by Snehanjali and S.B.Developers Pvt.Ltd. · Null, MumbaiAlso near Sion Chunabhatti, Nehru Nagar
Possession date of O2: 4 July 2026, moved from 31 December 2020 (63 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51800008513. Status: Lapsed (registration period ended). Its completion date has moved from December 2020 to July 2026: 63 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 51 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (July 2026) has passed.
On MahaRERA's insolvency (NCLT) list
MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.
On MahaRERA’s list since at least 23 Oct 2026See MahaRERA’s list
What do you want to know about O2?
How the possession date of O2 has moved
31 December 2020
Completion date given when the project was registered
30 December 2021
Extended at the builder's request (MahaRERA application EXT51800005409)
Reason the builder gave MahaRERA: “Declaration attached.”
30 June 2023
Extended at the builder's request (MahaRERA application EXT51800013584)
Reason the builder gave MahaRERA:
“1) Due to the then Prevailing Pandemic situation in year 2020 and 2021, for the majority of the period labours & materials were not available on site which delayed the construction. 2) After lockdown was over, labours started to remobilize.…” Read the full reason
“1) Due to the then Prevailing Pandemic situation in year 2020 and 2021, for the majority of the period labours & materials were not available on site which delayed the construction. 2) After lockdown was over, labours started to remobilize. However, it took more time to mobilise the required labours strength to recommence the construction work again. The considerable time was required to be spent in mobilizing the labours. 3)Material delivery was also affected and restarted again after the lockdown got over. 4) The Project is at advanced stage of completion. We will be shortly approaching t…”4 March 2026
Extended at the builder's request (MahaRERA application EXT51800027982)
Reason the builder gave MahaRERA:
“1. As per NCLT Order dated 12th February 2025 (IA (I.B.C) (Plan) No. 102/MB/2024 in CP (IB) No. 1046/MB/2023), SRA is instructed to revive, complete, and hand over the project.- uploaded in Tab 1 2. Clause 6.8 of the order mandates completi…” Read the full reason
“1. As per NCLT Order dated 12th February 2025 (IA (I.B.C) (Plan) No. 102/MB/2024 in CP (IB) No. 1046/MB/2023), SRA is instructed to revive, complete, and hand over the project.- uploaded in Tab 1 2. Clause 6.8 of the order mandates completion and possession within 1 year from project handover 3. Project was officially handed over on 4th March 2025 and therefore Completion deadline as per NCLT direction is 4th March 2026. 4. Requesting MahaRERA to grant project registration extension till 4th March 2026. 5. The extension is necessary and in the best interest of allottees and resettlers.”4 July 2026
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: O2’s extension records on MahaRERA (P51800008513), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on O2
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 51 complaints and 3 court cases, and how it ended
- Construction pace against the July 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800008513
- Status
- Lapsed (registration period ended)
- Builder
- Snehanjali and S.B.Developers Pvt.Ltd.
- Location
- Null, Mumbai · 400022
- Project type
- Residential / Group Housing
- Registered on
- 19 Aug 2017
- Completion date at registration
- December 2020
- Latest completion date
- July 2026
- Delay so far
- 63 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 310
- Sold or booked
- 96%
- Towers
- 6
- Complaints on MahaRERA
- 51
- Court cases listed
- 3
- Appeals at the tribunal
- 1
- Title report on file
- Not found
Construction progress of O2, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| O2 WING A | 100% | 100% | 44% | 1% |
| O2 WING B | 100% | 100% | 44% | 1% |
| O2 WING C | 100% | 100% | 44% | 1% |
| O2 WING D | 100% | 100% | 44% | 1% |
| O2 WING E | 100% | 100% | 44% | 1% |
| O2 WING F | 100% | 100% | 44% | 1% |
Commencement certificate (CC), as filed on MahaRERA
- O2 WING A: covers 19 floors
- O2 WING B: covers 19 floors
- O2 WING C: covers 19 floors
- O2 WING D: covers 19 floors
- O2 WING E: covers 19 floors
- O2 WING F: covers 19 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on O2 every month.
O2: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 663 – 826 | 246 |
| 3 BHK | 985 – 1,025 | 64 |
- Buildings: O2 WING A (19 floors, 62 units) · O2 WING B (19 floors, 32 units) · O2 WING C (19 floors, 61 units) · O2 WING D (19 floors, 61 units) · O2 WING E (19 floors, 32 units) · O2 WING F (19 floors, 62 units)
- Car parking: 370 covered
- Land: 5,969 sq m (about 1.5 acres) · sanctioned built-up 12,349 sq m · recreational space 828 sq m
- Boundaries filed include: V N PURAV MARG
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Shree Ahuja Properties (a group of 4 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 still being built, none past the promised date yet; 3 lapsed. 159 complaints on MahaRERA across 4 projects.
