Skip to content
GharKundli

Hitendra Dhamm Shabha Co-operative Housing Society Limited

by CRYSTAL CONSTRUCTION COMPANY (Anjani) · Goreagoan west, Mumbai 400104Also near Goregaon West, Kalanagar, Andheri East

What’s in the report? →

Possession date of Hitendra Dhamm Shabha Co-operative Housing Society Limited (MahaRERA P51800049489): 30 January 2027. It has 72 homes (1 BHK, 2 BHK and 3 BHK, 428–769 sq ft carpet), 77% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800049489, and currently active. Its completion date is now January 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for P51800049489, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Hitendra Dhamm Shabha Co-operative Housing Society Limited?

5 court cases MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Hitendra Dhamm Shabha Co-operative Housing Society Limited has moved

  1. 30 September 2026

    Completion date given when the project was registered

  2. 30 January 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Hitendra Dhamm Shabha Co-operative Housing Society Limited’s extension records on MahaRERA (P51800049489), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Hitendra Dhamm Shabha Co-operative Housing Society Limited

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 5 court cases, and how it ended
  • Construction pace against the January 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800049489
Status
Registered and active
Builder
CRYSTAL CONSTRUCTION COMPANY
Location
Goreagoan west, Mumbai · 400104
Project type
Residential / Group Housing
Registered on
15 Feb 2023
Completion date at registration
September 2026
Latest completion date
January 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
72
Sold or booked
77%
Towers
1
Complaints on MahaRERA
0
Court cases listed
5
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Hitendra Dhamm Shabha Co-operative Housing Society Limited, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Hitendra Dhamm Shabha Co-operative Housing Society Limited100%100%100%50%

Commencement certificate (CC), as filed on MahaRERA

  • Hitendra Dhamm Shabha Co-operative Housing Society Limited: covers 22 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Hitendra Dhamm Shabha Co-operative Housing Society Limited every 1–2 months.

Hitendra Dhamm Shabha Co-operative Housing Society Limited: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK569 – 64832
1 BHK42820
3 BHK76920
Shops243 – 3614

The builder’s record and reviews

Geeta Developers (a group of 11 linked companies) has 18 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 9 finished, all within the promised date; 8 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA.

Read Google reviews of Hitendra Dhamm Shabha Co-operative Housing Society Limited →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Hitendra Dhamm Shabha Co-operative Housing Society Limited: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Hitendra Dhamm Shabha Co-operative Housing Society Limited

What is the possession date of Hitendra Dhamm Shabha Co-operative Housing Society Limited?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Hitendra Dhamm Shabha Co-operative Housing Society Limited in Goreagoan west, Mumbai is 30 January 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Hitendra Dhamm Shabha Co-operative Housing Society Limited?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Hitendra Dhamm Shabha Co-operative Housing Society Limited's builder has filed on MahaRERA, the official one, is 30 January 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Hitendra Dhamm Shabha Co-operative Housing Society Limited?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Hitendra Dhamm Shabha Co-operative Housing Society Limited in Goreagoan west, Mumbai is P51800049489.

Is Hitendra Dhamm Shabha Co-operative Housing Society Limited registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Hitendra Dhamm Shabha Co-operative Housing Society Limited is registered as P51800049489 and its status is "Registered and active".

What is the current construction status of Hitendra Dhamm Shabha Co-operative Housing Society Limited? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Hitendra Dhamm Shabha Co-operative Housing Society Limited's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Hitendra Dhamm Shabha Co-operative Housing Society Limited is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Hitendra Dhamm Shabha Co-operative Housing Society Limited have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Hitendra Dhamm Shabha Co-operative Housing Society Limited safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Hitendra Dhamm Shabha Co-operative Housing Society Limited is registered on MahaRERA as P51800049489, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Hitendra Dhamm Shabha Co-operative Housing Society Limited?

Hitendra Dhamm Shabha Co-operative Housing Society Limited is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Hitendra Dhamm Shabha Co-operative Housing Society Limited are 428 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Hitendra Dhamm Shabha Co-operative Housing Society Limited?

