EKTA GREENVILLE PHASE 2 WING O , P , Q AND R

by EKTA HOUSING PRIVATE LIMITED · Kalanagar, Bandra East, Nashik

Possession date of EKTA GREENVILLE PHASE 2 WING O , P , Q AND R: 30 April 2027, moved from 30 June 2019 (90 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51600000685, and currently active. Its completion date has moved from June 2019 to April 2027: 90 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. MahaRERA has issued 3 regulatory orders on this project. 8 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about EKTA GREENVILLE PHASE 2 WING O , P , Q AND R?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of EKTA GREENVILLE PHASE 2 WING O , P , Q AND R has moved

  1. 30 June 2019

    Completion date given when the project was registered

  2. 29 June 2020

    Extended at the builder's request (MahaRERA application EXT51600000830)

    Reason the builder gave MahaRERA: “Due to scarcity of availability of the resources and also some technical reasons.”
  3. 31 March 2022

    Extended at the builder's request (MahaRERA application EXT51600009833)

    Reason the builder gave MahaRERA:
    “In the above said project, there are 4 wings O,P, Q & R and we have obtained Occupation Certificate for Wing O & P. Now we are applying for extension date for Q & R wing. In the Q & R Wing there are 24 Registered flats and we have obtained…” Read the full reason“In the above said project, there are 4 wings O,P, Q & R and we have obtained Occupation Certificate for Wing O & P. Now we are applying for extension date for Q & R wing. In the Q & R Wing there are 24 Registered flats and we have obtained consent of 51% allottee i.e. 13 allottees. Due to non availability of material and labour for the constructions of the Project and outbreak of novel Corona Virus Pandemic and imposition of the Lock down in entire State of Maharashtra which caused delay in Project. Due to non availability of material and labour for the constructions of the Project and outb…”
  4. 30 September 2023

    Extended at the builder's request (MahaRERA application EXT51600012726)

    Reason the builder gave MahaRERA:
    “We hereby apply for extension u/s 7(3) for the registered project naming Ekta Greenville Phase II bearing MahaRERA registration No. P51600000685 comprising of Four wings i.e. O,P,Q and R, out of the Two wings i.e. O and P have received O.C…” Read the full reason“We hereby apply for extension u/s 7(3) for the registered project naming Ekta Greenville Phase II bearing MahaRERA registration No. P51600000685 comprising of Four wings i.e. O,P,Q and R, out of the Two wings i.e. O and P have received O.C on 06th January, 2020. The O.C still pending for wings Q and R, and while the Buildings are almost complete, application for O.C is pending only for some technical issue. The current registration expired on 30.09.2022, and we are applying u/s 7(3) for the extension till 30.09.2023. As prescribed under circular No. 07/2019 dated 8th Feb, 2019 the details o…”
  5. 31 March 2025

    Extended at the builder's request (MahaRERA application EXT51600017875)

    Reason the builder gave MahaRERA: “Reply Annexed.”
  6. 31 December 2026

    Extended at the builder's request (MahaRERA application EA11092401792)

    Reason the builder gave MahaRERA: “Shortage of sand and skilled labour”
  7. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: EKTA GREENVILLE PHASE 2 WING O , P , Q AND R’s extension records on MahaRERA (P51600000685), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on EKTA GREENVILLE PHASE 2 WING O , P , Q AND R

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 8 complaints and 1 court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51600000685
Status
Registered and active
Builder
EKTA HOUSING PRIVATE LIMITED
Location
Kalanagar, Bandra East, Nashik · 422010
Project type
Residential / Group Housing
Registered on
20 Jul 2017
Completion date at registration
June 2019
Latest completion date
April 2027
Delay so far
90 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
128
Sold or booked
81%
Towers
4
Complaints on MahaRERA
8
Court cases listed
1
MahaRERA regulatory orders
3
Title report on file
Not found
Builder's other MahaRERA projects
8

Construction progress of EKTA GREENVILLE PHASE 2 WING O , P , Q AND R, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
WING O100%100%100%100%
WING P100%100%100%100%
WING Q100%100%100%50%
WING R100%95%75%11%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on EKTA GREENVILLE PHASE 2 WING O , P , Q AND R every month.

EKTA GREENVILLE PHASE 2 WING O , P , Q AND R: buildings, flats and land, as filed on MahaRERA

  • Buildings: WING O (10 floors) · WING P (10 floors) · WING Q (10 floors) · WING R (10 floors)
  • Land: 1,219 sq m (about 0.3 acres) · sanctioned built-up 9,007 sq m · recreational space 4,512 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of EKTA GREENVILLE PHASE 2 WING O , P , Q AND R →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

EKTA GREENVILLE PHASE 2 WING O , P , Q AND R: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about EKTA GREENVILLE PHASE 2 WING O , P , Q AND R

What is the possession date of EKTA GREENVILLE PHASE 2 WING O , P , Q AND R?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for EKTA GREENVILLE PHASE 2 WING O , P , Q AND R in Kalanagar, Bandra East, Nashik is 30 April 2027 — 90 months later than 30 June 2019, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for EKTA GREENVILLE PHASE 2 WING O , P , Q AND R?

Builders and listing sites often quote an earlier "target" date for handover. The completion date EKTA GREENVILLE PHASE 2 WING O , P , Q AND R's builder has filed on MahaRERA, the official one, is 30 April 2027, already 90 months later than the 30 June 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of EKTA GREENVILLE PHASE 2 WING O , P , Q AND R extended?

