
What is the possession date of Swapna-Niketan by NMC?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Swapna-Niketan by NMC in Wanjara, Nagpur is 30 March 2026 — 12 months later than 31 March 2025, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Swapna-Niketan by NMC?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Swapna-Niketan by NMC's builder has filed on MahaRERA, the official one, is 30 March 2026, already 12 months later than the 31 March 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Swapna-Niketan by NMC extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Swapna-Niketan by NMC's builder applied to MahaRERA to extend the completion date once: to 30 March 2026, giving the reason "We had been allotted the Work Order by Slum Rehabilitation Authority (Of Nagpur Municipal Corporation), for the Construction Development and Sale of 480 EWS DU’s including the required basic infrastructure of roads, utilities, social amenities etc. under AHP Pradhan Mantri Awas Yojana in Nagpur. The tenure of the work contract was for a period of 24 months. We were able to start work on 6 out of 8 building in the month of April 2023 but works of 2 buildings could not be started before June 2023 due to change in layout of the overall project as per site condition. In spite of this we have be…".
What is the RERA number of Swapna-Niketan by NMC?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Swapna-Niketan by NMC in Wanjara, Nagpur is P50500050570.
Is Swapna-Niketan by NMC registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Swapna-Niketan by NMC is registered as P50500050570 and its status is "Completed".
What is the construction status of Swapna-Niketan by NMC?
According to GharKundli's check of MahaRERA records (updated October 2026), Swapna-Niketan by NMC's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 8 towers. GharKundli's full report compares construction progress with the deadline.
Does Swapna-Niketan by NMC have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Swapna-Niketan by NMC safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Swapna-Niketan by NMC is registered on MahaRERA as P50500050570, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Swapna-Niketan by NMC's possession date changes?
The latest dates are on Swapna-Niketan by NMC's MahaRERA page (P50500050570). GharKundli's Kundli Watch sends a free WhatsApp update on Swapna-Niketan by NMC every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Swapna-Niketan by NMC have?
According to GharKundli's check of MahaRERA records (updated October 2026), Swapna-Niketan by NMC has 8 buildings filed: A1 with 8 floors; A2 with 8 floors; A3 with 8 floors; A4 with 8 floors; A5 with 8 floors; A6 with 8 floors; and 2 more.
How big is the land of Swapna-Niketan by NMC?
According to GharKundli's check of MahaRERA records (updated October 2026), Swapna-Niketan by NMC stands on 12,913 sq m of land (about 3.2 acres), with 19,085 sq m of sanctioned built-up area and 2,025 sq m of recreational open space.
What is the track record of Swapna-Niketan by NMC's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Sandeep Dwellers has 27 projects on MahaRERA since 2018, this one included. Of the 14 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 2 months); 12 still being built, 1 past the promised date (typically 18 months late). 6 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Swapna-Niketan by NMC?
Google Maps has reviews of Swapna-Niketan by NMC written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Swapna-Niketan by NMC?
Swapna-Niketan by NMC by SANDEEP DWELLERS PVT. LTD. is in Wanjara, Nagpur (pincode 440026), Maharashtra, and is registered on MahaRERA as P50500050570, per GharKundli's check of MahaRERA records. Its boundaries filed there include Kamptee Road and Basti.
How many homes are in Swapna-Niketan by NMC?
According to GharKundli's check of MahaRERA records (updated October 2026), Swapna-Niketan by NMC has 480 homes in 8 towers registered on MahaRERA.
When was Swapna-Niketan by NMC registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Swapna-Niketan by NMC was registered on MahaRERA on 21 April 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on Swapna-Niketan by NMC?
No court cases are listed for Swapna-Niketan by NMC on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Swapna-Niketan by NMC?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SANDEEP DWELLERS PVT. LTD., which has 26 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Swapna-Niketan by NMC
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Nagpur (Rural)
- SDPL Aashray Wanjara - II
- SDPL Greens Rowhouse II
- DEV BHUMI
- DWARKA NAGARI
- Shree Nagari 3
- LAKE SHORE OASIS-TWIN DUPLEX
- Royal Dream City-2
- SWASTIK IMPERIAL
Other projects by SANDEEP DWELLERS PVT. LTD.
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.