by CRYSTAL CONSTRUCTION COMPANY (Anjani) · Bachani Nagar, Mumbai 400097Also near Malad East, malad west, Kurar Village

What’s in the report? →

Possession date of Crystal Pride (MahaRERA P51800009735): 30 June 2026, moved from 31 December 2019 (78 months later), and it has already passed. It has 31 homes (1 BHK and 2 BHK, 305–593 sq ft carpet), 79% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800009735. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P51800009735, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (June 2026) has passed.

What do you want to know about Crystal Pride?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Crystal Pride has moved

  1. 31 December 2019

    Completion date given when the project was registered

  2. 30 December 2020

    Extended at the builder's request (MahaRERA application EXT51800003866)

    Reason the builder gave MahaRERA: “Carpet Area of Tenant and FSI increased due to change in DCR 2034 rules of SRA.”
  3. 30 June 2022

    Extended at the builder's request (MahaRERA application EXT51800009851)

    Reason the builder gave MahaRERA:
    “Stop of work due to Pandemic period of COVID-19 and change in rules of DCPR 2034 of SRA. Delay in receiving of permissions of extended F.S.I.like Amendments of plan, L.O.I, I.O.D. & C.C. All required permission now received and construction…” Read the full reason“Stop of work due to Pandemic period of COVID-19 and change in rules of DCPR 2034 of SRA. Delay in receiving of permissions of extended F.S.I.like Amendments of plan, L.O.I, I.O.D. & C.C. All required permission now received and construction is in full swing. But it will take another One Year to give Possession.”
  4. 30 June 2023

    Extended at the builder's request (MahaRERA application EXT51800012226)

    Reason the builder gave MahaRERA:
    “As per DCPR 2034 our FSI increased and we have started procedure of amended plan approval and obtaining of increased FSI commencement certificate. But due to delay in obtaining of permissions our site labours moved and this resulted slow in…” Read the full reason“As per DCPR 2034 our FSI increased and we have started procedure of amended plan approval and obtaining of increased FSI commencement certificate. But due to delay in obtaining of permissions our site labours moved and this resulted slow in construction work. Now we have arranged all and our construction is in full swing but it will take another one year to complete the project.”
  5. 30 June 2024

    Extended at the builder's request (MahaRERA application EXT51800017086)

    Reason the builder gave MahaRERA:
    “As per DCPR 2034 time taken for approvals & amendement of plan and amendedment in existing structure of Tenents constructed flats. Further we have also completed full RCC work alongwith part finishing work as per details submitted in projec…” Read the full reason“As per DCPR 2034 time taken for approvals & amendement of plan and amendedment in existing structure of Tenents constructed flats. Further we have also completed full RCC work alongwith part finishing work as per details submitted in projects details. Further It will take another 1 year to complete the project in all respect as only few finishing work remained to be completed.”
  6. 30 June 2025

    Extended at the builder's request (MahaRERA application EXT51800024559)

    Reason the builder gave MahaRERA: “RCC work completed. Finishing work partly finished and partly pending. Due to no sale of flat financial instability raised. Now everything is lineup and hopefully it shall be completed before extension period.”
  7. 30 June 2026

    Extended at the builder's request (MahaRERA application EA01092502486)

    Reason the builder gave MahaRERA:
    “Due to medical emergency of authorised partner of promoter, the work has been stopped and also due to no sale of flat financial instability raised. Now everything is lineup and hopefully it shall be completed before extension period coz onl…” Read the full reason“Due to medical emergency of authorised partner of promoter, the work has been stopped and also due to no sale of flat financial instability raised. Now everything is lineup and hopefully it shall be completed before extension period coz only few finishing works like lift, firefighting etc. remains pending.”

Source: Crystal Pride’s extension records on MahaRERA (P51800009735), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Crystal Pride

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800009735
Status
Lapsed (registration period ended)
Builder
CRYSTAL CONSTRUCTION COMPANY
Location
Bachani Nagar, Mumbai · 400097
Project type
Residential / Group Housing
Registered on
22 Aug 2017
Completion date at registration
December 2019
Latest completion date
June 2026
Delay so far
78 months
Homes
31
Sold or booked
79%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Crystal Pride, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
CRYSTAL PRIDE100%100%90%45%

Commencement certificate (CC), as filed on MahaRERA

  • CRYSTAL PRIDE: covers 16 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Crystal Pride every 1–2 months.

Crystal Pride: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK569 – 59328
1 BHK3053
Shops181 – 2712
  • Buildings: CRYSTAL PRIDE (19 floors, 33 units)
  • Land: 709 sq m (about 0.2 acres) · sanctioned built-up 1,889 sq m · recreational space 45 sq m
  • Boundaries filed include: KEDARMAL ROAD
  • Land, as filed: 401, 401/1 TO 401/25, 402 PART
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Geeta Developers (a group of 11 linked companies) has 18 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 9 finished, all within the promised date; 8 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA.