For a flat in Hitendra Dhamm Shabha Co-operative Housing Society Limited (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Hitendra Dhamm Shabha Co-operative Housing Society Limited received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Hitendra Dhamm Shabha Co-operative Housing Society Limited is still under construction, with 30 January 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Hitendra Dhamm Shabha Co-operative Housing Society Limited a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Hitendra Dhamm Shabha Co-operative Housing Society Limited is a redevelopment: 20 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has Hitendra Dhamm Shabha Co-operative Housing Society Limited uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Hitendra Dhamm Shabha Co-operative Housing Society Limited was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Hitendra Dhamm Shabha Co-operative Housing Society Limited's possession date changes?

The latest dates are on Hitendra Dhamm Shabha Co-operative Housing Society Limited's MahaRERA page (P51800049489). GharKundli's Kundli Watch sends a free WhatsApp update on Hitendra Dhamm Shabha Co-operative Housing Society Limited every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Hitendra Dhamm Shabha Co-operative Housing Society Limited have?

According to GharKundli's check of MahaRERA records (updated October 2026), Hitendra Dhamm Shabha Co-operative Housing Society Limited has one building filed: Hitendra Dhamm Shabha Co-operative Housing Society Limited with 25 floors and 76 units.

What are the flat sizes (carpet area) in Hitendra Dhamm Shabha Co-operative Housing Society Limited?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Hitendra Dhamm Shabha Co-operative Housing Society Limited: 2 BHK: 569 to 648 sq ft carpet (32 homes); 1 BHK: 428 sq ft carpet (20 homes); 3 BHK: 769 sq ft carpet (20 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Hitendra Dhamm Shabha Co-operative Housing Society Limited?

According to GharKundli's check of MahaRERA records (updated October 2026), Hitendra Dhamm Shabha Co-operative Housing Society Limited stands on 756 sq m of land (about 0.2 acres), with 4,634 sq m of sanctioned built-up area.

What is the track record of Hitendra Dhamm Shabha Co-operative Housing Society Limited's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Geeta Developers (a group of 11 linked companies) has 18 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 9 finished, all within the promised date; 8 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Hitendra Dhamm Shabha Co-operative Housing Society Limited?

Google Maps has reviews of Hitendra Dhamm Shabha Co-operative Housing Society Limited written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Hitendra Dhamm Shabha Co-operative Housing Society Limited?

Hitendra Dhamm Shabha Co-operative Housing Society Limited by CRYSTAL CONSTRUCTION COMPANY (Anjani) is in Goreagoan west, Mumbai, pincode 400104 (near Goregaon West, Kalanagar, Andheri East), Maharashtra, and is registered on MahaRERA as P51800049489, per GharKundli's check of MahaRERA records. Its land is filed as CTS No 217 part. GharKundli lists all 183 MahaRERA projects in Goregaon West (400104).

How many flats are in Hitendra Dhamm Shabha Co-operative Housing Society Limited, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Hitendra Dhamm Shabha Co-operative Housing Society Limited has 72 homes in 1 tower registered on MahaRERA, and 77% of them are sold or booked.

When was Hitendra Dhamm Shabha Co-operative Housing Society Limited registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Hitendra Dhamm Shabha Co-operative Housing Society Limited was registered on MahaRERA on 15 February 2023. GharKundli did not find a title report on the land on file there.

Does Hitendra Dhamm Shabha Co-operative Housing Society Limited have any legal issues or court cases?

5 court cases are listed for Hitendra Dhamm Shabha Co-operative Housing Society Limited on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what each case is about →

Who is the builder / developer of Hitendra Dhamm Shabha Co-operative Housing Society Limited?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is CRYSTAL CONSTRUCTION COMPANY, the company Anjani files this project under, which has 1 other project registered on MahaRERA.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in Goregaon West (400104)

All 183 projects in Goregaon West (400104) →

Other projects by CRYSTAL CONSTRUCTION COMPANY

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.