Possession date of STAR PLAZA: 31 December 2026, moved from 30 December 2022 (48 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800006698, and currently active. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about STAR PLAZA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of STAR PLAZA has moved

  1. 30 December 2022

    Completion date given when the project was registered

  2. 30 December 2023

    Extended at the builder's request (MahaRERA application EXT51800011766)

    Reason the builder gave MahaRERA: “Due to covid- 19 Effect the project was not able to get completed in time. we would like to request you to further grant us extension for 12 month i.e. upto 30-12-2023.”
  3. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT51800019030)

    Reason the builder gave MahaRERA: “due to shortage of martiral and labour not able to complete the project please grant us extension till 31/12/2024”
  4. 30 June 2025

    Extended at the builder's request (MahaRERA application EXT51800027281)

    Reason the builder gave MahaRERA:
    “We are making an application to extend the project registration with Maharashtra Real Estate Regulatory Authority. We have to revise the project timeline due to following reasons- (1) The Development Control and Promotion Regulations 2034 h…” Read the full reason“We are making an application to extend the project registration with Maharashtra Real Estate Regulatory Authority. We have to revise the project timeline due to following reasons- (1) The Development Control and Promotion Regulations 2034 has updated the Floor Space Index (FSI) guidelines, allowing promoters to seek additional FSI allocations. (2) In light of these updated guidelines, the promoter submitted a request to take advantage of the additional FSI provisions outlined in the new Development. Control and Promotion Regulations 2034. (3) The opportunity to access additional FSI necessi…”
  5. 31 December 2025

    Extended at the builder's request (MahaRERA application EA29072502232)

    Reason the builder gave MahaRERA:
    “We are making an application to extend the project registration with Maharashtra Real Estate Regulatory Authority. We have to revise the project timeline due to following reasons (1) The Development Control and Promotion Regulations 2034 ha…” Read the full reason“We are making an application to extend the project registration with Maharashtra Real Estate Regulatory Authority. We have to revise the project timeline due to following reasons (1) The Development Control and Promotion Regulations 2034 has updated the Floor Space Index (FSI) guidelines, allowing promoters to seek additional FSI allocations. (2) In light of these updated guidelines, the promoter submitted a request to take advantage of the additional FSI provisions outlined in the new Development Control and Promotion Regulations 2034. 3) The opportunity to access additional FSI necessitat…”
  6. 31 December 2026

    Extended at the builder's request (MahaRERA application EA20012619517)

    Reason the builder gave MahaRERA:
    “We, Seven Star Developers, are the developers of the project Star Plaza, bearing RERA Registration No. P51800006698, situated at C.T.S. No. 65, 66, 66/1 to 12, 67, 67/1 to 24, 68(pt), 68/1 to 6, F.P. No. 15 & 16(pt) TPS-II, of village Kanhe…” Read the full reason“We, Seven Star Developers, are the developers of the project Star Plaza, bearing RERA Registration No. P51800006698, situated at C.T.S. No. 65, 66, 66/1 to 12, 67, 67/1 to 24, 68(pt), 68/1 to 6, F.P. No. 15 & 16(pt) TPS-II, of village Kanheri at Borivali (E), Mumbai.We respectfully submit that the construction work of the above-mentioned project has been fully completed in all respects in accordance with the approved plans. Upon completion of the construction, we have started the process to fulfil the compliances for application of the Occupation Certificate to the competent authority. The…”

Source: STAR PLAZA’s extension records on MahaRERA (P51800006698), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on STAR PLAZA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800006698
Status
Registered and active
Builder
SEVENSTAR DEVELOPERS
Location
borivali east, Mumbai · 400066
Project type
Others
Registered on
16 Aug 2017
Completion date at registration
December 2022
Latest completion date
December 2026
Delay so far
48 months
Homes
114
Sold or booked
54%
Towers
2
Complaints on MahaRERA
1
Court cases listed
0
Appeals at the tribunal
1
Title report on file
Not found

Construction progress of STAR PLAZA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
COMPOSITE BUILDING WING A REHAB100%100%90%90%
COMPOSITE BUILDING WING B SALE100%100%90%90%

Commencement certificate (CC), as filed on MahaRERA

  • COMPOSITE BUILDING WING A REHAB: covers plinth level
  • COMPOSITE BUILDING WING B SALE: covers plinth level

Want to know when this changes? Kundli Watch sends a free WhatsApp update on STAR PLAZA every month.

STAR PLAZA: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
Office Space104 – 1,816130
1 BHK300 – 484113
Shops49 – 3,45729
Other1261
  • Buildings: COMPOSITE BUILDING WING A REHAB (18 floors, 114 units) · COMPOSITE BUILDING WING B SALE (25 floors, 159 units)
  • Car parking: 164 covered
  • Land: 2,279 sq m (about 0.6 acres) · sanctioned built-up 5,473 sq m · recreational space 119 sq m
  • Boundaries filed include: CARTER ROAD NO 7, CARTER ROAD NO 6
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of STAR PLAZA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

STAR PLAZA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about STAR PLAZA

What is the possession date of STAR PLAZA?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for STAR PLAZA in borivali east, Mumbai is 31 December 2026 — 48 months later than 30 December 2022, the date given at registration.

