Ashapura Riddhi Tower

by ASHAPURA DEVELOPERS PROPRIETOR SANJAYKUMAR MAKANJI KOTAK THAKKAR · Shivaji Nagar, Thane 421201

What’s in the report? →

Possession date of Ashapura Riddhi Tower (MahaRERA P51700080193): 30 April 2030. It has 48 homes, 16% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700080193, and currently active. Its completion date is now April 2030, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for P51700080193, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Ashapura Riddhi Tower?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Ashapura Riddhi Tower has moved

  1. 31 December 2029

    Completion date given when the project was registered

  2. 30 April 2030

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Ashapura Riddhi Tower’s extension records on MahaRERA (P51700080193), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Ashapura Riddhi Tower

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2030 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700080193
Status
Registered and active
Builder
ASHAPURA DEVELOPERS PROPRIETOR SANJAYKUMAR MAKANJI KOTAK THAKKAR
Location
Shivaji Nagar, Thane · 421201
Project type
Residential / Group Housing
Registered on
6 May 2025
Completion date at registration
December 2029
Latest completion date
April 2030
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
48
Sold or booked
16%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Ashapura Riddhi Tower, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
ASHAPURA RIDDHI TOWER100%75%15%15%

Commencement certificate (CC), as filed on MahaRERA

  • ASHAPURA RIDDHI TOWER: covers 8 floors

Latest CC order on MahaRERA: dated 31/03/2026.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Ashapura Riddhi Tower every 1–2 months.

Ashapura Riddhi Tower: buildings, flats and land, as filed on MahaRERA

  • Buildings: ASHAPURA RIDDHI TOWER (8 floors, 49 units)
  • Car parking: 18 covered
  • Land: 772 sq m (about 0.2 acres) · sanctioned built-up 2,768 sq m
  • Land, as filed: S.NO.85 H.NO.2, S. NO.86 H.NO.5
  • Map: Get directions

The builder’s record and reviews

Ashapura Developers Proprietor Sanjaykumar Makanji Kotak Thakkar has 3 projects on MahaRERA since 2019, this one included. Of the 3 GharKundli has checked: 3 still being built, 2 past the promised date (typically 34 months late). No complaints on MahaRERA.

Read Google reviews of Ashapura Riddhi Tower →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Ashapura Riddhi Tower: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Ashapura Riddhi Tower

What is the possession date of Ashapura Riddhi Tower?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Ashapura Riddhi Tower in Shivaji Nagar, Thane is 30 April 2030, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Ashapura Riddhi Tower?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Ashapura Riddhi Tower's builder has filed on MahaRERA, the official one, is 30 April 2030, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Ashapura Riddhi Tower?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Ashapura Riddhi Tower in Shivaji Nagar, Thane is P51700080193.

Is Ashapura Riddhi Tower registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Ashapura Riddhi Tower is registered as P51700080193 and its status is "Registered and active".

What is the current construction status of Ashapura Riddhi Tower? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Ashapura Riddhi Tower's status on MahaRERA is "Registered and active". As filed by the builder, slab work on ASHAPURA RIDDHI TOWER is 75% done and internal work 15%. GharKundli's full report compares construction progress with the deadline.

Does Ashapura Riddhi Tower have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Ashapura Riddhi Tower safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Ashapura Riddhi Tower is registered on MahaRERA as P51700080193, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Ashapura Riddhi Tower?

Ashapura Riddhi Tower is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Ashapura Riddhi Tower?

For a flat in Ashapura Riddhi Tower (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Ashapura Riddhi Tower received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Ashapura Riddhi Tower is still under construction, with 30 April 2030 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Ashapura Riddhi Tower uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Ashapura Riddhi Tower was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Ashapura Riddhi Tower's possession date changes?

The latest dates are on Ashapura Riddhi Tower's MahaRERA page (P51700080193). GharKundli's Kundli Watch sends a free WhatsApp update on Ashapura Riddhi Tower every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Ashapura Riddhi Tower have?

According to GharKundli's check of MahaRERA records (updated October 2026), Ashapura Riddhi Tower has one building filed: ASHAPURA RIDDHI TOWER with 8 floors and 49 units.

How much parking does Ashapura Riddhi Tower have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 18 covered car parking spaces for Ashapura Riddhi Tower.

How big is the land of Ashapura Riddhi Tower?

According to GharKundli's check of MahaRERA records (updated October 2026), Ashapura Riddhi Tower stands on 772 sq m of land (about 0.2 acres), with 2,768 sq m of sanctioned built-up area.

What is the track record of Ashapura Riddhi Tower's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Ashapura Developers Proprietor Sanjaykumar Makanji Kotak Thakkar has 3 projects on MahaRERA since 2019, this one included. Of the 3 GharKundli has checked: 3 still being built, 2 past the promised date (typically 34 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Ashapura Riddhi Tower?

Google Maps has reviews of Ashapura Riddhi Tower written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Ashapura Riddhi Tower?

Ashapura Riddhi Tower by ASHAPURA DEVELOPERS PROPRIETOR SANJAYKUMAR MAKANJI KOTAK THAKKAR is in Shivaji Nagar, Thane, pincode 421201, Maharashtra, and is registered on MahaRERA as P51700080193, per GharKundli's check of MahaRERA records. Its land is filed as S.NO.85 H.NO.2, S. NO.86 H.NO.5. GharKundli lists all 408 MahaRERA projects in Tilaknagar (421201).

How many flats are in Ashapura Riddhi Tower, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Ashapura Riddhi Tower has 48 homes in 1 tower registered on MahaRERA, and 16% of them are sold or booked.

When was Ashapura Riddhi Tower registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Ashapura Riddhi Tower was registered on MahaRERA on 6 May 2025. GharKundli did not find a title report on the land on file there.

Does Ashapura Riddhi Tower have any legal issues or court cases?

No court cases are listed for Ashapura Riddhi Tower on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Ashapura Riddhi Tower?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ASHAPURA DEVELOPERS PROPRIETOR SANJAYKUMAR MAKANJI KOTAK THAKKAR.

All projects with possession due in 2030 in Thane →

Other projects in Tilaknagar (421201)

All 408 projects in Tilaknagar (421201) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.