SHLOK SIDDHI
by SHLOK REALITIES · Chikalthana, Aurangabad, Aurangabad
Possession date of SHLOK SIDDHI: 28 February 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51500050908, and currently active. Its completion date is now February 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about SHLOK SIDDHI?
How the possession date of SHLOK SIDDHI has moved
31 October 2026
Completion date given when the project was registered
28 February 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SHLOK SIDDHI’s extension records on MahaRERA (P51500050908), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SHLOK SIDDHI
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the February 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51500050908
- Status
- Registered and active
- Builder
- SHLOK REALITIES
- Location
- Chikalthana, Aurangabad, Aurangabad · 431001
- Project type
- Residential / Group Housing
- Registered on
- 15 May 2023
- Completion date at registration
- October 2026
- Latest completion date
- February 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 58
- Sold or booked
- 46%
- Towers
- 4
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of SHLOK SIDDHI, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A Type Building | 100% | 100% | 85% | 50% |
| B Type Building | 100% | 100% | 95% | 95% |
| C Type Building | 100% | 100% | 100% | 100% |
| G Type Building | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- A Type Building: covers 8 floors
- B Type Building: covers 3 floors
- C Type Building: covers 3 floors
- G Type Building: covers 2 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHLOK SIDDHI every month.
SHLOK SIDDHI: buildings, flats and land, as filed on MahaRERA
- Buildings: A Type Building (8 floors, 28 units) · B Type Building (3 floors, 16 units) · C Type Building (3 floors, 6 units) · G Type Building (2 floors, 8 units)
- Land: 3,937 sq m (about 1.0 acres) · sanctioned built-up 4,403 sq m
The builder’s record and reviews
Shlok Realities has 3 projects on MahaRERA since 2021, this one included. Of the 3 GharKundli has checked: 2 still being built, none past the promised date yet; 1 lapsed. 1 complaint on MahaRERA across 1 project.
Read Google reviews of SHLOK SIDDHI →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SHLOK SIDDHI: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SHLOK SIDDHI
What is the possession date of SHLOK SIDDHI?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SHLOK SIDDHI in Chikalthana, Aurangabad, Aurangabad is 28 February 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SHLOK SIDDHI?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SHLOK SIDDHI's builder has filed on MahaRERA, the official one, is 28 February 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of SHLOK SIDDHI?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SHLOK SIDDHI in Chikalthana, Aurangabad, Aurangabad is P51500050908.
Is SHLOK SIDDHI registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SHLOK SIDDHI is registered as P51500050908 and its status is "Registered and active".
What is the construction status of SHLOK SIDDHI?
According to GharKundli's check of MahaRERA records (updated November 2026), SHLOK SIDDHI's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 4 towers. GharKundli's full report compares construction progress with the deadline.
Does SHLOK SIDDHI have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is SHLOK SIDDHI safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), SHLOK SIDDHI is registered on MahaRERA as P51500050908, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SHLOK SIDDHI's possession date changes?
The latest dates are on SHLOK SIDDHI's MahaRERA page (P51500050908). GharKundli's Kundli Watch sends a free WhatsApp update on SHLOK SIDDHI every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SHLOK SIDDHI have?
According to GharKundli's check of MahaRERA records (updated November 2026), SHLOK SIDDHI has 4 buildings filed: A Type Building with 8 floors and 28 units; B Type Building with 3 floors and 16 units; C Type Building with 3 floors and 6 units; G Type Building with 2 floors and 8 units.
How big is the land of SHLOK SIDDHI?
According to GharKundli's check of MahaRERA records (updated November 2026), SHLOK SIDDHI stands on 3,937 sq m of land (about 1.0 acres), with 4,403 sq m of sanctioned built-up area.
What is the track record of SHLOK SIDDHI's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Shlok Realities has 3 projects on MahaRERA since 2021, this one included. Of the 3 GharKundli has checked: 2 still being built, none past the promised date yet; 1 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SHLOK SIDDHI?
Google Maps has reviews of SHLOK SIDDHI written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SHLOK SIDDHI?
SHLOK SIDDHI by SHLOK REALITIES is in Chikalthana, Aurangabad, Aurangabad (pincode 431001), Maharashtra, and is registered on MahaRERA as P51500050908, per GharKundli's check of MahaRERA records.
How many homes are in SHLOK SIDDHI?
According to GharKundli's check of MahaRERA records (updated November 2026), SHLOK SIDDHI has 58 homes in 4 towers registered on MahaRERA, and 46% of them are sold or booked.
When was SHLOK SIDDHI registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SHLOK SIDDHI was registered on MahaRERA on 15 May 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on SHLOK SIDDHI?
No court cases are listed for SHLOK SIDDHI on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of SHLOK SIDDHI?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHLOK REALITIES, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SHLOK SIDDHI
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Aurangabad →
Other projects in Aurangabad
- NABHRAJ TRILOK HEIGHTS MHADA
- PARAM SUVARNVASTU
- KHINVANSARA AURA
- BUSINESS TRIANGLE
- PRASSANA HIGH CLASS CITY PHASE - I
- Siddhi Ellora Business Park
- HORIZON
- Gaia Carnival Apartment Phase II
Other projects by SHLOK REALITIES
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.