MOONHOUSE CELEBRATIONS

by MOONHOUSE LIFESTYLE LLP · Igatpuri, NashikAlso near Ghoti

Possession date of MOONHOUSE CELEBRATIONS: 31 December 2025, moved from 31 December 2024 (12 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51600050554. Status: Lapsed (registration period ended). 12 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (December 2025) has passed.

What do you want to know about MOONHOUSE CELEBRATIONS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of MOONHOUSE CELEBRATIONS has moved

  1. 31 December 2024

    Completion date given when the project was registered

  2. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51600028198)

    Reason the builder gave MahaRERA: “Delay”

Source: MOONHOUSE CELEBRATIONS’s extension records on MahaRERA (P51600050554), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on MOONHOUSE CELEBRATIONS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 12 complaints, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51600050554
Status
Lapsed (registration period ended)
Builder
MOONHOUSE LIFESTYLE LLP
Location
Igatpuri, Nashik · 422403
Project type
Others
Registered on
21 Apr 2023
Completion date at registration
December 2024
Latest completion date
December 2025
Delay so far
12 months
Homes
12
Towers
12
Complaints on MahaRERA
12
Court cases listed
0
Title report on file
Not found

Construction progress of MOONHOUSE CELEBRATIONS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
B-03100%100%50%0%
B-04100%100%50%0%
B-05100%100%50%0%
B-06100%100%50%0%
B-07100%100%50%0%
B-08100%100%50%0%
B-09100%100%50%0%
B-10100%100%50%0%
B-11100%100%50%30%
B-12100%100%50%30%
B-13100%100%30%0%
B-14100%100%30%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on MOONHOUSE CELEBRATIONS every month.

MOONHOUSE CELEBRATIONS: buildings, flats and land, as filed on MahaRERA

  • Buildings: B-03 (2 floors) · B-04 (1 floors) · B-05 (1 floors) · B-06 (1 floors) · B-07 (1 floors) · B-08 (1 floors) · B-09 (1 floors) · B-10 (1 floors) · and 4 more
  • Land: 2,313 sq m (about 0.6 acres) · sanctioned built-up 2,241 sq m · recreational space 1,124 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of MOONHOUSE CELEBRATIONS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

MOONHOUSE CELEBRATIONS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about MOONHOUSE CELEBRATIONS

What is the possession date of MOONHOUSE CELEBRATIONS?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for MOONHOUSE CELEBRATIONS in Igatpuri, Nashik is 31 December 2025 — 12 months later than 31 December 2024, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for MOONHOUSE CELEBRATIONS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date MOONHOUSE CELEBRATIONS's builder has filed on MahaRERA, the official one, is 31 December 2025, already 12 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of MOONHOUSE CELEBRATIONS extended?

According to GharKundli's check of MahaRERA records (updated October 2026), MOONHOUSE CELEBRATIONS's builder applied to MahaRERA to extend the completion date once: to 31 December 2025, giving the reason "Delay".

What is the RERA number of MOONHOUSE CELEBRATIONS?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of MOONHOUSE CELEBRATIONS in Igatpuri, Nashik is P51600050554.

Is MOONHOUSE CELEBRATIONS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), MOONHOUSE CELEBRATIONS is registered as P51600050554 and its status is "Lapsed (registration period ended)".

What is the construction status of MOONHOUSE CELEBRATIONS?

According to GharKundli's check of MahaRERA records (updated October 2026), MOONHOUSE CELEBRATIONS's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 12 towers. GharKundli's full report compares construction progress with the deadline.

Does MOONHOUSE CELEBRATIONS have complaints on MahaRERA?

12 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is MOONHOUSE CELEBRATIONS safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), MOONHOUSE CELEBRATIONS is registered on MahaRERA as P51600050554, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and 12 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if MOONHOUSE CELEBRATIONS's possession date changes?

The latest dates are on MOONHOUSE CELEBRATIONS's MahaRERA page (P51600050554). GharKundli's Kundli Watch sends a free WhatsApp update on MOONHOUSE CELEBRATIONS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does MOONHOUSE CELEBRATIONS have?

According to GharKundli's check of MahaRERA records (updated October 2026), MOONHOUSE CELEBRATIONS has 12 buildings filed: B-03 with 2 floors; B-04 with 1 floors; B-05 with 1 floors; B-06 with 1 floors; B-07 with 1 floors; B-08 with 1 floors; and 6 more.

How big is the land of MOONHOUSE CELEBRATIONS?

According to GharKundli's check of MahaRERA records (updated October 2026), MOONHOUSE CELEBRATIONS stands on 2,313 sq m of land (about 0.6 acres), with 2,241 sq m of sanctioned built-up area and 1,124 sq m of recreational open space.

Where can I read reviews of MOONHOUSE CELEBRATIONS?

Google Maps has reviews of MOONHOUSE CELEBRATIONS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 12 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is MOONHOUSE CELEBRATIONS?

MOONHOUSE CELEBRATIONS by MOONHOUSE LIFESTYLE LLP is in Igatpuri, Nashik (pincode 422403), near Ghoti, Maharashtra, and is registered on MahaRERA as P51600050554, per GharKundli's check of MahaRERA records.

How many homes are in MOONHOUSE CELEBRATIONS?

According to GharKundli's check of MahaRERA records (updated October 2026), MOONHOUSE CELEBRATIONS has 12 homes in 12 towers registered on MahaRERA.

When was MOONHOUSE CELEBRATIONS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), MOONHOUSE CELEBRATIONS was registered on MahaRERA on 21 April 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on MOONHOUSE CELEBRATIONS?

No court cases are listed for MOONHOUSE CELEBRATIONS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of MOONHOUSE CELEBRATIONS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MOONHOUSE LIFESTYLE LLP.

Other projects in pincode 422403

All 29 projects in Igatpuri (422403) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.