Skip to content
GharKundli

BHUJARI TOWER

by SHREE MAHALAXMI BUILDERS & DEVELOPERS · Igatpuri, Nashik

Possession: BHUJARI TOWER is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51600015404. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about BHUJARI TOWER?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of BHUJARI TOWER has moved

  1. 7 May 2019

    Completion date given when the project was registered

  2. 31 January 2023

    Extended at the builder's request (MahaRERA application EXT51600011731)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of the project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of the project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid-19. We have consent of 55.56% allottees for purpose of extension of RERA registration period of the said project. We have received Occupancy Certificate on 27th October 2021. We have completed the closure process as well. We request you to grant us extension in order to comply with the Closure Process of MahaRERA.”

Source: BHUJARI TOWER’s extension records on MahaRERA (P51600015404), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on BHUJARI TOWER

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the January 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51600015404
Status
Completed
Builder
SHREE MAHALAXMI BUILDERS & DEVELOPERS
Location
Igatpuri, Nashik · 422403
Project type
Residential / Group Housing
Registered on
21 Feb 2018
Completion date at registration
May 2019
Latest completion date
January 2023
Delay so far
44 months
Homes
34
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of BHUJARI TOWER, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BHUJARI TOWER100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on BHUJARI TOWER every month.

BHUJARI TOWER: buildings, flats and land, as filed on MahaRERA

  • Buildings: BHUJARI TOWER (6 floors)
  • Land: 513 sq m (about 0.1 acres) · sanctioned built-up 1,026 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of BHUJARI TOWER →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

BHUJARI TOWER: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about BHUJARI TOWER

What is the possession date of BHUJARI TOWER?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for BHUJARI TOWER in Igatpuri, Nashik is 31 January 2023 — 44 months later than 7 May 2019, the date given at registration.

Is the builder's possession date different from the MahaRERA date for BHUJARI TOWER?

Builders and listing sites often quote an earlier "target" date for handover. The completion date BHUJARI TOWER's builder has filed on MahaRERA, the official one, is 31 January 2023, already 44 months later than the 7 May 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of BHUJARI TOWER extended?

According to GharKundli's check of MahaRERA records (updated November 2026), BHUJARI TOWER's builder applied to MahaRERA to extend the completion date once: to 31 January 2023, giving the reason "In accordance with circular no 28, we hereby apply for extension of the project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid-19. We have consent of 55.56% allottees for purpose of extension of RERA registration period of the said project. We have received Occupancy Certificate on 27th October 2021. We have completed the closure process as well. We request you to grant us extension in order to comply with the Closure Process of MahaRERA.".

What is the RERA number of BHUJARI TOWER?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of BHUJARI TOWER in Igatpuri, Nashik is P51600015404.

Is BHUJARI TOWER registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), BHUJARI TOWER is registered as P51600015404 and its status is "Completed".

What is the construction status of BHUJARI TOWER?

According to GharKundli's check of MahaRERA records (updated November 2026), BHUJARI TOWER's status on MahaRERA is "Completed". As filed by the builder, slab work on BHUJARI TOWER is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does BHUJARI TOWER have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is BHUJARI TOWER safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), BHUJARI TOWER is registered on MahaRERA as P51600015404, its MahaRERA status is "Completed", its completion date has moved 44 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if BHUJARI TOWER's possession date changes?

The latest dates are on BHUJARI TOWER's MahaRERA page (P51600015404). GharKundli's Kundli Watch sends a free WhatsApp update on BHUJARI TOWER every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does BHUJARI TOWER have?

According to GharKundli's check of MahaRERA records (updated November 2026), BHUJARI TOWER has one building filed: BHUJARI TOWER with 6 floors.

How big is the land of BHUJARI TOWER?

According to GharKundli's check of MahaRERA records (updated November 2026), BHUJARI TOWER stands on 513 sq m of land (about 0.1 acres), with 1,026 sq m of sanctioned built-up area.

Where can I read reviews of BHUJARI TOWER?

Google Maps has reviews of BHUJARI TOWER written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is BHUJARI TOWER?

BHUJARI TOWER by SHREE MAHALAXMI BUILDERS & DEVELOPERS is in Igatpuri, Nashik (pincode 422403), Maharashtra, and is registered on MahaRERA as P51600015404, per GharKundli's check of MahaRERA records.

How many homes are in BHUJARI TOWER?

According to GharKundli's check of MahaRERA records (updated November 2026), BHUJARI TOWER has 34 homes in 1 tower registered on MahaRERA.

When was BHUJARI TOWER registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), BHUJARI TOWER was registered on MahaRERA on 21 February 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on BHUJARI TOWER?

No court cases are listed for BHUJARI TOWER on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of BHUJARI TOWER?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHREE MAHALAXMI BUILDERS & DEVELOPERS.

Other projects in pincode 422403

All 29 projects in Igatpuri (422403) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.