PARK BELLAGIO
by Prabhav Reality & Infrastructure Private Limited · Igatpuri, Nashik
Possession date of PARK BELLAGIO: 30 April 2027, moved from 30 October 2024 (26 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51600033061, and currently active. Its completion date has moved from October 2024 to April 2027: 26 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about PARK BELLAGIO?
How the possession date of PARK BELLAGIO has moved
30 October 2024
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EXT51600028114)
Reason the builder gave MahaRERA: “Since there are multiple units purchse by in person the proper bifurcation with consent is given in the Format B uploaded below alog with the Index II of all such flats.”
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: PARK BELLAGIO’s extension records on MahaRERA (P51600033061), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on PARK BELLAGIO
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 1 court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51600033061
- Status
- Registered and active
- Builder
- Prabhav Reality & Infrastructure Private Limited
- Location
- Igatpuri, Nashik · 422403
- Project type
- Residential / Group Housing
- Registered on
- 3 Feb 2022
- Completion date at registration
- October 2024
- Latest completion date
- April 2027
- Delay so far
- 26 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 132
- Towers
- 8
- Complaints on MahaRERA
- 1
- Court cases listed
- 1
- Title report on file
- Not found
Construction progress of PARK BELLAGIO, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| ASTER | 0% | 0% | 0% | 0% |
| PETUNIA A WING | 0% | 0% | 0% | 0% |
| PETUNIA B WING | 0% | 0% | 0% | 0% |
| BUNGALOW 301 | 0% | 0% | 0% | 0% |
| BUNGALOW 302 | 0% | 0% | 0% | 0% |
| BUNGALOW 303 | 0% | 0% | 0% | 0% |
| BUNGALOW 304 | 0% | 0% | 0% | 0% |
| BUNGALOW 305 | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on PARK BELLAGIO every month.
PARK BELLAGIO: buildings, flats and land, as filed on MahaRERA
- Buildings: ASTER (8 floors) · PETUNIA A WING (8 floors) · PETUNIA B WING (8 floors) · BUNGALOW 301 (4 floors) · BUNGALOW 302 (4 floors) · BUNGALOW 303 (4 floors) · BUNGALOW 304 (4 floors) · BUNGALOW 305 (4 floors)
- Land: 4,485 sq m (about 1.1 acres) · sanctioned built-up 6,006 sq m
- Boundaries filed include: NATIONAL HIGHWAY NO 3
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of PARK BELLAGIO →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
PARK BELLAGIO: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about PARK BELLAGIO
What is the possession date of PARK BELLAGIO?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for PARK BELLAGIO in Igatpuri, Nashik is 30 April 2027 — 26 months later than 30 October 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for PARK BELLAGIO?
Builders and listing sites often quote an earlier "target" date for handover. The completion date PARK BELLAGIO's builder has filed on MahaRERA, the official one, is 30 April 2027, already 26 months later than the 30 October 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of PARK BELLAGIO extended?
According to GharKundli's check of MahaRERA records (updated October 2026), PARK BELLAGIO's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "Since there are multiple units purchse by in person the proper bifurcation with consent is given in the Format B uploaded below alog with the Index II of all such flats.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of PARK BELLAGIO?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of PARK BELLAGIO in Igatpuri, Nashik is P51600033061.
Is PARK BELLAGIO registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), PARK BELLAGIO is registered as P51600033061 and its status is "Registered and active".
What is the construction status of PARK BELLAGIO?
According to GharKundli's check of MahaRERA records (updated October 2026), PARK BELLAGIO's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 8 towers. GharKundli's full report compares construction progress with the deadline.
Does PARK BELLAGIO have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is PARK BELLAGIO safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), PARK BELLAGIO is registered on MahaRERA as P51600033061, its completion date has moved 26 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if PARK BELLAGIO's possession date changes?
The latest dates are on PARK BELLAGIO's MahaRERA page (P51600033061). GharKundli's Kundli Watch sends a free WhatsApp update on PARK BELLAGIO every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does PARK BELLAGIO have?
According to GharKundli's check of MahaRERA records (updated October 2026), PARK BELLAGIO has 8 buildings filed: ASTER with 8 floors; PETUNIA A WING with 8 floors; PETUNIA B WING with 8 floors; BUNGALOW 301 with 4 floors; BUNGALOW 302 with 4 floors; BUNGALOW 303 with 4 floors; and 2 more.
How big is the land of PARK BELLAGIO?
According to GharKundli's check of MahaRERA records (updated October 2026), PARK BELLAGIO stands on 4,485 sq m of land (about 1.1 acres), with 6,006 sq m of sanctioned built-up area.
Where can I read reviews of PARK BELLAGIO?
Google Maps has reviews of PARK BELLAGIO written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is PARK BELLAGIO?
PARK BELLAGIO by Prabhav Reality & Infrastructure Private Limited is in Igatpuri, Nashik (pincode 422403), Maharashtra, and is registered on MahaRERA as P51600033061, per GharKundli's check of MahaRERA records. Its boundaries filed there include NATIONAL HIGHWAY NO 3.
How many homes are in PARK BELLAGIO?
According to GharKundli's check of MahaRERA records (updated October 2026), PARK BELLAGIO has 132 homes in 8 towers registered on MahaRERA.
When was PARK BELLAGIO registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), PARK BELLAGIO was registered on MahaRERA on 3 February 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on PARK BELLAGIO?
1 court case is listed for PARK BELLAGIO on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of PARK BELLAGIO?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Prabhav Reality & Infrastructure Private Limited.
Check it yourself on MahaRERA
- How to check the possession date of PARK BELLAGIO
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Nashik →
Other projects in pincode 422403
- MANOMAY NATURES PARADIZE
- ANANDVANN PHASE II
- MOONHOUSE CELEBRATIONS
- INDO ASIAN SIGNATURE
- Rosewood - I J and K Wing
- United Infinity
- WESTERN HILLS
- Mysty Heaven
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.