GAURAV VISTA

by M/S GAURAV INFRA · Society Pha Scheme, NagpurAlso near Dr.Ambedkar Marg, Jaripatka, Mahatma Fule Bazar

Possession date of GAURAV VISTA: 30 April 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P50500080581, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about GAURAV VISTA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of GAURAV VISTA has moved

  1. 31 December 2027

    Completion date given when the project was registered

  2. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: GAURAV VISTA’s extension records on MahaRERA (P50500080581), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on GAURAV VISTA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P50500080581
Status
Registered and active
Builder
M/S GAURAV INFRA
Location
Society Pha Scheme, Nagpur · 440017
Project type
Commercial
Registered on
16 Jun 2025
Completion date at registration
December 2027
Latest completion date
April 2028
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
0
Sold or booked
25%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of GAURAV VISTA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
GAURAV INFRA95%80%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • GAURAV INFRA: covers 6 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on GAURAV VISTA every month.

GAURAV VISTA: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of GAURAV VISTA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

GAURAV VISTA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about GAURAV VISTA

What is the possession date of GAURAV VISTA?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for GAURAV VISTA in Society Pha Scheme, Nagpur is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for GAURAV VISTA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date GAURAV VISTA's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of GAURAV VISTA?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of GAURAV VISTA in Society Pha Scheme, Nagpur is P50500080581.

Is GAURAV VISTA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), GAURAV VISTA is registered as P50500080581 and its status is "Registered and active".

What is the construction status of GAURAV VISTA?

According to GharKundli's check of MahaRERA records (updated October 2026), GAURAV VISTA's status on MahaRERA is "Registered and active". As filed by the builder, slab work on GAURAV INFRA is 80% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does GAURAV VISTA have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is GAURAV VISTA safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), GAURAV VISTA is registered on MahaRERA as P50500080581, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if GAURAV VISTA's possession date changes?

The latest dates are on GAURAV VISTA's MahaRERA page (P50500080581). GharKundli's Kundli Watch sends a free WhatsApp update on GAURAV VISTA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does GAURAV VISTA have?

According to GharKundli's check of MahaRERA records (updated October 2026), GAURAV VISTA has one building filed: GAURAV INFRA with 7 floors and 36 units.

How big is the land of GAURAV VISTA?

According to GharKundli's check of MahaRERA records (updated October 2026), GAURAV VISTA stands on 523 sq m of land (about 0.1 acres), with 1,346 sq m of sanctioned built-up area.

Where can I read reviews of GAURAV VISTA?

Google Maps has reviews of GAURAV VISTA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is GAURAV VISTA?

GAURAV VISTA by M/S GAURAV INFRA is in Society Pha Scheme, Nagpur (pincode 440017), near Dr.Ambedkar Marg, Jaripatka, Mahatma Fule Bazar, Maharashtra, and is registered on MahaRERA as P50500080581, per GharKundli's check of MahaRERA records.

How many homes are in GAURAV VISTA?

According to GharKundli's check of MahaRERA records (updated October 2026), GAURAV VISTA has 0 homes in 1 tower registered on MahaRERA, and 25% of them are sold or booked.

When was GAURAV VISTA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), GAURAV VISTA was registered on MahaRERA on 16 June 2025. GharKundli did not find a title report on the land on file there.

Are there court cases on GAURAV VISTA?

No court cases are listed for GAURAV VISTA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of GAURAV VISTA?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/S GAURAV INFRA.

All projects with possession due in 2028 in Nagpur →

Other projects in Nagpur (Urban)

All 10 projects in Dr.Ambedkar Marg (440017) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.