One World Phase I
by SIMAR PRIDE VENTURES LLP · PratapNagar Shahnoorwadi, AurangabadAlso near Osmanpura, Shahanoorwadi, Satara Parisar
Possession date of One World Phase I: 30 April 2029. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51500050146, and currently active. Its completion date is now April 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about One World Phase I?
How the possession date of One World Phase I has moved
31 December 2028
Completion date given when the project was registered
30 April 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: One World Phase I’s extension records on MahaRERA (P51500050146), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on One World Phase I
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 2 court cases, and how it ended
- Construction pace against the April 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51500050146
- Status
- Registered and active
- Builder
- SIMAR PRIDE VENTURES LLP
- Location
- PratapNagar Shahnoorwadi, Aurangabad · 431005
- Project type
- Others
- Registered on
- 21 Mar 2023
- Completion date at registration
- December 2028
- Latest completion date
- April 2029
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 567
- Sold or booked
- 67%
- Towers
- 5
- Complaints on MahaRERA
- 1
- Court cases listed
- 2
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 9
Construction progress of One World Phase I, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Building A1-A2 | 0% | 70% | 40% | 0% |
| Building B1 | 0% | 60% | 50% | 0% |
| Building C1-C2 | 0% | 55% | 50% | 0% |
| Building E1 E2 E3 E4 | 0% | 100% | 100% | 90% |
| MHADA | 0% | 100% | 100% | 90% |
Commencement certificate (CC), as filed on MahaRERA
- Building A1-A2: covers 23 floors
- Building B1: covers 23 floors
- Building C1-C2: covers 23 floors
- Building E1 E2 E3 E4: covers 4 floors
- MHADA: covers 17 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on One World Phase I every month.
One World Phase I: buildings, flats and land, as filed on MahaRERA
- Buildings: Building A1-A2 (23 floors, 160 units) · Building B1 (23 floors, 118 units) · Building C1-C2 (23 floors, 160 units) · Building E1 E2 E3 E4 (4 floors, 133 units) · MHADA (17 floors, 129 units)
- Land: 16,470 sq m (about 4.1 acres) · sanctioned built-up 73,439 sq m · recreational space 1,653 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of One World Phase I →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
One World Phase I: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about One World Phase I
What is the possession date of One World Phase I?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for One World Phase I in PratapNagar Shahnoorwadi, Aurangabad is 30 April 2029, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for One World Phase I?
Builders and listing sites often quote an earlier "target" date for handover. The completion date One World Phase I's builder has filed on MahaRERA, the official one, is 30 April 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of One World Phase I?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of One World Phase I in PratapNagar Shahnoorwadi, Aurangabad is P51500050146.
Is One World Phase I registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), One World Phase I is registered as P51500050146 and its status is "Registered and active".
What is the construction status of One World Phase I?
According to GharKundli's check of MahaRERA records (updated November 2026), One World Phase I's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 55% to 100% across 5 towers. GharKundli's full report compares construction progress with the deadline.
Does One World Phase I have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is One World Phase I safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), One World Phase I is registered on MahaRERA as P51500050146, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if One World Phase I's possession date changes?
The latest dates are on One World Phase I's MahaRERA page (P51500050146). GharKundli's Kundli Watch sends a free WhatsApp update on One World Phase I every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does One World Phase I have?
According to GharKundli's check of MahaRERA records (updated November 2026), One World Phase I has 5 buildings filed: Building A1-A2 with 23 floors and 160 units; Building B1 with 23 floors and 118 units; Building C1-C2 with 23 floors and 160 units; Building E1 E2 E3 E4 with 4 floors and 133 units; MHADA with 17 floors and 129 units.
How big is the land of One World Phase I?
According to GharKundli's check of MahaRERA records (updated November 2026), One World Phase I stands on 16,470 sq m of land (about 4.1 acres), with 73,439 sq m of sanctioned built-up area and 1,653 sq m of recreational open space.
Where can I read reviews of One World Phase I?
Google Maps has reviews of One World Phase I written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is One World Phase I?
One World Phase I by SIMAR PRIDE VENTURES LLP is in PratapNagar Shahnoorwadi, Aurangabad (pincode 431005), near Osmanpura, Shahanoorwadi, Satara Parisar, Maharashtra, and is registered on MahaRERA as P51500050146, per GharKundli's check of MahaRERA records.
How many homes are in One World Phase I?
According to GharKundli's check of MahaRERA records (updated November 2026), One World Phase I has 567 homes in 5 towers registered on MahaRERA, and 67% of them are sold or booked.
When was One World Phase I registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), One World Phase I was registered on MahaRERA on 21 March 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on One World Phase I?
2 court cases are listed for One World Phase I on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of One World Phase I?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SIMAR PRIDE VENTURES LLP, which has 9 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of One World Phase I
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Aurangabad →
Other projects in Aurangabad
- NABHRAJ TRILOK HEIGHTS MHADA
- PARAM SUVARNVASTU
- KHINVANSARA AURA
- BUSINESS TRIANGLE
- Siddhi Ellora Business Park
- PRASSANA HIGH CLASS CITY PHASE - I
- HORIZON
- Gaia Carnival Apartment Phase II
Other projects by SIMAR PRIDE VENTURES LLP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.