PALACIO
by RAGHAV LIFESPACES · Shivaji Nagar, NagpurAlso near Khare Town Dharampeth, Shankar Nagar, A.D. Project
Possession date of PALACIO: 30 April 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P50500051602, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about PALACIO?
How the possession date of PALACIO has moved
31 December 2027
Completion date given when the project was registered
30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: PALACIO’s extension records on MahaRERA (P50500051602), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on PALACIO
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P50500051602
- Status
- Registered and active
- Builder
- RAGHAV LIFESPACES
- Location
- Shivaji Nagar, Nagpur · 440010
- Project type
- Residential / Group Housing
- Registered on
- 27 Jun 2023
- Completion date at registration
- December 2027
- Latest completion date
- April 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 30
- Sold or booked
- 89%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of PALACIO, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| PALACIO | 95% | 100% | 90% | 90% |
Commencement certificate (CC), as filed on MahaRERA
- PALACIO: covers 16 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on PALACIO every month.
PALACIO: buildings, flats and land, as filed on MahaRERA
- Buildings: PALACIO (16 floors, 30 units)
- Car parking: 1 covered
- Land: 1,237 sq m (about 0.3 acres) · sanctioned built-up 7,072 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Raghav Lifespaces has 3 projects on MahaRERA since 2023, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. No complaints on MahaRERA.
Read Google reviews of PALACIO →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
PALACIO: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about PALACIO
What is the possession date of PALACIO?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for PALACIO in Shivaji Nagar, Nagpur is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for PALACIO?
Builders and listing sites often quote an earlier "target" date for handover. The completion date PALACIO's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of PALACIO?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of PALACIO in Shivaji Nagar, Nagpur is P50500051602.
Is PALACIO registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), PALACIO is registered as P50500051602 and its status is "Registered and active".
What is the construction status of PALACIO?
According to GharKundli's check of MahaRERA records (updated November 2026), PALACIO's status on MahaRERA is "Registered and active". As filed by the builder, slab work on PALACIO is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.
Does PALACIO have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is PALACIO safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), PALACIO is registered on MahaRERA as P50500051602, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if PALACIO's possession date changes?
The latest dates are on PALACIO's MahaRERA page (P50500051602). GharKundli's Kundli Watch sends a free WhatsApp update on PALACIO every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does PALACIO have?
According to GharKundli's check of MahaRERA records (updated November 2026), PALACIO has one building filed: PALACIO with 16 floors and 30 units.
How much parking does PALACIO have?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 1 covered car parking spaces for PALACIO.
How big is the land of PALACIO?
According to GharKundli's check of MahaRERA records (updated November 2026), PALACIO stands on 1,237 sq m of land (about 0.3 acres), with 7,072 sq m of sanctioned built-up area.
What is the track record of PALACIO's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Raghav Lifespaces has 3 projects on MahaRERA since 2023, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of PALACIO?
Google Maps has reviews of PALACIO written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is PALACIO?
PALACIO by RAGHAV LIFESPACES is in Shivaji Nagar, Nagpur (pincode 440010), near Khare Town Dharampeth, Shankar Nagar, A.D. Project, Maharashtra, and is registered on MahaRERA as P50500051602, per GharKundli's check of MahaRERA records.
How many homes are in PALACIO?
According to GharKundli's check of MahaRERA records (updated November 2026), PALACIO has 30 homes in 1 tower registered on MahaRERA, and 89% of them are sold or booked.
When was PALACIO registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), PALACIO was registered on MahaRERA on 27 June 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on PALACIO?
No court cases are listed for PALACIO on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of PALACIO?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is RAGHAV LIFESPACES, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of PALACIO
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Nagpur →
Other projects in Shivaji Nagar
- SUNMAN CO-OPERATIVE HOUSING SOCIETY LIMITED
- GAJANAN GALAXY
- ASHAPURA RIDDHI TOWER
- MIAMI-A1-A2-A3-B2
- SAYAJI APARTMENT
- 44 NECTAR RESIDENCY
- CONCLAVE
- THE RHYTHM
Other projects by RAGHAV LIFESPACES
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.