Read Google reviews of Crystal Pride →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Crystal Pride: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Crystal Pride

What is the possession date of Crystal Pride?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Crystal Pride in Bachani Nagar, Mumbai is 30 June 2026 — 78 months later than 31 December 2019, the date given at registration. That date has already passed.

The date has already moved 78 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Crystal Pride?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Crystal Pride's builder has filed on MahaRERA, the official one, is 30 June 2026, already 78 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Crystal Pride extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Crystal Pride's builder applied to MahaRERA to extend the completion date 6 times: to 30 December 2020, giving the reason "Carpet Area of Tenant and FSI increased due to change in DCR 2034 rules of SRA."; to 30 June 2022, giving the reason "Stop of work due to Pandemic period of COVID-19 and change in rules of DCPR 2034 of SRA. Delay in receiving of permissions of extended F.S.I.like Amendments of plan, L.O.I, I.O.D. & C.C. All required permission now received and construction is in full swing. But it will take another One Year to give Possession."; to 30 June 2023, giving the reason "As per DCPR 2034 our FSI increased and we have started procedure of amended plan approval and obtaining of increased FSI commencement certificate. But due to delay in obtaining of permissions our site labours moved and this resulted slow in construction work. Now we have arranged all and our construction is in full swing but it will take another one year to complete the project."; to 30 June 2024, giving the reason "As per DCPR 2034 time taken for approvals & amendement of plan and amendedment in existing structure of Tenents constructed flats. Further we have also completed full RCC work alongwith part finishing work as per details submitted in projects details. Further It will take another 1 year to complete the project in all respect as only few finishing work remained to be completed."; to 30 June 2025, giving the reason "RCC work completed. Finishing work partly finished and partly pending. Due to no sale of flat financial instability raised. Now everything is lineup and hopefully it shall be completed before extension period."; to 30 June 2026, giving the reason "Due to medical emergency of authorised partner of promoter, the work has been stopped and also due to no sale of flat financial instability raised. Now everything is lineup and hopefully it shall be completed before extension period coz only few finishing works like lift, firefighting etc. remains pending.".

What is the RERA number of Crystal Pride?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Crystal Pride in Bachani Nagar, Mumbai is P51800009735.

Is Crystal Pride registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Crystal Pride is registered as P51800009735 and its status is "Lapsed (registration period ended)".

What is the current construction status of Crystal Pride? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Crystal Pride's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on CRYSTAL PRIDE is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.

Does Crystal Pride have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Crystal Pride safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Crystal Pride is registered on MahaRERA as P51800009735, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 78 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Crystal Pride?

Crystal Pride isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Crystal Pride are 305 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Crystal Pride?

For a flat in Crystal Pride (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Crystal Pride received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Crystal Pride isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 June 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Crystal Pride?

According to GharKundli's check of MahaRERA records (updated October 2026), Crystal Pride's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 June 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Crystal Pride uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Crystal Pride was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Crystal Pride's possession date changes?

The latest dates are on Crystal Pride's MahaRERA page (P51800009735). GharKundli's Kundli Watch sends a free WhatsApp update on Crystal Pride every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Crystal Pride have?

According to GharKundli's check of MahaRERA records (updated October 2026), Crystal Pride has one building filed: CRYSTAL PRIDE with 19 floors and 33 units.

What are the flat sizes (carpet area) in Crystal Pride?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Crystal Pride: 2 BHK: 569 to 593 sq ft carpet (28 homes); 1 BHK: 305 sq ft carpet (3 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Crystal Pride?

According to GharKundli's check of MahaRERA records (updated October 2026), Crystal Pride stands on 709 sq m of land (about 0.2 acres), with 1,889 sq m of sanctioned built-up area and 45 sq m of recreational open space.

What is the track record of Crystal Pride's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Geeta Developers (a group of 11 linked companies) has 18 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 9 finished, all within the promised date; 8 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Crystal Pride?

Google Maps has reviews of Crystal Pride written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Crystal Pride?

Crystal Pride by CRYSTAL CONSTRUCTION COMPANY (Anjani) is in Bachani Nagar, Mumbai, pincode 400097 (near Malad East, malad west, Kurar Village), Maharashtra, and is registered on MahaRERA as P51800009735, per GharKundli's check of MahaRERA records. Its boundaries filed there include KEDARMAL ROAD. Its land is filed as 401, 401/1 TO 401/25, 402 PART. GharKundli lists all 195 MahaRERA projects in Malad East (400097).

How many flats are in Crystal Pride, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Crystal Pride has 31 homes in 1 tower registered on MahaRERA, and 79% of them are sold or booked.

When was Crystal Pride registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Crystal Pride was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.

Does Crystal Pride have any legal issues or court cases?

No court cases are listed for Crystal Pride on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Crystal Pride?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is CRYSTAL CONSTRUCTION COMPANY, the company Anjani files this project under, which has 1 other project registered on MahaRERA.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in Borivali

All 195 projects in Malad East (400097) →

Other projects by CRYSTAL CONSTRUCTION COMPANY

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.