SOLITAIRE
by SOLITAIRE CONSTRUCTIONS · Somwari Bazar, MumbaiAlso near Malad West, Malad East, Borivali
Possession date of SOLITAIRE: 30 April 2027, moved from 31 March 2019 (93 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800008101, and currently active. Its completion date has moved from March 2019 to April 2027: 93 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SOLITAIRE?
How the possession date of SOLITAIRE has moved
31 March 2019
Completion date given when the project was registered
30 March 2020
Extended at the builder's request (MahaRERA application EXT51800001595)
Reason the builder gave MahaRERA: “ATTACHED IN OTHER AS PER OTHER ATTACHMENT”
30 September 2021
Extended at the builder's request (MahaRERA application EXT51800008731)
Reason the builder gave MahaRERA:
“EXTENDED DUE DATE WAS 30TH SEPTEMBER 2020 , PROMOTER COULD NOT COMPLETE THE PENDING WORK DUE TO VARIETY OF FACTORS MAINLY DUE TO NON-AVAILABILITY OF LABOUR BECAUSE OF COVID SITUATIONS, SHORTAGE OF MATERIALS ETC AND AS STATED IN DECLARATION…” Read the full reason
“EXTENDED DUE DATE WAS 30TH SEPTEMBER 2020 , PROMOTER COULD NOT COMPLETE THE PENDING WORK DUE TO VARIETY OF FACTORS MAINLY DUE TO NON-AVAILABILITY OF LABOUR BECAUSE OF COVID SITUATIONS, SHORTAGE OF MATERIALS ETC AND AS STATED IN DECLARATION CUM APPROVAL OF ALLOTTEES LETTER ATTACHED HEREWITH. ALSO PROMOTER FAMILY MEMBERS WERE HOSPITALISED AND TEAM WERE WORKING REMOTELY DUE TO WHICH IT WAS DIFFICULT IN OBTAINING APPROVAL OF ALLOTTEES , SAME HAS BEEN OBTAINED NOW AND ATTACHED HEREWITH. PROMOTER PRAYS HUMBLY THAT EXTENTION FOR 1 YEAR SHOULD BE GIVEN TO COMPLETE THE BALANCE WORK AND HANDOVER THE…”15 May 2025
Extended at the builder's request (MahaRERA application EXT51800011971)
Reason the builder gave MahaRERA:
“INITIAL DELAY DUE TO LOCKDOWN NO SUPPLY OF MATERIALS, SERVICES OF CONTRACTOR, ECONOMICAL CONDITION OF REAL ESTATE SECTOR MARKET SLOWDOWN AND PROLONGED DELAY IN OBTAINING NECESSARY APPROVAL OF THE AUTHORITY FOR THE AMENDED PLAN FOR UTILIAING…” Read the full reason
“INITIAL DELAY DUE TO LOCKDOWN NO SUPPLY OF MATERIALS, SERVICES OF CONTRACTOR, ECONOMICAL CONDITION OF REAL ESTATE SECTOR MARKET SLOWDOWN AND PROLONGED DELAY IN OBTAINING NECESSARY APPROVAL OF THE AUTHORITY FOR THE AMENDED PLAN FOR UTILIAING BALANCE FSI INC CHANGE SCHEME AFTER OBTAINING CONSENT OF 60 FLAT OWNERS OUT OF TOTAL 82 OWNERS.”31 December 2026
Extended at the builder's request (MahaRERA application EA27102518178)
Reason the builder gave MahaRERA:
“We, Solitaire Construnctions, hereby declare the following with respect to the project “SOLITAIRE” bearing registration number P51800008101 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that we have com…” Read the full reason
“We, Solitaire Construnctions, hereby declare the following with respect to the project “SOLITAIRE” bearing registration number P51800008101 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that we have completed the 100% of RCC (Reinforced Cement Concrete) work for the building. Currently, we are undertaking the finishing work, which includes plastering, flooring, electrical fittings, and other essential internal and external works. 2. Expected Timeline for Completion: We are committed to completing all balance works and applying for the Occupation Certifi…”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SOLITAIRE’s extension records on MahaRERA (P51800008101), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SOLITAIRE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 1 court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800008101
- Status
- Registered and active
- Builder
- SOLITAIRE CONSTRUCTIONS
- Location
- Somwari Bazar, Mumbai · 400064
- Project type
- Others
- Registered on
- 18 Aug 2017
- Completion date at registration
- March 2019
- Latest completion date
- April 2027
- Delay so far
- 93 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 146
- Sold or booked
- 76%
- Towers
- 2
- Complaints on MahaRERA
- 1
- Court cases listed
- 1
- Title report on file
- Not found
Construction progress of SOLITAIRE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| OM DATTA KRUPA WELFARE SRA SAHAKARI GRUHANIRMAN SANSTHA MARYADIT | 100% | 100% | 100% | 98% |
| SOLITAIRE HEIGHTS | 100% | 100% | 100% | 98% |
Commencement certificate (CC), as filed on MahaRERA
- OM DATTA KRUPA WELFARE SRA SAHAKARI GRUHANIRMAN SANSTHA MARYADIT: covers 21 floors
- SOLITAIRE HEIGHTS: covers 26 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SOLITAIRE every month.