According to GharKundli's check of MahaRERA records (updated October 2026), EKTA GREENVILLE PHASE 2 WING O , P , Q AND R's builder applied to MahaRERA to extend the completion date 5 times: to 29 June 2020, giving the reason "Due to scarcity of availability of the resources and also some technical reasons."; to 31 March 2022, giving the reason "In the above said project, there are 4 wings O,P, Q & R and we have obtained Occupation Certificate for Wing O & P. Now we are applying for extension date for Q & R wing. In the Q & R Wing there are 24 Registered flats and we have obtained consent of 51% allottee i.e. 13 allottees. Due to non availability of material and labour for the constructions of the Project and outbreak of novel Corona Virus Pandemic and imposition of the Lock down in entire State of Maharashtra which caused delay in Project. Due to non availability of material and labour for the constructions of the Project and outb…"; to 30 September 2023, giving the reason "We hereby apply for extension u/s 7(3) for the registered project naming Ekta Greenville Phase II bearing MahaRERA registration No. P51600000685 comprising of Four wings i.e. O,P,Q and R, out of the Two wings i.e. O and P have received O.C on 06th January, 2020. The O.C still pending for wings Q and R, and while the Buildings are almost complete, application for O.C is pending only for some technical issue. The current registration expired on 30.09.2022, and we are applying u/s 7(3) for the extension till 30.09.2023. As prescribed under circular No. 07/2019 dated 8th Feb, 2019 the details o…"; to 31 March 2025, giving the reason "Reply Annexed."; to 31 December 2026, giving the reason "Shortage of sand and skilled labour". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of EKTA GREENVILLE PHASE 2 WING O , P , Q AND R?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of EKTA GREENVILLE PHASE 2 WING O , P , Q AND R in Kalanagar, Bandra East, Nashik is P51600000685.

Is EKTA GREENVILLE PHASE 2 WING O , P , Q AND R registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), EKTA GREENVILLE PHASE 2 WING O , P , Q AND R is registered as P51600000685 and its status is "Registered and active".

What is the construction status of EKTA GREENVILLE PHASE 2 WING O , P , Q AND R?

According to GharKundli's check of MahaRERA records (updated October 2026), EKTA GREENVILLE PHASE 2 WING O , P , Q AND R's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 95% to 100% across 4 towers. GharKundli's full report compares construction progress with the deadline.

Does EKTA GREENVILLE PHASE 2 WING O , P , Q AND R have complaints on MahaRERA?

8 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is EKTA GREENVILLE PHASE 2 WING O , P , Q AND R safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), EKTA GREENVILLE PHASE 2 WING O , P , Q AND R is registered on MahaRERA as P51600000685, its completion date has moved 90 months since registration and 8 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if EKTA GREENVILLE PHASE 2 WING O , P , Q AND R's possession date changes?

The latest dates are on EKTA GREENVILLE PHASE 2 WING O , P , Q AND R's MahaRERA page (P51600000685). GharKundli's Kundli Watch sends a free WhatsApp update on EKTA GREENVILLE PHASE 2 WING O , P , Q AND R every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does EKTA GREENVILLE PHASE 2 WING O , P , Q AND R have?

According to GharKundli's check of MahaRERA records (updated October 2026), EKTA GREENVILLE PHASE 2 WING O , P , Q AND R has 4 buildings filed: WING O with 10 floors; WING P with 10 floors; WING Q with 10 floors; WING R with 10 floors.

How big is the land of EKTA GREENVILLE PHASE 2 WING O , P , Q AND R?

According to GharKundli's check of MahaRERA records (updated October 2026), EKTA GREENVILLE PHASE 2 WING O , P , Q AND R stands on 1,219 sq m of land (about 0.3 acres), with 9,007 sq m of sanctioned built-up area and 4,512 sq m of recreational open space.

Where can I read reviews of EKTA GREENVILLE PHASE 2 WING O , P , Q AND R?

Google Maps has reviews of EKTA GREENVILLE PHASE 2 WING O , P , Q AND R written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 8 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is EKTA GREENVILLE PHASE 2 WING O , P , Q AND R?

EKTA GREENVILLE PHASE 2 WING O , P , Q AND R by EKTA HOUSING PRIVATE LIMITED is in Kalanagar, Bandra East, Nashik (pincode 422010), Maharashtra, and is registered on MahaRERA as P51600000685, per GharKundli's check of MahaRERA records.

How many homes are in EKTA GREENVILLE PHASE 2 WING O , P , Q AND R?

According to GharKundli's check of MahaRERA records (updated October 2026), EKTA GREENVILLE PHASE 2 WING O , P , Q AND R has 128 homes in 4 towers registered on MahaRERA, and 81% of them are sold or booked.

When was EKTA GREENVILLE PHASE 2 WING O , P , Q AND R registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), EKTA GREENVILLE PHASE 2 WING O , P , Q AND R was registered on MahaRERA on 20 July 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on EKTA GREENVILLE PHASE 2 WING O , P , Q AND R?

1 court case is listed for EKTA GREENVILLE PHASE 2 WING O , P , Q AND R on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of EKTA GREENVILLE PHASE 2 WING O , P , Q AND R?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is EKTA HOUSING PRIVATE LIMITED, which has 8 other projects registered on MahaRERA.

All projects with possession due in 2027 in Nashik →

Other projects in Nashik

All 222 projects in Ambad (422010) →

Other projects by EKTA HOUSING PRIVATE LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.