by SANKALP SIDDHI DEVELOPERS PVT LTD · Oshiwara, MumbaiAlso near Jogeshwari West, Andheri West, Vesava

Possession date of LAMOR: 29 June 2023, moved from 30 June 2022 (12 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800007725. Status: Lapsed (registration period ended). 71 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (June 2023) has passed.

What do you want to know about LAMOR?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of LAMOR has moved

  1. 30 June 2022

    Completion date given when the project was registered

  2. 29 June 2023

    Extended at the builder's request (MahaRERA application EXT51800011746)

    Reason the builder gave MahaRERA: “Due to lock down all contractors and workers are not available to work.”

Source: LAMOR’s extension records on MahaRERA (P51800007725), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on LAMOR

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 71 complaints, and how it ended
  • Construction pace against the June 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800007725
Status
Lapsed (registration period ended)
Builder
SANKALP SIDDHI DEVELOPERS PVT LTD
Location
Oshiwara, Mumbai · 400102
Project type
Residential / Group Housing
Registered on
17 Aug 2017
Completion date at registration
June 2022
Latest completion date
June 2023
Delay so far
12 months
Homes
240
Towers
1
Complaints on MahaRERA
71
Court cases listed
0
Appeals at the tribunal
13
Title report on file
Not found

Construction progress of LAMOR, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
LAMOR Wing A B100%97%43%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on LAMOR every month.

LAMOR: buildings, flats and land, as filed on MahaRERA

  • Buildings: LAMOR Wing A B (42 floors)
  • Land: 3,381 sq m (about 0.8 acres) · sanctioned built-up 18,153 sq m · recreational space 269 sq m
  • Boundaries filed include: 90 ft relief road
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Shree Ahuja Properties (a group of 4 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 still being built, none past the promised date yet; 3 lapsed. 159 complaints on MahaRERA across 4 projects.

Read Google reviews of LAMOR →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

LAMOR: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about LAMOR

What is the possession date of LAMOR?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for LAMOR in Oshiwara, Mumbai is 29 June 2023 — 12 months later than 30 June 2022, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for LAMOR?

Builders and listing sites often quote an earlier "target" date for handover. The completion date LAMOR's builder has filed on MahaRERA, the official one, is 29 June 2023, already 12 months later than the 30 June 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of LAMOR extended?

According to GharKundli's check of MahaRERA records (updated November 2026), LAMOR's builder applied to MahaRERA to extend the completion date once: to 29 June 2023, giving the reason "Due to lock down all contractors and workers are not available to work.".

What is the RERA number of LAMOR?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of LAMOR in Oshiwara, Mumbai is P51800007725.

Is LAMOR registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), LAMOR is registered as P51800007725 and its status is "Lapsed (registration period ended)". On MahaRERA's own list: On MahaRERA's insolvency (NCLT) list. MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.

What is the construction status of LAMOR?

According to GharKundli's check of MahaRERA records (updated November 2026), LAMOR's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on LAMOR Wing A B is 97% done and internal work 43%. GharKundli's full report compares construction progress with the deadline.

Does LAMOR have complaints on MahaRERA?

71 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is LAMOR safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), LAMOR is registered on MahaRERA as P51800007725, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration, 71 complaints are listed against it and it is on MahaRERA's list "On MahaRERA's insolvency (NCLT) list". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if LAMOR's possession date changes?

The latest dates are on LAMOR's MahaRERA page (P51800007725). GharKundli's Kundli Watch sends a free WhatsApp update on LAMOR every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does LAMOR have?

According to GharKundli's check of MahaRERA records (updated November 2026), LAMOR has one building filed: LAMOR Wing A B with 42 floors.

How big is the land of LAMOR?

According to GharKundli's check of MahaRERA records (updated November 2026), LAMOR stands on 3,381 sq m of land (about 0.8 acres), with 18,153 sq m of sanctioned built-up area and 269 sq m of recreational open space.

What is the track record of LAMOR's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Shree Ahuja Properties (a group of 4 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 still being built, none past the promised date yet; 3 lapsed. 159 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of LAMOR?

Google Maps has reviews of LAMOR written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 71 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is LAMOR?

LAMOR by SANKALP SIDDHI DEVELOPERS PVT LTD is in Oshiwara, Mumbai (pincode 400102), near Jogeshwari West, Andheri West, Vesava, Maharashtra, and is registered on MahaRERA as P51800007725, per GharKundli's check of MahaRERA records. Its boundaries filed there include 90 ft relief road.

How many homes are in LAMOR?

According to GharKundli's check of MahaRERA records (updated November 2026), LAMOR has 240 homes in 1 tower registered on MahaRERA.

When was LAMOR registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), LAMOR was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on LAMOR?

No court cases are listed for LAMOR on MahaRERA, and 13 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of LAMOR?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SANKALP SIDDHI DEVELOPERS PVT LTD.