BBJ Siena
by Geetai Developers Private Limited · Vikhroli East, MumbaiAlso near Kanjurmarg East, Vikhroli West, Bhandup West
Possession date of BBJ Siena: 30 April 2027, moved from 30 December 2022 (48 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800008680, and currently active. Its completion date has moved from December 2022 to April 2027: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 31 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about BBJ Siena?
How the possession date of BBJ Siena has moved
30 December 2022
Completion date given when the project was registered
30 June 2024
Extended at the builder's request (MahaRERA application EXT51800013344)
Reason the builder gave MahaRERA: “The reasons for delay are not intentional and detailed in the application itself and affidavit cum declaration, application letter & 110 resolution / consents taken for extension are attached herewith.”
31 December 2026
Extended at the builder's request (MahaRERA application EXT51800024431)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons. We have consent of 57.80% allottees for purpose of e…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons. We have consent of 57.80% allottees for purpose of extension of RERA registration period of the said project”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: BBJ Siena’s extension records on MahaRERA (P51800008680), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on BBJ Siena
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 31 complaints and 4 court cases, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800008680
- Status
- Registered and active
- Builder
- Geetai Developers Private Limited
- Location
- Vikhroli East, Mumbai · 400083
- Project type
- Residential / Group Housing
- Registered on
- 19 Aug 2017
- Completion date at registration
- December 2022
- Latest completion date
- April 2027
- Delay so far
- 48 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 330
- Towers
- 2
- Complaints on MahaRERA
- 31
- Court cases listed
- 4
- Appeals at the tribunal
- 5
- Title report on file
- Not found
Construction progress of BBJ Siena, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A Wing and B Wing | 100% | 100% | 88% | 80% |
| C Wing and D Wing | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on BBJ Siena every month.
BBJ Siena: buildings, flats and land, as filed on MahaRERA
- Buildings: A Wing and B Wing (22 floors) · C Wing and D Wing (26 floors)
- Land: 5,686 sq m (about 1.4 acres) · sanctioned built-up 13,120 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of BBJ Siena →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
BBJ Siena: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about BBJ Siena
What is the possession date of BBJ Siena?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for BBJ Siena in Vikhroli East, Mumbai is 30 April 2027 — 48 months later than 30 December 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for BBJ Siena?
Builders and listing sites often quote an earlier "target" date for handover. The completion date BBJ Siena's builder has filed on MahaRERA, the official one, is 30 April 2027, already 48 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of BBJ Siena extended?
According to GharKundli's check of MahaRERA records (updated October 2026), BBJ Siena's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2024, giving the reason "The reasons for delay are not intentional and detailed in the application itself and affidavit cum declaration, application letter & 110 resolution / consents taken for extension are attached herewith."; to 31 December 2026, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons. We have consent of 57.80% allottees for purpose of extension of RERA registration period of the said project". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of BBJ Siena?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of BBJ Siena in Vikhroli East, Mumbai is P51800008680.
Is BBJ Siena registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), BBJ Siena is registered as P51800008680 and its status is "Registered and active".
What is the construction status of BBJ Siena?
According to GharKundli's check of MahaRERA records (updated October 2026), BBJ Siena's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does BBJ Siena have complaints on MahaRERA?
31 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is BBJ Siena safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), BBJ Siena is registered on MahaRERA as P51800008680, its completion date has moved 48 months since registration and 31 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if BBJ Siena's possession date changes?
The latest dates are on BBJ Siena's MahaRERA page (P51800008680). GharKundli's Kundli Watch sends a free WhatsApp update on BBJ Siena every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does BBJ Siena have?
According to GharKundli's check of MahaRERA records (updated October 2026), BBJ Siena has 2 buildings filed: A Wing and B Wing with 22 floors; C Wing and D Wing with 26 floors.
How big is the land of BBJ Siena?
According to GharKundli's check of MahaRERA records (updated October 2026), BBJ Siena stands on 5,686 sq m of land (about 1.4 acres), with 13,120 sq m of sanctioned built-up area.
Where can I read reviews of BBJ Siena?
Google Maps has reviews of BBJ Siena written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 31 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is BBJ Siena?
BBJ Siena by Geetai Developers Private Limited is in Vikhroli East, Mumbai (pincode 400083), near Kanjurmarg East, Vikhroli West, Bhandup West, Maharashtra, and is registered on MahaRERA as P51800008680, per GharKundli's check of MahaRERA records.
How many homes are in BBJ Siena?
According to GharKundli's check of MahaRERA records (updated October 2026), BBJ Siena has 330 homes in 2 towers registered on MahaRERA.
When was BBJ Siena registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), BBJ Siena was registered on MahaRERA on 19 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on BBJ Siena?
4 court cases are listed for BBJ Siena on MahaRERA, and 5 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of BBJ Siena?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Geetai Developers Private Limited.
Check it yourself on MahaRERA
- How to check the possession date of BBJ Siena
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Vikhroli East
- Element 7 8
- Shubh Elanza
- Shree Balaji 7
- Kannamwar Nagar Panchsheel CHSL
- RUDRA VISHWAROOP RESIDENCY
- Truearth VEDAA
- Pragati Pinnacle
- Godrej Ivara
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.