Nayantara Presidency Phase 3
by Pancharatna Builcon Pvt. Ltd · Rajiv nagar, NashikAlso near Indira Nagar, Indiranagar, Trimurti Chowk
Possession date of Nayantara Presidency Phase 3: 30 July 2027, moved from 30 March 2023 (48 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51600000133, and currently active. Its completion date has moved from March 2023 to July 2027: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Nayantara Presidency Phase 3?
How the possession date of Nayantara Presidency Phase 3 has moved
30 March 2023
Completion date given when the project was registered
30 March 2026
Extended at the builder's request (MahaRERA application EXT51600015224)
Reason the builder gave MahaRERA:
“Date: 30.03.2023 To, The RERA, Maharastra State. Sir, The Project Nayantara Presidency by - Pancharatna Buildcon Pvt. Ltd. are divided into following: Phase-3-Wing- B, C & D wings (RERA No. – P51600000133) The said has received complete app…” Read the full reason
“Date: 30.03.2023 To, The RERA, Maharastra State. Sir, The Project Nayantara Presidency by - Pancharatna Buildcon Pvt. Ltd. are divided into following: Phase-3-Wing- B, C & D wings (RERA No. – P51600000133) The said has received complete approval for all phases from Nashik Municipal Corporation. The CC No.-B5/401/17567 dated 09.03.2018. Now after securing all the necessary approvals from NMC, EC department, MCPB department, etc. We are in state to complete the project with our full capacity. We seek your kind approval in extending our committed project delivery timelines from 30th March 2023…”30 March 2027
Extended at the builder's request (MahaRERA application EA27032620394)
Reason the builder gave MahaRERA:
“1. Shortage of Key Construction Materials: The project execution was significantly impacted due to acute shortage and irregular supply of essential construction materials such as sand and metal. This directly affected RCC work and delayed s…” Read the full reason
“1. Shortage of Key Construction Materials: The project execution was significantly impacted due to acute shortage and irregular supply of essential construction materials such as sand and metal. This directly affected RCC work and delayed structural timelines. 2. Disruption in Procurement of Finishing Materials: Procurement of tiles and allied materials was affected due to temporary closure and reduced operations of manufacturing units at Morbi, Gujarat, resulting in delay in finishing activities. 3. Impact of Ongoing Geopolitical Conditions: The prevailing international geopolitical tensio…”30 July 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Nayantara Presidency Phase 3’s extension records on MahaRERA (P51600000133), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Nayantara Presidency Phase 3
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints, and how it ended
- Construction pace against the July 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Nayantara Presidency Phase 1P51600000245 · possession 9 May 2024
- Nayantara Presidency Phase 2P51600000079 · possession 30 Mar 2025
- Nayantara Presidency Phase 4P51600000098 · possession 30 Jul 2028
- MahaRERA registration
- P51600000133
- Status
- Registered and active
- Builder
- Pancharatna Builcon Pvt. Ltd
- Location
- Rajiv nagar, Nashik · 422002
- Project type
- Residential / Group Housing
- Registered on
- 5 Jul 2017
- Completion date at registration
- March 2023
- Latest completion date
- July 2027
- Delay so far
- 48 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 166
- Sold or booked
- 41%
- Towers
- 3
- Complaints on MahaRERA
- 2
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of Nayantara Presidency Phase 3, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| B-Bouganvillea | 100% | 100% | 75% | 30% |
| C-Carnation | 100% | 100% | 75% | 35% |
| D-Daisy | 100% | 100% | 75% | 35% |
Commencement certificate (CC), as filed on MahaRERA
- B-Bouganvillea: covers 14 floors
- C-Carnation: covers 14 floors
- D-Daisy: covers 14 floors
Latest CC order on MahaRERA: dated 07/04/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Nayantara Presidency Phase 3 every month.
Nayantara Presidency Phase 3: buildings, flats and land, as filed on MahaRERA
- Buildings: B-Bouganvillea (16 floors, 56 units) · C-Carnation (16 floors, 56 units) · D-Daisy (16 floors, 54 units)
- Car parking: 134 covered, 21 open
- Land: 28,300 sq m (about 7.0 acres) · sanctioned built-up 12,166 sq m · recreational space 666 sq m
- Boundaries filed include: Mumbai-Agra Highway
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Pancharatna Builcon has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 21 months); 2 still being built, 2 past the promised date (typically 21 months late). 5 complaints on MahaRERA across 4 projects.