Is the builder's possession date different from the MahaRERA date for STAR PLAZA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date STAR PLAZA's builder has filed on MahaRERA, the official one, is 31 December 2026, already 48 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of STAR PLAZA extended?

According to GharKundli's check of MahaRERA records (updated October 2026), STAR PLAZA's builder applied to MahaRERA to extend the completion date 5 times: to 30 December 2023, giving the reason "Due to covid- 19 Effect the project was not able to get completed in time. we would like to request you to further grant us extension for 12 month i.e. upto 30-12-2023."; to 31 December 2024, giving the reason "due to shortage of martiral and labour not able to complete the project please grant us extension till 31/12/2024"; to 30 June 2025, giving the reason "We are making an application to extend the project registration with Maharashtra Real Estate Regulatory Authority. We have to revise the project timeline due to following reasons- (1) The Development Control and Promotion Regulations 2034 has updated the Floor Space Index (FSI) guidelines, allowing promoters to seek additional FSI allocations. (2) In light of these updated guidelines, the promoter submitted a request to take advantage of the additional FSI provisions outlined in the new Development. Control and Promotion Regulations 2034. (3) The opportunity to access additional FSI necessi…"; to 31 December 2025, giving the reason "We are making an application to extend the project registration with Maharashtra Real Estate Regulatory Authority. We have to revise the project timeline due to following reasons (1) The Development Control and Promotion Regulations 2034 has updated the Floor Space Index (FSI) guidelines, allowing promoters to seek additional FSI allocations. (2) In light of these updated guidelines, the promoter submitted a request to take advantage of the additional FSI provisions outlined in the new Development Control and Promotion Regulations 2034. 3) The opportunity to access additional FSI necessitat…"; to 31 December 2026, giving the reason "We, Seven Star Developers, are the developers of the project Star Plaza, bearing RERA Registration No. P51800006698, situated at C.T.S. No. 65, 66, 66/1 to 12, 67, 67/1 to 24, 68(pt), 68/1 to 6, F.P. No. 15 & 16(pt) TPS-II, of village Kanheri at Borivali (E), Mumbai.We respectfully submit that the construction work of the above-mentioned project has been fully completed in all respects in accordance with the approved plans. Upon completion of the construction, we have started the process to fulfil the compliances for application of the Occupation Certificate to the competent authority. The…".

What is the RERA number of STAR PLAZA?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of STAR PLAZA in borivali east, Mumbai is P51800006698.

Is STAR PLAZA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), STAR PLAZA is registered as P51800006698 and its status is "Registered and active".

What is the construction status of STAR PLAZA?

According to GharKundli's check of MahaRERA records (updated October 2026), STAR PLAZA's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does STAR PLAZA have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is STAR PLAZA safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), STAR PLAZA is registered on MahaRERA as P51800006698, its completion date has moved 48 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if STAR PLAZA's possession date changes?

The latest dates are on STAR PLAZA's MahaRERA page (P51800006698). GharKundli's Kundli Watch sends a free WhatsApp update on STAR PLAZA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does STAR PLAZA have?

According to GharKundli's check of MahaRERA records (updated October 2026), STAR PLAZA has 2 buildings filed: COMPOSITE BUILDING WING A REHAB with 18 floors and 114 units; COMPOSITE BUILDING WING B SALE with 25 floors and 159 units.

What are the flat sizes (carpet area) in STAR PLAZA?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for STAR PLAZA: 1 BHK: 300 to 484 sq ft carpet (113 homes); Other: 126 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does STAR PLAZA have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 164 covered car parking spaces for STAR PLAZA.

How big is the land of STAR PLAZA?

According to GharKundli's check of MahaRERA records (updated October 2026), STAR PLAZA stands on 2,279 sq m of land (about 0.6 acres), with 5,473 sq m of sanctioned built-up area and 119 sq m of recreational open space.

Where can I read reviews of STAR PLAZA?

Google Maps has reviews of STAR PLAZA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is STAR PLAZA?

STAR PLAZA by SEVENSTAR DEVELOPERS is in borivali east, Mumbai (pincode 400066), near Borivali West, Daulat Nagar, Kandivali West, Maharashtra, and is registered on MahaRERA as P51800006698, per GharKundli's check of MahaRERA records. Its boundaries filed there include CARTER ROAD NO 7, CARTER ROAD NO 6.

How many homes are in STAR PLAZA?

According to GharKundli's check of MahaRERA records (updated October 2026), STAR PLAZA has 114 homes in 2 towers registered on MahaRERA, and 54% of them are sold or booked.

When was STAR PLAZA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), STAR PLAZA was registered on MahaRERA on 16 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on STAR PLAZA?

No court cases are listed for STAR PLAZA on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of STAR PLAZA?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SEVENSTAR DEVELOPERS.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in pincode 400066

All 228 projects in Borivali East (400066) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.