MAHALAXMI NAGAR 30 AND VISION CITY 2
by VISION INFRA · Takli, NagpurAlso near Umred Project
Possession date of MAHALAXMI NAGAR 30 AND VISION CITY 2: 14 December 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P50500053716, and currently active. Its completion date is now December 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about MAHALAXMI NAGAR 30 AND VISION CITY 2?
How the possession date of MAHALAXMI NAGAR 30 AND VISION CITY 2 has moved
14 August 2028
Completion date given when the project was registered
14 December 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: MAHALAXMI NAGAR 30 AND VISION CITY 2’s extension records on MahaRERA (P50500053716), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on MAHALAXMI NAGAR 30 AND VISION CITY 2
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P50500053716
- Status
- Registered and active
- Builder
- VISION INFRA
- Location
- Takli, Nagpur · 441204
- Project type
- Plotted
- Registered on
- 22 Nov 2023
- Completion date at registration
- August 2028
- Latest completion date
- December 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 9
MAHALAXMI NAGAR 30 AND VISION CITY 2: buildings, flats and land, as filed on MahaRERA
- Land: 34,951 sq m (about 8.6 acres) · recreational space 6,374 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Vision Infra (a group of 3 linked companies) has 8 projects on MahaRERA since 2022, this one included. Of the 6 GharKundli has checked: 5 still being built, 1 past the promised date (typically 22 months late); 1 lapsed. No complaints on MahaRERA.
Read Google reviews of MAHALAXMI NAGAR 30 AND VISION CITY 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
MAHALAXMI NAGAR 30 AND VISION CITY 2: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about MAHALAXMI NAGAR 30 AND VISION CITY 2
What is the possession date of MAHALAXMI NAGAR 30 AND VISION CITY 2?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for MAHALAXMI NAGAR 30 AND VISION CITY 2 in Takli, Nagpur is 14 December 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for MAHALAXMI NAGAR 30 AND VISION CITY 2?
Builders and listing sites often quote an earlier "target" date for handover. The completion date MAHALAXMI NAGAR 30 AND VISION CITY 2's builder has filed on MahaRERA, the official one, is 14 December 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of MAHALAXMI NAGAR 30 AND VISION CITY 2?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of MAHALAXMI NAGAR 30 AND VISION CITY 2 in Takli, Nagpur is P50500053716.
Is MAHALAXMI NAGAR 30 AND VISION CITY 2 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), MAHALAXMI NAGAR 30 AND VISION CITY 2 is registered as P50500053716 and its status is "Registered and active".
What is the construction status of MAHALAXMI NAGAR 30 AND VISION CITY 2?
According to GharKundli's check of MahaRERA records (updated November 2026), MAHALAXMI NAGAR 30 AND VISION CITY 2's status on MahaRERA is "Registered and active". GharKundli's full report compares construction progress with the deadline.
Does MAHALAXMI NAGAR 30 AND VISION CITY 2 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is MAHALAXMI NAGAR 30 AND VISION CITY 2 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), MAHALAXMI NAGAR 30 AND VISION CITY 2 is registered on MahaRERA as P50500053716, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if MAHALAXMI NAGAR 30 AND VISION CITY 2's possession date changes?
The latest dates are on MAHALAXMI NAGAR 30 AND VISION CITY 2's MahaRERA page (P50500053716). GharKundli's Kundli Watch sends a free WhatsApp update on MAHALAXMI NAGAR 30 AND VISION CITY 2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How big is the land of MAHALAXMI NAGAR 30 AND VISION CITY 2?
According to GharKundli's check of MahaRERA records (updated November 2026), MAHALAXMI NAGAR 30 AND VISION CITY 2 stands on 34,951 sq m of land (about 8.6 acres) and 6,374 sq m of recreational open space.
What is the track record of MAHALAXMI NAGAR 30 AND VISION CITY 2's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Vision Infra (a group of 3 linked companies) has 8 projects on MahaRERA since 2022, this one included. Of the 6 GharKundli has checked: 5 still being built, 1 past the promised date (typically 22 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of MAHALAXMI NAGAR 30 AND VISION CITY 2?
Google Maps has reviews of MAHALAXMI NAGAR 30 AND VISION CITY 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is MAHALAXMI NAGAR 30 AND VISION CITY 2?
MAHALAXMI NAGAR 30 AND VISION CITY 2 by VISION INFRA is in Takli, Nagpur (pincode 441204), near Umred Project, Maharashtra, and is registered on MahaRERA as P50500053716, per GharKundli's check of MahaRERA records.
When was MAHALAXMI NAGAR 30 AND VISION CITY 2 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), MAHALAXMI NAGAR 30 AND VISION CITY 2 was registered on MahaRERA on 22 November 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on MAHALAXMI NAGAR 30 AND VISION CITY 2?
No court cases are listed for MAHALAXMI NAGAR 30 AND VISION CITY 2 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of MAHALAXMI NAGAR 30 AND VISION CITY 2?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is VISION INFRA, which has 9 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of MAHALAXMI NAGAR 30 AND VISION CITY 2
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Nagpur →
Other projects in Nagpur (Rural)
- DEV BHUMI
- DWARKA NAGARI
- Shree Nagari 3
- LAKE SHORE OASIS-TWIN DUPLEX
- Royal Dream City-2
- SWASTIK IMPERIAL
- SHIV SOLITAIRE
- Park House Tranquil
Other projects by VISION INFRA
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.