Read Google reviews of Nayantara Presidency Phase 3 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Nayantara Presidency Phase 3: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Nayantara Presidency Phase 3
What is the possession date of Nayantara Presidency Phase 3?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Nayantara Presidency Phase 3 in Rajiv nagar, Nashik is 30 July 2027 — 48 months later than 30 March 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Nayantara Presidency Phase 3?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Nayantara Presidency Phase 3's builder has filed on MahaRERA, the official one, is 30 July 2027, already 48 months later than the 30 March 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Nayantara Presidency Phase 3 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Nayantara Presidency Phase 3's builder applied to MahaRERA to extend the completion date 2 times: to 30 March 2026, giving the reason "Date: 30.03.2023 To, The RERA, Maharastra State. Sir, The Project Nayantara Presidency by - Pancharatna Buildcon Pvt. Ltd. are divided into following: Phase-3-Wing- B, C & D wings (RERA No. – P51600000133) The said has received complete approval for all phases from Nashik Municipal Corporation. The CC No.-B5/401/17567 dated 09.03.2018. Now after securing all the necessary approvals from NMC, EC department, MCPB department, etc. We are in state to complete the project with our full capacity. We seek your kind approval in extending our committed project delivery timelines from 30th March 2023…"; to 30 March 2027, giving the reason "1. Shortage of Key Construction Materials: The project execution was significantly impacted due to acute shortage and irregular supply of essential construction materials such as sand and metal. This directly affected RCC work and delayed structural timelines. 2. Disruption in Procurement of Finishing Materials: Procurement of tiles and allied materials was affected due to temporary closure and reduced operations of manufacturing units at Morbi, Gujarat, resulting in delay in finishing activities. 3. Impact of Ongoing Geopolitical Conditions: The prevailing international geopolitical tensio…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Nayantara Presidency Phase 3?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Nayantara Presidency Phase 3 in Rajiv nagar, Nashik is P51600000133.
Is Nayantara Presidency Phase 3 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Nayantara Presidency Phase 3 is registered as P51600000133 and its status is "Registered and active".
What is the construction status of Nayantara Presidency Phase 3?
According to GharKundli's check of MahaRERA records (updated October 2026), Nayantara Presidency Phase 3's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does Nayantara Presidency Phase 3 have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Nayantara Presidency Phase 3 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Nayantara Presidency Phase 3 is registered on MahaRERA as P51600000133, its completion date has moved 48 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Nayantara Presidency Phase 3 have other wings or phases?
Yes. MahaRERA lists 3 other registrations of the same project, each with its own possession date: Nayantara Presidency Phase 1 (P51600000245, possession 9 May 2024); Nayantara Presidency Phase 2 (P51600000079, possession 30 Mar 2025); Nayantara Presidency Phase 4 (P51600000098, possession 30 Jul 2028). Check that your agreement names the registration of your own wing.
How can I get updates if Nayantara Presidency Phase 3's possession date changes?
The latest dates are on Nayantara Presidency Phase 3's MahaRERA page (P51600000133). GharKundli's Kundli Watch sends a free WhatsApp update on Nayantara Presidency Phase 3 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Nayantara Presidency Phase 3 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Nayantara Presidency Phase 3 has 3 buildings filed: B-Bouganvillea with 16 floors and 56 units; C-Carnation with 16 floors and 56 units; D-Daisy with 16 floors and 54 units.
How much parking does Nayantara Presidency Phase 3 have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 134 covered and 21 open car parking spaces for Nayantara Presidency Phase 3.
How big is the land of Nayantara Presidency Phase 3?
According to GharKundli's check of MahaRERA records (updated October 2026), Nayantara Presidency Phase 3 stands on 28,300 sq m of land (about 7.0 acres), with 12,166 sq m of sanctioned built-up area and 666 sq m of recreational open space.
What is the track record of Nayantara Presidency Phase 3's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Pancharatna Builcon has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 21 months); 2 still being built, 2 past the promised date (typically 21 months late). 5 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Nayantara Presidency Phase 3?
Google Maps has reviews of Nayantara Presidency Phase 3 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Nayantara Presidency Phase 3?
Nayantara Presidency Phase 3 by Pancharatna Builcon Pvt. Ltd is in Rajiv nagar, Nashik (pincode 422002), near Indira Nagar, Indiranagar, Trimurti Chowk, Maharashtra, and is registered on MahaRERA as P51600000133, per GharKundli's check of MahaRERA records. Its boundaries filed there include Mumbai-Agra Highway.
How many homes are in Nayantara Presidency Phase 3?
According to GharKundli's check of MahaRERA records (updated October 2026), Nayantara Presidency Phase 3 has 166 homes in 3 towers registered on MahaRERA, and 41% of them are sold or booked.
When was Nayantara Presidency Phase 3 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Nayantara Presidency Phase 3 was registered on MahaRERA on 5 July 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Nayantara Presidency Phase 3?
No court cases are listed for Nayantara Presidency Phase 3 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Nayantara Presidency Phase 3?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Pancharatna Builcon Pvt. Ltd, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Nayantara Presidency Phase 3
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Nashik →
Other projects in Nashik
- Nayantara Presidency Phase 4
- Nayantara Presidency Phase 2
- Fortunes Emerald Park
- Laxmi Commercial Complex
- Quillion Residencies at Quillion Park - Phase 2
- SHIV KUNJ
- YUNUS RESIDENCY
- SHUBHSANKALP CO-OPERATIVE HOUSING SOCIETY LIMITED
Other projects by Pancharatna Builcon Pvt. Ltd
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.