RACHANA PURVA
by Rachana Developers · Borgaon, NagpurAlso near Katolroad, Seminary Hills, Sillewara Project
Possession: RACHANA PURVA is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P50500053221. Status: Completed. Its completion date has moved from June 2026 to January 2027: 3 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about RACHANA PURVA?
How the possession date of RACHANA PURVA has moved
30 June 2026
Completion date given when the project was registered
30 September 2026
Extended at the builder's request (MahaRERA application EA30042620797)
Reason the builder gave MahaRERA:
“Applying under section 6 of RERA ACT.. That it is to be submitted that our project “Rachana Purva” is completed about 85% and due for completion and Occupancy Certificate (OC) till 30.06.2026. But due to present Middle East War crisis more…” Read the full reason
“Applying under section 6 of RERA ACT.. That it is to be submitted that our project “Rachana Purva” is completed about 85% and due for completion and Occupancy Certificate (OC) till 30.06.2026. But due to present Middle East War crisis more specifically pertaining to Power and fuel section, we are not getting the supply of Tiles/Fire Equipment’s/Steel/Cement/Aluminium from the manufacturer, as raw material required to make these products contents petroleum, oil, natural gases etc. and also diesel for transportation. Due to interruption in supply of these material, interruption in ship routes…”30 January 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: RACHANA PURVA’s extension records on MahaRERA (P50500053221), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on RACHANA PURVA
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 court case, and how it ended
- Construction pace against the January 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P50500053221
- Status
- Completed
- Builder
- Rachana Developers
- Location
- Borgaon, Nagpur · 440013
- Project type
- Others
- Registered on
- 23 Oct 2023
- Completion date at registration
- June 2026
- Latest completion date
- January 2027
- Delay so far
- 3 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 130
- Sold or booked
- 85%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 12
Construction progress of RACHANA PURVA, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Rachana Purva | 100% | 100% | 90% | 30% |
Commencement certificate (CC), as filed on MahaRERA
- Rachana Purva: covers 14 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on RACHANA PURVA every month.
RACHANA PURVA: buildings, flats and land, as filed on MahaRERA
- Buildings: Rachana Purva (14 floors, 135 units)
- Land: 4,431 sq m (about 1.1 acres) · sanctioned built-up 15,953 sq m
The builder’s record and reviews
Rachana Construction Co Nagpur (a group of 2 linked companies) has 9 projects on MahaRERA since 2022, this one included. Of the 5 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 7 months); 2 still being built, none past the promised date yet. No complaints on MahaRERA.
Read Google reviews of RACHANA PURVA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
RACHANA PURVA: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about RACHANA PURVA
What is the possession date of RACHANA PURVA?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for RACHANA PURVA in Borgaon, Nagpur is 30 January 2027 — 3 months later than 30 June 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for RACHANA PURVA?
Builders and listing sites often quote an earlier "target" date for handover. The completion date RACHANA PURVA's builder has filed on MahaRERA, the official one, is 30 January 2027, already 3 months later than the 30 June 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of RACHANA PURVA extended?
According to GharKundli's check of MahaRERA records (updated October 2026), RACHANA PURVA's builder applied to MahaRERA to extend the completion date once: to 30 September 2026, giving the reason "Applying under section 6 of RERA ACT.. That it is to be submitted that our project “Rachana Purva” is completed about 85% and due for completion and Occupancy Certificate (OC) till 30.06.2026. But due to present Middle East War crisis more specifically pertaining to Power and fuel section, we are not getting the supply of Tiles/Fire Equipment’s/Steel/Cement/Aluminium from the manufacturer, as raw material required to make these products contents petroleum, oil, natural gases etc. and also diesel for transportation. Due to interruption in supply of these material, interruption in ship routes…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of RACHANA PURVA?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of RACHANA PURVA in Borgaon, Nagpur is P50500053221.
Is RACHANA PURVA registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), RACHANA PURVA is registered as P50500053221 and its status is "Completed".
What is the construction status of RACHANA PURVA?
According to GharKundli's check of MahaRERA records (updated October 2026), RACHANA PURVA's status on MahaRERA is "Completed". As filed by the builder, slab work on Rachana Purva is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.
Does RACHANA PURVA have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is RACHANA PURVA safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), RACHANA PURVA is registered on MahaRERA as P50500053221, its MahaRERA status is "Completed", its completion date has moved 3 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if RACHANA PURVA's possession date changes?
The latest dates are on RACHANA PURVA's MahaRERA page (P50500053221). GharKundli's Kundli Watch sends a free WhatsApp update on RACHANA PURVA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does RACHANA PURVA have?
According to GharKundli's check of MahaRERA records (updated October 2026), RACHANA PURVA has one building filed: Rachana Purva with 14 floors and 135 units.
How big is the land of RACHANA PURVA?
According to GharKundli's check of MahaRERA records (updated October 2026), RACHANA PURVA stands on 4,431 sq m of land (about 1.1 acres), with 15,953 sq m of sanctioned built-up area.
What is the track record of RACHANA PURVA's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Rachana Construction Co Nagpur (a group of 2 linked companies) has 9 projects on MahaRERA since 2022, this one included. Of the 5 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 7 months); 2 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of RACHANA PURVA?
Google Maps has reviews of RACHANA PURVA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is RACHANA PURVA?
RACHANA PURVA by Rachana Developers is in Borgaon, Nagpur (pincode 440013), near Katolroad, Seminary Hills, Sillewara Project, Maharashtra, and is registered on MahaRERA as P50500053221, per GharKundli's check of MahaRERA records.
How many homes are in RACHANA PURVA?
According to GharKundli's check of MahaRERA records (updated October 2026), RACHANA PURVA has 130 homes in 1 tower registered on MahaRERA, and 85% of them are sold or booked.
When was RACHANA PURVA registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), RACHANA PURVA was registered on MahaRERA on 23 October 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on RACHANA PURVA?
1 court case is listed for RACHANA PURVA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of RACHANA PURVA?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Rachana Developers, which has 12 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of RACHANA PURVA
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 440013
- Sadoday Shubham
- Naniks Ashtavinayak Bhakti-4
- NANIKS ASHTAVINAYAK UPPALS SHERATON
- PRAYAG PARADISE
- OAK STERLING VISTA
- DREAM HOME
- Sai Basera Nagari
- Devotie
Other projects by Rachana Developers
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.