by VISION INFRA · Umred Project, Nagpur

Possession date of VISION INFRA: 5 October 2023, moved from 7 October 2022 (12 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P50500032991. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (October 2023) has passed.

What do you want to know about VISION INFRA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of VISION INFRA has moved

  1. 7 October 2022

    Completion date given when the project was registered

  2. 5 October 2023

    Extended at the builder's request (MahaRERA application EXT50500012639)

    Reason the builder gave MahaRERA: “DUE TO STOCK NOT SOLD”

Source: VISION INFRA’s extension records on MahaRERA (P50500032991), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on VISION INFRA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P50500032991
Status
Lapsed (registration period ended)
Builder
VISION INFRA
Location
Umred Project, Nagpur · 441204
Project type
Plotted
Registered on
3 Feb 2022
Completion date at registration
October 2022
Latest completion date
October 2023
Delay so far
12 months
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
9

VISION INFRA: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Vision Infra (a group of 3 linked companies) has 8 projects on MahaRERA since 2022, this one included. Of the 6 GharKundli has checked: 5 still being built, 1 past the promised date (typically 22 months late); 1 lapsed. No complaints on MahaRERA.

Read Google reviews of VISION INFRA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

VISION INFRA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about VISION INFRA

What is the possession date of VISION INFRA?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for VISION INFRA in Umred Project, Nagpur is 5 October 2023 — 12 months later than 7 October 2022, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for VISION INFRA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date VISION INFRA's builder has filed on MahaRERA, the official one, is 5 October 2023, already 12 months later than the 7 October 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of VISION INFRA extended?

According to GharKundli's check of MahaRERA records (updated November 2026), VISION INFRA's builder applied to MahaRERA to extend the completion date once: to 5 October 2023, giving the reason "DUE TO STOCK NOT SOLD".

What is the RERA number of VISION INFRA?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of VISION INFRA in Umred Project, Nagpur is P50500032991.

Is VISION INFRA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), VISION INFRA is registered as P50500032991 and its status is "Lapsed (registration period ended)".

What is the construction status of VISION INFRA?

According to GharKundli's check of MahaRERA records (updated November 2026), VISION INFRA's status on MahaRERA is "Lapsed (registration period ended)". GharKundli's full report compares construction progress with the deadline.

Does VISION INFRA have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is VISION INFRA safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), VISION INFRA is registered on MahaRERA as P50500032991, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if VISION INFRA's possession date changes?

The latest dates are on VISION INFRA's MahaRERA page (P50500032991). GharKundli's Kundli Watch sends a free WhatsApp update on VISION INFRA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How big is the land of VISION INFRA?

According to GharKundli's check of MahaRERA records (updated November 2026), VISION INFRA stands on 20,123 sq m of land (about 5.0 acres) and 3,175 sq m of recreational open space.

What is the track record of VISION INFRA's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Vision Infra (a group of 3 linked companies) has 8 projects on MahaRERA since 2022, this one included. Of the 6 GharKundli has checked: 5 still being built, 1 past the promised date (typically 22 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of VISION INFRA?

Google Maps has reviews of VISION INFRA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is VISION INFRA?

VISION INFRA by VISION INFRA is in Umred Project, Nagpur (pincode 441204), Maharashtra, and is registered on MahaRERA as P50500032991, per GharKundli's check of MahaRERA records. Its boundaries filed there include Khasara No 96 and road.

When was VISION INFRA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), VISION INFRA was registered on MahaRERA on 3 February 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on VISION INFRA?

No court cases are listed for VISION INFRA on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of VISION INFRA?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is VISION INFRA, which has 9 other projects registered on MahaRERA.

Other projects in pincode 441204

All 47 projects in Umred Project (441204) →

Other projects by VISION INFRA

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.