ICHHAMANI

by SANKET BUILDTECH · Near Ramleela Lawns, Nashik

Possession: ICHHAMANI is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51600004120. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about ICHHAMANI?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of ICHHAMANI has moved

  1. 31 December 2018

    Completion date given when the project was registered

  2. 31 March 2024

    Extended at the builder's request (MahaRERA application EXT51600017138)

    Reason the builder gave MahaRERA: “WE HAVE APPLIED FOR OCCUPANCY CERTIFICATE TO LOCAL PLANNING AUTHORITYWITHIN DUE DATE. HOWEVER WE DID NOT RECEIVE COPY OF COMPLETION CERTIFICATE FROM LOCAL PLANNING AUTHORITY IN DUE TIME. HENCE, WE ARE APPLYING FOR EXTENTION.”

Source: ICHHAMANI’s extension records on MahaRERA (P51600004120), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on ICHHAMANI

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51600004120
Status
Completed
Builder
SANKET BUILDTECH
Location
Near Ramleela Lawns, Nashik · 422003
Project type
Residential / Group Housing
Registered on
8 Aug 2017
Completion date at registration
December 2018
Latest completion date
March 2024
Delay so far
63 months
Homes
20
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of ICHHAMANI, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
ICCHAMANI100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on ICHHAMANI every month.

ICHHAMANI: buildings, flats and land, as filed on MahaRERA

  • Buildings: ICCHAMANI (6 floors)
  • Land: 507 sq m (about 0.1 acres) · sanctioned built-up 710 sq m
  • Boundaries filed include: 9 MTR COLONY ROAD, 6 MTR COLONY ROAD, COLONY ROAD

The builder’s record and reviews

Shree Sanket Developers (a group of 2 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 6 finished, 1 within the promised date and 5 needed more time (typically 14 months); 1 still being built, 1 past the promised date (typically 2 months late). No complaints on MahaRERA.

Read Google reviews of ICHHAMANI →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

ICHHAMANI: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about ICHHAMANI

What is the possession date of ICHHAMANI?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for ICHHAMANI in Near Ramleela Lawns, Nashik is 31 March 2024 — 63 months later than 31 December 2018, the date given at registration.

Is the builder's possession date different from the MahaRERA date for ICHHAMANI?

Builders and listing sites often quote an earlier "target" date for handover. The completion date ICHHAMANI's builder has filed on MahaRERA, the official one, is 31 March 2024, already 63 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of ICHHAMANI extended?

According to GharKundli's check of MahaRERA records (updated November 2026), ICHHAMANI's builder applied to MahaRERA to extend the completion date once: to 31 March 2024, giving the reason "WE HAVE APPLIED FOR OCCUPANCY CERTIFICATE TO LOCAL PLANNING AUTHORITYWITHIN DUE DATE. HOWEVER WE DID NOT RECEIVE COPY OF COMPLETION CERTIFICATE FROM LOCAL PLANNING AUTHORITY IN DUE TIME. HENCE, WE ARE APPLYING FOR EXTENTION.".

What is the RERA number of ICHHAMANI?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of ICHHAMANI in Near Ramleela Lawns, Nashik is P51600004120.

Is ICHHAMANI registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), ICHHAMANI is registered as P51600004120 and its status is "Completed".

What is the construction status of ICHHAMANI?

According to GharKundli's check of MahaRERA records (updated November 2026), ICHHAMANI's status on MahaRERA is "Completed". As filed by the builder, slab work on ICCHAMANI is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does ICHHAMANI have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is ICHHAMANI safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), ICHHAMANI is registered on MahaRERA as P51600004120, its MahaRERA status is "Completed", its completion date has moved 63 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if ICHHAMANI's possession date changes?

The latest dates are on ICHHAMANI's MahaRERA page (P51600004120). GharKundli's Kundli Watch sends a free WhatsApp update on ICHHAMANI every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does ICHHAMANI have?

According to GharKundli's check of MahaRERA records (updated November 2026), ICHHAMANI has one building filed: ICCHAMANI with 6 floors.

How big is the land of ICHHAMANI?

According to GharKundli's check of MahaRERA records (updated November 2026), ICHHAMANI stands on 507 sq m of land (about 0.1 acres), with 710 sq m of sanctioned built-up area.

What is the track record of ICHHAMANI's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Shree Sanket Developers (a group of 2 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 6 finished, 1 within the promised date and 5 needed more time (typically 14 months); 1 still being built, 1 past the promised date (typically 2 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of ICHHAMANI?

Google Maps has reviews of ICHHAMANI written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is ICHHAMANI?

ICHHAMANI by SANKET BUILDTECH is in Near Ramleela Lawns, Nashik (pincode 422003), Maharashtra, and is registered on MahaRERA as P51600004120, per GharKundli's check of MahaRERA records. Its boundaries filed there include 9 MTR COLONY ROAD, 6 MTR COLONY ROAD, COLONY ROAD.

How many homes are in ICHHAMANI?

According to GharKundli's check of MahaRERA records (updated November 2026), ICHHAMANI has 20 homes in 1 tower registered on MahaRERA.

When was ICHHAMANI registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), ICHHAMANI was registered on MahaRERA on 8 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on ICHHAMANI?

No court cases are listed for ICHHAMANI on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of ICHHAMANI?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SANKET BUILDTECH, which has 2 other projects registered on MahaRERA.