Read Google reviews of O2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
O2: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about O2
What is the possession date of O2?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for O2 in Null, Mumbai is 4 July 2026 — 63 months later than 31 December 2020, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.
Is the builder's possession date different from the MahaRERA date for O2?
Builders and listing sites often quote an earlier "target" date for handover. The completion date O2's builder has filed on MahaRERA, the official one, is 4 July 2026, already 63 months later than the 31 December 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of O2 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), O2's builder applied to MahaRERA to extend the completion date 3 times: to 30 December 2021, giving the reason "Declaration attached."; to 30 June 2023, giving the reason "1) Due to the then Prevailing Pandemic situation in year 2020 and 2021, for the majority of the period labours & materials were not available on site which delayed the construction. 2) After lockdown was over, labours started to remobilize. However, it took more time to mobilise the required labours strength to recommence the construction work again. The considerable time was required to be spent in mobilizing the labours. 3)Material delivery was also affected and restarted again after the lockdown got over. 4) The Project is at advanced stage of completion. We will be shortly approaching t…"; to 4 March 2026, giving the reason "1. As per NCLT Order dated 12th February 2025 (IA (I.B.C) (Plan) No. 102/MB/2024 in CP (IB) No. 1046/MB/2023), SRA is instructed to revive, complete, and hand over the project.- uploaded in Tab 1 2. Clause 6.8 of the order mandates completion and possession within 1 year from project handover 3. Project was officially handed over on 4th March 2025 and therefore Completion deadline as per NCLT direction is 4th March 2026. 4. Requesting MahaRERA to grant project registration extension till 4th March 2026. 5. The extension is necessary and in the best interest of allottees and resettlers.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of O2?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of O2 in Null, Mumbai is P51800008513.
Is O2 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), O2 is registered as P51800008513 and its status is "Lapsed (registration period ended)". On MahaRERA's own list: On MahaRERA's insolvency (NCLT) list. MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.
What is the construction status of O2?
According to GharKundli's check of MahaRERA records (updated October 2026), O2's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 6 towers. GharKundli's full report compares construction progress with the deadline.
Does O2 have complaints on MahaRERA?
51 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is O2 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), O2 is registered on MahaRERA as P51800008513, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 63 months since registration, 51 complaints are listed against it and it is on MahaRERA's list "On MahaRERA's insolvency (NCLT) list". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if O2's possession date changes?
The latest dates are on O2's MahaRERA page (P51800008513). GharKundli's Kundli Watch sends a free WhatsApp update on O2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does O2 have?
According to GharKundli's check of MahaRERA records (updated October 2026), O2 has 6 buildings filed: O2 WING A with 19 floors and 62 units; O2 WING B with 19 floors and 32 units; O2 WING C with 19 floors and 61 units; O2 WING D with 19 floors and 61 units; O2 WING E with 19 floors and 32 units; O2 WING F with 19 floors and 62 units.
What are the flat sizes (carpet area) in O2?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for O2: 2 BHK: 663 to 826 sq ft carpet (246 homes); 3 BHK: 985 to 1025 sq ft carpet (64 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does O2 have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 370 covered car parking spaces for O2.
How big is the land of O2?
According to GharKundli's check of MahaRERA records (updated October 2026), O2 stands on 5,969 sq m of land (about 1.5 acres), with 12,349 sq m of sanctioned built-up area and 828 sq m of recreational open space.
What is the track record of O2's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Ahuja Properties (a group of 4 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 still being built, none past the promised date yet; 3 lapsed. 159 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of O2?
Google Maps has reviews of O2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 51 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is O2?
O2 by Snehanjali and S.B.Developers Pvt.Ltd. is in Null, Mumbai (pincode 400022), near Sion Chunabhatti, Nehru Nagar, Maharashtra, and is registered on MahaRERA as P51800008513, per GharKundli's check of MahaRERA records. Its boundaries filed there include V N PURAV MARG.
How many homes are in O2?
According to GharKundli's check of MahaRERA records (updated October 2026), O2 has 310 homes in 6 towers registered on MahaRERA, and 96% of them are sold or booked.
When was O2 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), O2 was registered on MahaRERA on 19 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on O2?
3 court cases are listed for O2 on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of O2?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Snehanjali and S.B.Developers Pvt.Ltd..
Check it yourself on MahaRERA
- How to check the possession date of O2
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai City →
Other projects in Kurla
- SUDHANSHU HEIGHTS
- Saptashringi
- Jai Arihant
- Kalyan Kutir Co-operative Housing Society Limited
- Heritage Lakeside
- Kanakdhara
- Privilon
- Valentina CHS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.