MALATI- MANOHAR APT

by SATISH MANOHAR DESHPANDE · Gulmohar Nagar Mhasrul, Nashik

Possession: MALATI- MANOHAR APT is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51600003147. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about MALATI- MANOHAR APT?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of MALATI- MANOHAR APT has moved

  1. 30 December 2018

    Completion date given when the project was registered

  2. 31 December 2022

    Extended at the builder's request (MahaRERA application EXT51600011147)

    Reason the builder gave MahaRERA: “Delay in taking OC”
  3. 30 June 2023

    Revised completion date on MahaRERA

Source: MALATI- MANOHAR APT’s extension records on MahaRERA (P51600003147), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on MALATI- MANOHAR APT

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51600003147
Status
Completed
Builder
SATISH MANOHAR DESHPANDE
Location
Gulmohar Nagar Mhasrul, Nashik · 422004
Project type
Residential / Group Housing
Registered on
4 Aug 2017
Completion date at registration
December 2018
Latest completion date
June 2023
Delay so far
54 months
Homes
14
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of MALATI- MANOHAR APT, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
MALATI MANOHAR100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on MALATI- MANOHAR APT every month.

MALATI- MANOHAR APT: buildings, flats and land, as filed on MahaRERA

  • Buildings: MALATI MANOHAR (6 floors)
  • Land: 502 sq m (about 0.1 acres) · sanctioned built-up 502 sq m
  • Boundaries filed include: COLONY ROAD, COLONY ROAD70

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of MALATI- MANOHAR APT →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

MALATI- MANOHAR APT: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about MALATI- MANOHAR APT

What is the possession date of MALATI- MANOHAR APT?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for MALATI- MANOHAR APT in Gulmohar Nagar Mhasrul, Nashik is 30 June 2023 — 54 months later than 30 December 2018, the date given at registration.

Is the builder's possession date different from the MahaRERA date for MALATI- MANOHAR APT?

Builders and listing sites often quote an earlier "target" date for handover. The completion date MALATI- MANOHAR APT's builder has filed on MahaRERA, the official one, is 30 June 2023, already 54 months later than the 30 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of MALATI- MANOHAR APT extended?

According to GharKundli's check of MahaRERA records (updated November 2026), MALATI- MANOHAR APT's builder applied to MahaRERA to extend the completion date once: to 31 December 2022, giving the reason "Delay in taking OC".

What is the RERA number of MALATI- MANOHAR APT?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of MALATI- MANOHAR APT in Gulmohar Nagar Mhasrul, Nashik is P51600003147.

Is MALATI- MANOHAR APT registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), MALATI- MANOHAR APT is registered as P51600003147 and its status is "Completed".

What is the construction status of MALATI- MANOHAR APT?

According to GharKundli's check of MahaRERA records (updated November 2026), MALATI- MANOHAR APT's status on MahaRERA is "Completed". As filed by the builder, slab work on MALATI MANOHAR is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does MALATI- MANOHAR APT have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is MALATI- MANOHAR APT safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), MALATI- MANOHAR APT is registered on MahaRERA as P51600003147, its MahaRERA status is "Completed", its completion date has moved 54 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if MALATI- MANOHAR APT's possession date changes?

The latest dates are on MALATI- MANOHAR APT's MahaRERA page (P51600003147). GharKundli's Kundli Watch sends a free WhatsApp update on MALATI- MANOHAR APT every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does MALATI- MANOHAR APT have?

According to GharKundli's check of MahaRERA records (updated November 2026), MALATI- MANOHAR APT has one building filed: MALATI MANOHAR with 6 floors.

How big is the land of MALATI- MANOHAR APT?

According to GharKundli's check of MahaRERA records (updated November 2026), MALATI- MANOHAR APT stands on 502 sq m of land (about 0.1 acres), with 502 sq m of sanctioned built-up area.

Where can I read reviews of MALATI- MANOHAR APT?

Google Maps has reviews of MALATI- MANOHAR APT written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is MALATI- MANOHAR APT?

MALATI- MANOHAR APT by SATISH MANOHAR DESHPANDE is in Gulmohar Nagar Mhasrul, Nashik (pincode 422004), Maharashtra, and is registered on MahaRERA as P51600003147, per GharKundli's check of MahaRERA records. Its boundaries filed there include COLONY ROAD, COLONY ROAD70.

How many homes are in MALATI- MANOHAR APT?

According to GharKundli's check of MahaRERA records (updated November 2026), MALATI- MANOHAR APT has 14 homes in 1 tower registered on MahaRERA.

When was MALATI- MANOHAR APT registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), MALATI- MANOHAR APT was registered on MahaRERA on 4 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on MALATI- MANOHAR APT?

No court cases are listed for MALATI- MANOHAR APT on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of MALATI- MANOHAR APT?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SATISH MANOHAR DESHPANDE.

Other projects in Nashik

All 93 projects in Meri Colony (422004) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.

MALATI- MANOHAR APT, Gulmohar Nagar Mhasrul, Nashik: MahaRERA status, possession & complaints