TIMES SQUARE
by TALWARE BUILDERS PRIVATE LIMITED · Thatte Nagar, NashikAlso near Kulkarni Garden, Gole Colony, M G Road
Possession date of TIMES SQUARE: 30 June 2030, moved from 11 September 2023 (81 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51600014166, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about TIMES SQUARE?
How the possession date of TIMES SQUARE has moved
11 September 2023
Completion date given when the project was registered
30 June 2030
Extended at the builder's request (MahaRERA application EA25062621540)
Reason the builder gave MahaRERA: “There were liquidity issues and delays in funding. Labour and material shortages, along with disruptions in supply chains and workforce availability, are impacting construction timelines.”
Source: TIMES SQUARE’s extension records on MahaRERA (P51600014166), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on TIMES SQUARE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2030 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51600014166
- Status
- Registered and active
- Builder
- TALWARE BUILDERS PRIVATE LIMITED
- Location
- Thatte Nagar, Nashik · 422001
- Project type
- Commercial
- Registered on
- 10 Nov 2017
- Completion date at registration
- September 2023
- Latest completion date
- June 2030
- Delay so far
- 81 months
- Homes
- 0
- Sold or booked
- 4%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of TIMES SQUARE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| TIMES SQUARE | 100% | 7% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- TIMES SQUARE: covers 2 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on TIMES SQUARE every month.
TIMES SQUARE: buildings, flats and land, as filed on MahaRERA
- Buildings: TIMES SQUARE (5 floors, 55 units)
- Car parking: 15 open
- Land: 3,497 sq m (about 0.9 acres) · sanctioned built-up 2,984 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of TIMES SQUARE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
TIMES SQUARE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about TIMES SQUARE
What is the possession date of TIMES SQUARE?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for TIMES SQUARE in Thatte Nagar, Nashik is 30 June 2030 — 81 months later than 11 September 2023, the date given at registration.
Is the builder's possession date different from the MahaRERA date for TIMES SQUARE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date TIMES SQUARE's builder has filed on MahaRERA, the official one, is 30 June 2030, already 81 months later than the 11 September 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of TIMES SQUARE extended?
According to GharKundli's check of MahaRERA records (updated October 2026), TIMES SQUARE's builder applied to MahaRERA to extend the completion date once: to 30 June 2030, giving the reason "There were liquidity issues and delays in funding. Labour and material shortages, along with disruptions in supply chains and workforce availability, are impacting construction timelines.".
What is the RERA number of TIMES SQUARE?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of TIMES SQUARE in Thatte Nagar, Nashik is P51600014166.
Is TIMES SQUARE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), TIMES SQUARE is registered as P51600014166 and its status is "Registered and active".
What is the construction status of TIMES SQUARE?
According to GharKundli's check of MahaRERA records (updated October 2026), TIMES SQUARE's status on MahaRERA is "Registered and active". As filed by the builder, slab work on TIMES SQUARE is 7% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does TIMES SQUARE have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is TIMES SQUARE safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), TIMES SQUARE is registered on MahaRERA as P51600014166, its completion date has moved 81 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if TIMES SQUARE's possession date changes?
The latest dates are on TIMES SQUARE's MahaRERA page (P51600014166). GharKundli's Kundli Watch sends a free WhatsApp update on TIMES SQUARE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does TIMES SQUARE have?
According to GharKundli's check of MahaRERA records (updated October 2026), TIMES SQUARE has one building filed: TIMES SQUARE with 5 floors and 55 units.
How much parking does TIMES SQUARE have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 15 open car parking spaces for TIMES SQUARE.
How big is the land of TIMES SQUARE?
According to GharKundli's check of MahaRERA records (updated October 2026), TIMES SQUARE stands on 3,497 sq m of land (about 0.9 acres), with 2,984 sq m of sanctioned built-up area.
Where can I read reviews of TIMES SQUARE?
Google Maps has reviews of TIMES SQUARE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is TIMES SQUARE?
TIMES SQUARE by TALWARE BUILDERS PRIVATE LIMITED is in Thatte Nagar, Nashik (pincode 422001), near Kulkarni Garden, Gole Colony, M G Road, Maharashtra, and is registered on MahaRERA as P51600014166, per GharKundli's check of MahaRERA records.
How many homes are in TIMES SQUARE?
According to GharKundli's check of MahaRERA records (updated October 2026), TIMES SQUARE has 0 homes in 1 tower registered on MahaRERA, and 4% of them are sold or booked.
When was TIMES SQUARE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), TIMES SQUARE was registered on MahaRERA on 10 November 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on TIMES SQUARE?
No court cases are listed for TIMES SQUARE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of TIMES SQUARE?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is TALWARE BUILDERS PRIVATE LIMITED, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of TIMES SQUARE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2030 in Nashik →
Other projects in Nashik
- Fortunes Emerald Park
- Laxmi Commercial Complex
- YUNUS RESIDENCY
- SHUBHSANKALP CO-OPERATIVE HOUSING SOCIETY LIMITED
- SHREE VISHVA
- SHIV KUNJ
- Quillion Residencies at Quillion Park - Phase 2
- SARA SERENITY APARTMENT
Other projects by TALWARE BUILDERS PRIVATE LIMITED
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.