SOLITAIRE: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 287 – 449 | 87 |
| 2 BHK | 681 – 713 | 59 |
| Shops | 191 – 636 | 9 |
| Office Space | 1,685 | 1 |
- Buildings: OM DATTA KRUPA WELFARE SRA SAHAKARI GRUHANIRMAN SANSTHA MARYADIT (21 floors, 54 units) · SOLITAIRE HEIGHTS (26 floors, 102 units)
- Car parking: 42 covered
- Land: 3,466 sq m (about 0.9 acres) · sanctioned built-up 6,963 sq m · recreational space 101 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SOLITAIRE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SOLITAIRE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SOLITAIRE
What is the possession date of SOLITAIRE?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SOLITAIRE in Somwari Bazar, Mumbai is 30 April 2027 — 93 months later than 31 March 2019, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SOLITAIRE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SOLITAIRE's builder has filed on MahaRERA, the official one, is 30 April 2027, already 93 months later than the 31 March 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SOLITAIRE extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SOLITAIRE's builder applied to MahaRERA to extend the completion date 4 times: to 30 March 2020, giving the reason "ATTACHED IN OTHER AS PER OTHER ATTACHMENT"; to 30 September 2021, giving the reason "EXTENDED DUE DATE WAS 30TH SEPTEMBER 2020 , PROMOTER COULD NOT COMPLETE THE PENDING WORK DUE TO VARIETY OF FACTORS MAINLY DUE TO NON-AVAILABILITY OF LABOUR BECAUSE OF COVID SITUATIONS, SHORTAGE OF MATERIALS ETC AND AS STATED IN DECLARATION CUM APPROVAL OF ALLOTTEES LETTER ATTACHED HEREWITH. ALSO PROMOTER FAMILY MEMBERS WERE HOSPITALISED AND TEAM WERE WORKING REMOTELY DUE TO WHICH IT WAS DIFFICULT IN OBTAINING APPROVAL OF ALLOTTEES , SAME HAS BEEN OBTAINED NOW AND ATTACHED HEREWITH. PROMOTER PRAYS HUMBLY THAT EXTENTION FOR 1 YEAR SHOULD BE GIVEN TO COMPLETE THE BALANCE WORK AND HANDOVER THE…"; to 15 May 2025, giving the reason "INITIAL DELAY DUE TO LOCKDOWN NO SUPPLY OF MATERIALS, SERVICES OF CONTRACTOR, ECONOMICAL CONDITION OF REAL ESTATE SECTOR MARKET SLOWDOWN AND PROLONGED DELAY IN OBTAINING NECESSARY APPROVAL OF THE AUTHORITY FOR THE AMENDED PLAN FOR UTILIAING BALANCE FSI INC CHANGE SCHEME AFTER OBTAINING CONSENT OF 60 FLAT OWNERS OUT OF TOTAL 82 OWNERS."; to 31 December 2026, giving the reason "We, Solitaire Construnctions, hereby declare the following with respect to the project “SOLITAIRE” bearing registration number P51800008101 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that we have completed the 100% of RCC (Reinforced Cement Concrete) work for the building. Currently, we are undertaking the finishing work, which includes plastering, flooring, electrical fittings, and other essential internal and external works. 2. Expected Timeline for Completion: We are committed to completing all balance works and applying for the Occupation Certifi…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of SOLITAIRE?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SOLITAIRE in Somwari Bazar, Mumbai is P51800008101.
Is SOLITAIRE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SOLITAIRE is registered as P51800008101 and its status is "Registered and active".
What is the construction status of SOLITAIRE?
According to GharKundli's check of MahaRERA records (updated October 2026), SOLITAIRE's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does SOLITAIRE have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SOLITAIRE safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SOLITAIRE is registered on MahaRERA as P51800008101, its completion date has moved 93 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SOLITAIRE's possession date changes?
The latest dates are on SOLITAIRE's MahaRERA page (P51800008101). GharKundli's Kundli Watch sends a free WhatsApp update on SOLITAIRE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SOLITAIRE have?
According to GharKundli's check of MahaRERA records (updated October 2026), SOLITAIRE has 2 buildings filed: OM DATTA KRUPA WELFARE SRA SAHAKARI GRUHANIRMAN SANSTHA MARYADIT with 21 floors and 54 units; SOLITAIRE HEIGHTS with 26 floors and 102 units.
What are the flat sizes (carpet area) in SOLITAIRE?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for SOLITAIRE: 1 BHK: 287 to 449 sq ft carpet (87 homes); 2 BHK: 681 to 713 sq ft carpet (59 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does SOLITAIRE have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 42 covered car parking spaces for SOLITAIRE.
How big is the land of SOLITAIRE?
According to GharKundli's check of MahaRERA records (updated October 2026), SOLITAIRE stands on 3,466 sq m of land (about 0.9 acres), with 6,963 sq m of sanctioned built-up area and 101 sq m of recreational open space.
Where can I read reviews of SOLITAIRE?
Google Maps has reviews of SOLITAIRE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SOLITAIRE?
SOLITAIRE by SOLITAIRE CONSTRUCTIONS is in Somwari Bazar, Mumbai (pincode 400064), near Malad West, Malad East, Borivali, Maharashtra, and is registered on MahaRERA as P51800008101, per GharKundli's check of MahaRERA records.
How many homes are in SOLITAIRE?
According to GharKundli's check of MahaRERA records (updated October 2026), SOLITAIRE has 146 homes in 2 towers registered on MahaRERA, and 76% of them are sold or booked.
When was SOLITAIRE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SOLITAIRE was registered on MahaRERA on 18 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on SOLITAIRE?
1 court case is listed for SOLITAIRE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of SOLITAIRE?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SOLITAIRE CONSTRUCTIONS.
Check it yourself on MahaRERA
- How to check the possession date of SOLITAIRE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Borivali
- SAFFRONWOODS CHSL
- L&T Realty Ahana Tower B
- L&T Realty Ahana Tower A
- PARSHURAM HEIGHTS
- AVIRAHI ELEGANCE
- MARU MANSION
- SHRADDHA SKYLINE
- RASHMI ICON
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.