by Prime Builders and Developers · Jogeshwari west, MumbaiAlso near Oshiwara, Andheri West, Vesava

Possession: Prime Builders is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800008911. Status: Completed. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Prime Builders?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Prime Builders has moved

  1. 30 November 2020

    Completion date given when the project was registered

  2. 30 November 2021

    Extended at the builder's request (MahaRERA application EXT51800008571)

    Reason the builder gave MahaRERA: “The work has been completed, application for OC has been made, awaiting receipt of OC, hence the delay.”
  3. 30 May 2022

    Revised completion date on MahaRERA

Source: Prime Builders’s extension records on MahaRERA (P51800008911), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Prime Builders

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the May 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800008911
Status
Completed
Builder
Prime Builders and Developers
Location
Jogeshwari west, Mumbai · 400102
Project type
Mixed
Registered on
19 Aug 2017
Completion date at registration
November 2020
Latest completion date
May 2022
Delay so far
18 months
Homes
55
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of Prime Builders, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Amil Brothers CHS100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Prime Builders every month.

Prime Builders: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Prime Builders And Developers has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 12 months). 1 complaint on MahaRERA across 1 project.

Read Google reviews of Prime Builders →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Prime Builders: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Prime Builders

What is the possession date of Prime Builders?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Prime Builders in Jogeshwari west, Mumbai is 30 May 2022 — 18 months later than 30 November 2020, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Prime Builders?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Prime Builders's builder has filed on MahaRERA, the official one, is 30 May 2022, already 18 months later than the 30 November 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Prime Builders extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Prime Builders's builder applied to MahaRERA to extend the completion date once: to 30 November 2021, giving the reason "The work has been completed, application for OC has been made, awaiting receipt of OC, hence the delay.".

What is the RERA number of Prime Builders?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Prime Builders in Jogeshwari west, Mumbai is P51800008911.

Is Prime Builders registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Prime Builders is registered as P51800008911 and its status is "Completed".

What is the construction status of Prime Builders?

According to GharKundli's check of MahaRERA records (updated November 2026), Prime Builders's status on MahaRERA is "Completed". As filed by the builder, slab work on Amil Brothers CHS is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Prime Builders have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Prime Builders safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Prime Builders is registered on MahaRERA as P51800008911, its MahaRERA status is "Completed", its completion date has moved 18 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Prime Builders's possession date changes?

The latest dates are on Prime Builders's MahaRERA page (P51800008911). GharKundli's Kundli Watch sends a free WhatsApp update on Prime Builders every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Prime Builders have?

According to GharKundli's check of MahaRERA records (updated November 2026), Prime Builders has one building filed: Amil Brothers CHS with 18 floors.

How big is the land of Prime Builders?

According to GharKundli's check of MahaRERA records (updated November 2026), Prime Builders stands on 728 sq m of land (about 0.2 acres), with 1,950 sq m of sanctioned built-up area.

What is the track record of Prime Builders's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Prime Builders And Developers has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 12 months). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Prime Builders?

Google Maps has reviews of Prime Builders written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Prime Builders?

Prime Builders by Prime Builders and Developers is in Jogeshwari west, Mumbai (pincode 400102), near Oshiwara, Andheri West, Vesava, Maharashtra, and is registered on MahaRERA as P51800008911, per GharKundli's check of MahaRERA records. Its boundaries filed there include Public Road.

How many homes are in Prime Builders?

According to GharKundli's check of MahaRERA records (updated November 2026), Prime Builders has 55 homes in 1 tower registered on MahaRERA.

When was Prime Builders registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Prime Builders was registered on MahaRERA on 19 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Prime Builders?

No court cases are listed for Prime Builders on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Prime Builders?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Prime Builders and Developers, which has 3 other projects registered on MahaRERA.

Other projects in pincode 400102

All 115 projects in Jogeshwari West (400102) →

Other projects by Prime Builders and Developers

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.